Decision on Iron Point Facility Budget & Financing Steve - - PowerPoint PPT Presentation

decision on iron point facility budget financing
SMART_READER_LITE
LIVE PREVIEW

Decision on Iron Point Facility Budget & Financing Steve - - PowerPoint PPT Presentation

Decision on Iron Point Facility Budget & Financing Steve Berberich Vice President Corporate Services, Interim Chief Financial Officer and Treasurer ISO Board of Governors Meeting General Session May 18, 2009 The new facility will address


slide-1
SLIDE 1

Decision on Iron Point Facility Budget & Financing

Steve Berberich Vice President Corporate Services, Interim Chief Financial Officer and Treasurer ISO Board of Governors Meeting General Session May 18, 2009

slide-2
SLIDE 2

Slide 2

The new facility will address space and critical security concerns.

! Our current facilities are inadequate:

! Security concerns exist with our open campus ! We lack appropriate public meeting places ! Many of our staff are in inadequate work spaces ! Our control room will require significant reconstruction to provide world class grid management

! The ISO considered several options, including staying at the current

site, purchasing a building or constructing a new facility

! We chose a new facility as the best option and designed a multi-wing

facility:

! Office wing to house staff ! Public wing for external meetings and board meetings ! Highly secure mission critical wing for control room and data centers

slide-3
SLIDE 3

Slide 3

Our vision for the building is expansive.

! The building will be a showcase for environmental

stewardship with a commitment to achieving Gold Level LEED (Leadership in Energy and Environmental Design)

! Superior energy savings ! Water efficiency ! Reduced greenhouse gas footprint ! Commitment to environmental quality

! We plan to create a world class control room ! The building will be practical, functional and comfortable for

the public and employees

slide-4
SLIDE 4

Slide 4

The project is now ready for final approvals.

! Overall budget approval ! Authorization for a bond offering ! Resolution to allow certain cost reimbursement from the bond proceeds ! Authorization of several documents related to the bond

  • ffering and related mortgage
slide-5
SLIDE 5

Slide 5

The overall budget for the building has been set at $160 million.

! We negotiated a firm, fixed

contract for construction with penalties and incentives

! We included all incurred

and projected costs including furnishings, the move, and data center and control room equipment

! We included $10 million in

  • wner contingency

Category Estimate (millions) Schematic Design $2 Design Costs to 60% Design Development $2.9 Design Completion and Construction $110.9 Owner Costs $34.2 Subtotal Project Costs $150 Owner Contingency $10 Total Project Total $160

slide-6
SLIDE 6

Slide 6

We plan to finance construction of the facility.

! Financing team is in place ! Issuance amount of $205

million to $210 million

! Fixed rate securities with a

thirty year life

! Expected interest rate between

5.5% and 6%

! Issued through the California

Infrastructure Bank

! Expect to receive funds in July

Category Estimate (millions) Facility Design and Construction Costs $115.8 Associated Costs (move data center, consultants, construction management, furniture, fixtures, contingency, audio/visual) $44.2 Subtotal, Building Funding Need $160.0 Capitalized Interest $25.7 Issuance Costs $2.5 Subtotal, prior to Debt Service Reserve Fund $188.2 Debt Service Reserve Fund $17 Total Issuance Amount $205.2 to $210.0

slide-7
SLIDE 7

Slide 7

The GMC impact will be modest.

! Average GMC impact

  • f 1.6 cents over life of

financing ! No impact to GMC in 2009 or 2010 ! Forecasted GMC is not expected to increase materially

$0.000 $0.005 $0.010 $0.015 $0.020 $0.025 $0.030 $0.035 $0.040 $0.045

2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041

Incremental Cost of New Iron Point Facility (GMC impact from status quo, assuming 5.75% cost of funds)

Additional security/ environmental benefits of ISO owned building One-time transitional costs

slide-8
SLIDE 8

Slide 8

We will tightly manage the project.

! We have a project manager from an experienced construction firm retained to manage the project ! We formed critical teams and tapped senior leadership to lead them

! Control Center ! Data Center ! Interiors ! Move

! We have tight controls around change controls and other contract matters

slide-9
SLIDE 9

Slide 9

The move into the new building will begin in late 2010.

! Site work (including foundations) will occur through the

summer

! Construction of the steel frame will begin in September ! The mission critical wing will be available for furniture

and fixtures in late 2010

! The general office building will be available for furniture

and fixtures in early 2011

! Plans are to complete the move prior to summer 2011

slide-10
SLIDE 10

Slide 10

Resolutions

! Budget Resolution – Approves the overall budget ! Bond Issuance Resolution – Allows the ISO to issue

bonds to finance the project

! Reimbursement Resolution – Allows bond funds to be

used to reimburse the ISO for funds already spent

! Financing Agreement Resolution – Approves the

financing documents in substance