Decom m issioning of the Danish 5 MW research reactor DR2 by - - PowerPoint PPT Presentation

decom m issioning of the danish 5 mw research reactor dr2
SMART_READER_LITE
LIVE PREVIEW

Decom m issioning of the Danish 5 MW research reactor DR2 by - - PowerPoint PPT Presentation

Decom m issioning of the Danish 5 MW research reactor DR2 by Niels Strufe and Kurt Lauridsen Danish Decommissioning at Nordic Nuclear Safety Research (NKS) Decommissioning Conference, 14th - 16th September 2010, Studsvik, Sweden Aerial


slide-1
SLIDE 1

Decom m issioning of the Danish 5 MW research reactor DR2

by Niels Strufe and Kurt Lauridsen Danish Decommissioning at Nordic Nuclear Safety Research (NKS) Decommissioning Conference, 14th - 16th September 2010, Studsvik, Sweden

slide-2
SLIDE 2

Aerial photograph of Risø National Laboratory. Reactor DR 2 can be seen in the foreground. DR 3 is situated at the left hand side of the peninsula. DR 1 is hidden to the far right in the picture.

slide-3
SLIDE 3

DR 2

slide-4
SLIDE 4

DR 2

  • Reactor type: Light-water

cooled and moderated pool-type.

  • Max. output: 5 MW.
  • I n service: 1958-1975

(subsequently brought to state of ”safe enclosure”).

  • Prim ary activity: Physics

research and production of isotopes.

slide-5
SLIDE 5

DR 2

slide-6
SLIDE 6

Decommissioning of DR 2

  • April 2006: funding granted.
  • May-December 2006: removal of

irradiation facilities and beam tubes.

  • January–March 2007: removal of

thermal column and grid plate.

  • April-December 2007: demolition of

concrete reactor block.

  • 2008: clearance measurements.
  • Final report approved by the nuclear

supervisory authorities 30th April 2009

slide-7
SLIDE 7

Rem oval of irradiation facilities and beam tubes

  • Removal and dismantling and cutting
  • f experimental tubes ("S"-, "R"-, "T"-

and "B"-tubes)

slide-8
SLIDE 8

S-tube

B- tube

slide-9
SLIDE 9

Rem oval of irradiation facilities and beam tubes

slide-10
SLIDE 10

Rem oving the S-5 tube

slide-11
SLIDE 11

Rem oving the B-5 plug

slide-12
SLIDE 12

Rem oval of therm al colum n and grid plate

slide-13
SLIDE 13

Rem oval of therm al colum n and grid plate The works included:

  • Removal of graphite
  • Removal of Lead nose
  • Removal of grid plate
slide-14
SLIDE 14

Rem oval of graphite

Measurement of radiation level

slide-15
SLIDE 15

Rem oval of graphite

slide-16
SLIDE 16

Rem oval of Lead nose

Plasma cutting of the lead nose

slide-17
SLIDE 17

Rem oval of Lead nose

Lead nose cut out and placed in container

slide-18
SLIDE 18

Rem oval of grid plate

Sketch of the aluminium grid plate Stainless steel bolts Cutting line points

slide-19
SLIDE 19

Rem oval of grid plate

Grid plate being cut loose by use of plasma cutting

slide-20
SLIDE 20

Dem olition of the biological shield

  • Characterisation of the activity

content in the concrete

  • Demolition of concrete reactor block
slide-21
SLIDE 21

Characterisation of the activity content in the concrete

slide-22
SLIDE 22

The dem olition process

  • In order to prevent spreading of contamination to the

building and the environment a tent was built around the reactor block. The tent was supplied with a filtered ventilation

  • Demolition of concrete by use of a hydraulic hammer

mounted on a remote operated ’Brokk’ demolition robot

  • Demolition of other materials by use of

Plasma cutter (steel, aluminium) Dry wire cutting for cutting free the horizontal beam tubes (layers of concrete, steel, aluminium, lead) Saw, handheld (aluminium tank) Flame cutter (steel, pipes)

slide-23
SLIDE 23

Principle sketch of the dem olition site

slide-24
SLIDE 24

Dem olition of concrete by use of a hydraulic ham m er m ounted on a rem ote

  • perated ’Brokk’ dem olition robot
slide-25
SLIDE 25

Dem olition of active parts

slide-26
SLIDE 26

Dem olition com pleted

slide-27
SLIDE 27

Clearance m easurem ents

slide-28
SLIDE 28

Change of end state for the decom m issioning

The project ended with control measurements documenting that no activity from the operation from DR 2 was left, except some contamination in a pipe that is cast into the bearing construction. The removal of this pipe and demolition of the building will wait until the final stages of the overall decommissioning project at Risø.

slide-29
SLIDE 29

Thank you

Report available by download: http://dekom.dk/ddcom_en/