WINNER http://communitymeeting.ocps.net/ Hidden Oaks Elementary - - PowerPoint PPT Presentation

winner
SMART_READER_LITE
LIVE PREVIEW

WINNER http://communitymeeting.ocps.net/ Hidden Oaks Elementary - - PowerPoint PPT Presentation

Orange County Public Schools Welcome! Please sign in on your mobile device: WINNER http://communitymeeting.ocps.net/ Hidden Oaks Elementary School 40% Construction Community Meeting February 5, 2018 Superintendent Dr. Barbara Jenkins


slide-1
SLIDE 1

Orange County Public Schools

WINNER

Hidden Oaks Elementary School 40% Construction Community Meeting February 5, 2018

Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/

Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris

slide-2
SLIDE 2

Orange County Public Schools Orange County Public Schools Hidden Oaks Elementary School 40% Construction Update Meeting Agenda

February 5, 2018: Hidden Oaks Elementary School Media Center, 6:00pm

  • Welcome – Daryl Flynn, School Board Member
  • Introductions – Lauren Roth, Facilities Meeting Organizer
  • Project Update – Architect: Harvard Jolly Architects

Construction Manager: Core Construction Services of Florida, LLC

  • Questions and Answers
  • Adjournment
slide-3
SLIDE 3

Orange County Public Schools

Media Center Admin Multi Purpose

CEP

Kitchen Bus Loop Parent Pick Up Play Field Hardcourt Future Portables Dry Retention Pond Tot Youth Covered Play Suburban Dr Service

Bikes

Master Site Plan

Project Data

Capacity 650 Student Stations Building Area 76,796 Gross SF Parking 120 Spaces Car Queuing 122 Cars Bus Canopy 151 ft 14 Buses Parent Canopy 146 ft Portables 7 Portables Site Area +/- 20.07 Acres

N

Wet Retention Pond Buses/Service Parent/Sta ff

Dumpsters

slide-4
SLIDE 4

Orange County Public Schools

Rendering at Main Entry

slide-5
SLIDE 5

Orange County Public Schools

Phasing Plan

N

PHASE 1

Phase 1

Jun/2017 – May/2018

  • 1. Demolish existing

Buildings and Portables

  • 2. New 2-Story Building

3. New Bus Loop and Parking 4. New Parent Loop and Parking 5. New PE Facilities

Pedestrian/Bicycle Route

slide-6
SLIDE 6

Orange County Public Schools

Phasing Plan

N

PHASE 2 PHASE 2

Phase 2a

Jun/2018 – Jul/2018 1. Begin Demolition of Existing Portables and Buildings 2. Extend Bus Drive and Parking 3. Construct New Hardcourt

slide-7
SLIDE 7

Orange County Public Schools

Phasing Plan

N

PHASE 3 PHASE 3

Phase 3

Oct/2018 1. Complete Playfields 2. Complete Drive

slide-8
SLIDE 8

Orange County Public Schools Construction Update and Milestones

  • Notice to Proceed (NTP) was issued July 24, 2017.
  • Tilt Wall Panels were completed on November 06, 2017.
  • Structural Steel Erection was completed January 05, 2018
  • Roofing work has started and will be completed by February 01, 2018
  • Window installation started and will be completed by February 28, 2018
  • Exterior painting has started and will be completed by February 15, 2018
  • Interior finishes have begun.
  • Project is 40% complete.
  • Project remains on schedule:
  • Substantial Completion of Phase I - June 8th 2018
  • Substantial Completion of Phase II – August 3rd 2018
  • Substantial Completion of Phase III – September 18th 2018

Sustainability

slide-9
SLIDE 9

Orange County Public Schools

Aerial Photo – Mid August

slide-10
SLIDE 10

Orange County Public Schools

Aerial Photo – Mid September 2017

slide-11
SLIDE 11

Orange County Public Schools

Aerial Photo – Mid October 2017

slide-12
SLIDE 12

Orange County Public Schools

Aerial Photo – Mid November 2017

slide-13
SLIDE 13

Orange County Public Schools

Aerial Photo – Mid December 2017

slide-14
SLIDE 14

Orange County Public Schools

Aerial Photo – Mid January 2018

slide-15
SLIDE 15

Orange County Public Schools

Neighborhood Access to School

slide-16
SLIDE 16

Orange County Public Schools

Preliminary Site Work

Primary Trenching Underground Conduit

slide-17
SLIDE 17

Orange County Public Schools

Concrete Progress

Slab on Grade Pour Forming Tilt Panels

slide-18
SLIDE 18

Orange County Public Schools

Tilt Panel Progress

Elevator Pit & Tilt Panel Rebar Thin-Set Brick Veneer

slide-19
SLIDE 19

Orange County Public Schools

Tilt Panel Installation

Tilt Panel Pour Tilt Panel Erection

slide-20
SLIDE 20

Orange County Public Schools

Structural Steel Progress

Structural Steel Fabrication Structural Steel Erection

slide-21
SLIDE 21

Orange County Public Schools

Topping Out

Roof Deck Installation Fire Proofing

slide-22
SLIDE 22

Orange County Public Schools

Roofing Membrane Installation

slide-23
SLIDE 23

Orange County Public Schools

Questions??