DAVID KNAPP STRUCTURAL OPTION SPRING 2003 OAK BROOK POINTE Six - - PowerPoint PPT Presentation

david knapp
SMART_READER_LITE
LIVE PREVIEW

DAVID KNAPP STRUCTURAL OPTION SPRING 2003 OAK BROOK POINTE Six - - PowerPoint PPT Presentation

DAVID KNAPP STRUCTURAL OPTION SPRING 2003 OAK BROOK POINTE Six story office building Chicago suburb 250,000 ft 2 total Contents Relevant Building Depth: Structural Steel Background Loads Gravity Design Design Team Mechanical


slide-1
SLIDE 1

DAVID KNAPP

STRUCTURAL OPTION

SPRING 2003

slide-2
SLIDE 2

OAK BROOK POINTE

Six story office building Chicago suburb 250,000 ft2 total

slide-3
SLIDE 3

David Knapp Oak Brook Pointe

Contents

Relevant Building Background

Design Team Architecture Structure Mechanical System

Breadth: Green Roof

Benefits Design

Breadth: Mechanical System

Roof Adjustments Floor Adjustments

Depth: Structural Steel

Loads Gravity Design Mechanical Integration Lateral System Final Design Cost

Conclusions Acknowledgements Questions

slide-4
SLIDE 4

David Knapp Oak Brook Pointe

Contents

Relevant Building Background

Design Team Architecture Structure Mechanical System

Breadth: Green Roof

Benefits Design

Breadth: Mechanical System

Roof Adjustments Floor Adjustments

Depth: Structural Steel

Loads Gravity Design Mechanical Integration Lateral System Final Design Cost

Conclusions Acknowledgements Questions

slide-5
SLIDE 5

David Knapp Oak Brook Pointe

Owner – Hines Architect – Wright Architects, LTD Structural Engineer – Halvorson & Kaye Structural Engineers, PC MEPFP Engineer – Cosentini Associates General Contractor & CM – Turner Construction Civil Consultants – SDI Consultants, LTD

Design Team

slide-6
SLIDE 6

David Knapp Oak Brook Pointe

Architecture

700 Commerce Dr. Oak Brook, IL 120° L-shape Footprint, stepped wing ends Award-winning pre-cast w/ blue reflective glass exterior $21 million project cost, $16.5 million for building

slide-7
SLIDE 7

David Knapp Oak Brook Pointe

Architecture

Typical floor plan

slide-8
SLIDE 8

David Knapp Oak Brook Pointe

Initial Structural System

Gravity System – Two-way reinforced concrete flat slab with drop panels Lateral System – continuously poured slabs and columns forming slab frames Typical Bay Strip – 30’ wide with 35’ side bays with a 30’ center “corridor” bay Foundations – Square spread footings, basement floor is slab on grade Concrete – Normal weight with 28-day compressive strength of 6,000 psi at columns and walls; 4,000 psi everywhere else

slide-9
SLIDE 9

David Knapp Oak Brook Pointe

Initial Structural System

Typical structural layout

slide-10
SLIDE 10

David Knapp Oak Brook Pointe

Initial Mechanical System

Six rooftop packaged units 12” deep main supply loop with VAV fan boxes 2 29,000 CFM exhaust fans in basement

RTU 1 & 4 RTU 2 & 3 RTU 5 & 6 SERVICE Floor 5 Floors 1-4 Floors 1-4 EVAPORATOR FAN: Air flow (CM) 22,000 42,000 42,000 Fan RPM 1060 880 880 EXHAUST FAN: Air flow (CM) 22,000 42,000 42,000 Fan RPM 650 610 610 CONDESSOR FAN: Air flow (CM) 40,800 63,200 63,200 COMPRESSOR DATA: RPM 3450 3450 3450 EVAPORATOR COIL: Total cooling load (BTU) 806,000 1,530,000 1,530,000 Sensible cooling load (BTU) 589,000 1,164,000 1,164,000 Entering D.B. Temp. (°F) 83 80 80 Entering W.B. Temp. (°F) 66 66 66 Leaving D.B. Temp. (°F) 55 55 55 Ambient D.B. Temp (°F) 94 94 94 ELECTRIC HEATER: kW 90 190 190 TOTAL WEIGHT (lbs) 11,000 17,000 17,000

24x12 36x12 30x12 76x14 54x20 76x14 58x12 44x12 36x12 30x12 36x12 1680 CFM Fan Box 1680 CFM Fan Box 1400 CFM Fan Box 1530 CFM Fan Box 1530 CFM Fan Box 144x18 Return Air Duct

Typical mechanical plan

slide-11
SLIDE 11

David Knapp Oak Brook Pointe

Contents

Relevant Building Background

Design Team Architecture Structure Mechanical System

Breadth: Green Roof

Benefits Design

Breadth: Mechanical System

Roof Adjustments Floor Adjustments

Depth: Structural Steel

Loads Gravity Design Mechanical Integration Lateral System Final Design Cost

Conclusions Acknowledgements Questions

slide-12
SLIDE 12

David Knapp Oak Brook Pointe

Green Roof

A green roof is a system

  • f filtering layers and

growth layers, characterized by soils, grasses, shrubs, even trees, that substitutes for conventional flat roof water-proofing. Popular in Europe In the process of becoming mandatory in Chicago

slide-13
SLIDE 13

David Knapp Oak Brook Pointe

Green Roof - Benefits

Reduced Urban Heat Island Effect Effective management and utilization of stormwater Clean and oxigenated air Reduced heat and noise translation through roof Creation of additional usable space and property value for the building tenants

Infrared photo of U.H.I.E.

slide-14
SLIDE 14

David Knapp Oak Brook Pointe

Green Roof - Design

Products by HydroTech USA Two main types:

Extensive Garden Roof Intensive Garden Roof

Two alternatives:

Extensive Garden Roof w/ public

access intensive system park area

Emergency egress requirements

Non-public extensive system over

the entire roof

slide-15
SLIDE 15

David Knapp Oak Brook Pointe

Green Roof - Cost

Initial Ballasted Membrane Roof: $250,000

  • ALT. 2

EXTENSIVE INTENSIVE EXTENSIVE AREA (ft2) 30,800 6,675 37,475 SYSTEM $215,600 $146,850 $262,325 PLANTS $61,600 $233,625 $74,950 INSTALLATION $154,000 $86,775 $187,375 GUARDRAIL

  • $10,500
  • BUILDING
  • $16,500
  • TOTALS

$431,200 $494,250 $524,650 OVERALL TOTAL $524,650 MAINTAINENCE $46,200/yr $10,000/yr $56,200/yr

  • ALT. 1

$925,450

slide-16
SLIDE 16

David Knapp Oak Brook Pointe

Contents

Relevant Building Background

Design Team Architecture Structure Mechanical System

Breadth: Green Roof

Benefits Design

Breadth: Mechanical System

Roof Adjustments Floor Adjustments

Depth: Structural Steel

Loads Gravity Design Mechanical Integration Lateral System Final Design Cost

Conclusions Acknowledgements Questions

slide-17
SLIDE 17

David Knapp Oak Brook Pointe

Mechanical Redesign - Roof

Red: Existing design Blue: Proposed design

slide-18
SLIDE 18

David Knapp Oak Brook Pointe

Mechanical Redesign - Roof

Initial RTU configuration Proposed RTU configuration

slide-19
SLIDE 19

David Knapp Oak Brook Pointe

Mechanical Redesign - Floors

30x13 30x13 24x13 76x14 54x20 24x13 24x13 1680 CFM Fan Box 1400 CFM Fan Box 1530 CFM Fan Box 1530 CFM Fan Box 144x18 Return Air Duct 1680 CFM Fan Box 54x20 76x14 24x13 30x13 30x13

Proposed mechanical layout

slide-20
SLIDE 20

David Knapp Oak Brook Pointe

Contents

Relevant Building Background

Design Team Architecture Structure Mechanical System

Breadth: Green Roof

Benefits Design

Breadth: Mechanical System

Roof Adjustments Floor Adjustments

Depth: Structural Steel

Gravity Design Mechanical Integration Lateral System Final Design Cost

Conclusions Acknowledgements Questions

slide-21
SLIDE 21

David Knapp Oak Brook Pointe

Steel – Gravity Design

Loads the same except:

Dead load = 80 psf Green roof system:

Extensive = 35 psf Intensive = 120 psf

2” Lok-floor composite deck with 3” LW concrete cover Composite beam and column design by RAMSteel

LOCATION B - 2 2 - 4 4 - R Exterior W12x72 W12x53 W12x40 Interior W12x106 W12x72 W12x53

COLUMN SCHEDULE

slide-22
SLIDE 22

David Knapp Oak Brook Pointe

Steel – Gravity Design

Gravity framing layout

slide-23
SLIDE 23

David Knapp Oak Brook Pointe

Steel – Mechanical Integration

AVOID BUILDING HEIGHT INCREASE

Increases total square footage of exterior cladding Increases length of vertical elements such as stairs, elevators, utility shafts, and columns Increases lateral loading and their respective resisting systemsIncreases volume of conditioned air

GOAL: MAINTAIN 3’-1” PLENUM

slide-24
SLIDE 24

David Knapp Oak Brook Pointe

Steel – Mechanical Integration

VIERENDEEL TRUSSES

Castellated beams too deep Vulcraft composite joists too conservative WT chords, LL angle web members Girders increased to W24x55 for framing

slide-25
SLIDE 25

David Knapp Oak Brook Pointe

Steel – Mechanical Integration

GIRDER OPENINGS

Large opening – cantilever support Wide opening – Reinforced web opening

slide-26
SLIDE 26

David Knapp Oak Brook Pointe

Steel – Lateral System

Shear walls (green) surrounding elevator core Steel moment frames (blue) to assist with torsion

slide-27
SLIDE 27

David Knapp Oak Brook Pointe

Steel – Lateral System

Shear walls reinforcement:

  • #5 @ 12” horizontal
  • 26 - #9 bars for flexure
slide-28
SLIDE 28

David Knapp Oak Brook Pointe

Steel – Final Design

Final proposed structural plan

slide-29
SLIDE 29

David Knapp Oak Brook Pointe

Steel - Cost

Initial Superstructure: $4,700,000

ITEM MATERIAL LABOR EQUIPMENT TOTAL Steel Framing $735,000 $207,360 $63,600 $1,005,960

  • V. Trusses

$60,368 $24,538 $7,526 $92,432 Shear Studs $17,468 $55,611 $7,130 $80,208 Fireproofing $159,250 $150,000 $30,000 $339,250 Steel Deck $857,500 $231,000 $15,000 $1,103,500 Concrete Slabs $202,860 $201,600 $66,000 $470,460 Concrete Walls $84,280 $103,200 $21,500 $208,980 Mat Foundation $10,290 $6,600 $100 $16,990 Spread Footings $40,572 $33,120 $345 $74,037 SUPERSTRUCTURE TOTAL $3,391,817

slide-30
SLIDE 30

David Knapp Oak Brook Pointe

Contents

Relevant Building Background

Design Team Architecture Structure Mechanical System

Breadth: Green Roof

Benefits Design

Breadth: Mechanical System

Roof Adjustments Floor Adjustments

Depth: Structural Steel

Gravity Design Mechanical Integration Lateral System Final Design Cost

Conclusions Acknowledgements Questions

slide-31
SLIDE 31

David Knapp Oak Brook Pointe

Conclusions

GREEN ROOF

Despite higher costs, ecological impacts are very important, and there either green roof alternative is suggested.

STRUCTURAL SYSTEM

The proposed steel system would save $1.3M and would be completed earlier, and therefore is suggested

MECHANICAL SYSTEM

Any mechanical changes were made to benefit the green roof and structural redesign, and would not be needed if those alternatives were not chosen

slide-32
SLIDE 32

David Knapp Oak Brook Pointe

Thank You

Faculty

  • Dr. Thomas Boothby
  • Jonathan Dougherty
  • Dr. Louis Geschwindner
  • Dr. Linda Hanagan
  • Dr. Moses Ling
  • Dan Mattern
  • Dr. Ali Memari
  • Dr. Kevin Parfitt

Professionals

  • Joe Krolopp
  • Lynne McMillion
  • Josh Munson
  • David Samuelson
  • Paul Stout
  • Jim Swanson

Peers

  • Amy Graver
  • Jon Jadico
  • Brad Koehler
  • Melissa Rosol
  • Andrew Tech

Family and Friends

  • My mother and father
  • All my brothers and their families
  • Alison Killian
  • Jason Kelso
  • The good people at Kinkos
slide-33
SLIDE 33

QUESTIONS?

slide-34
SLIDE 34

David Knapp Oak Brook Pointe

Reinforcement Details

slide-35
SLIDE 35

David Knapp Oak Brook Pointe

Truss Model and Loading

slide-36
SLIDE 36

David Knapp Oak Brook Pointe

Green Roof Components

  • Roof Membrane
  • Membrane Protection
  • Insulation
  • Drainage
  • Filter
  • Soil
  • Vegetation
slide-37
SLIDE 37

David Knapp Oak Brook Pointe

Structural Steel

PROS

Fast and easy construction Lighter dead loads Composite design with slab lightens beams

CONS

More lead time, CM preparation Deeper plenum

slide-38
SLIDE 38

David Knapp Oak Brook Pointe

Structural Loads

DESIGN GRAVITY LOADS DESIGN WIND LOADS TYPICAL FLOOR: LATERAL LOAD ON STRUCTURAL FRAME 25 PSF ROOF UPLIFT 15 PSF SUPERIMPOSED DEAD LOADS - ROOF OVERHANG 40 PSF

  • MEP. CEILING, ETC.

10 PSF PARTITIONS 20 PSF CODE MINIMUM WIND LOADS BASED ON THE FOLLOWING: BASIC WIND SPEED, V=75 MPH LIVE LOAD - WIND LOAD IMPORTANCE FACTOR, I=1.0 OFFICE AREA 80 PSF** WIND EXPOSURE (TYPICAL) = B CORRIDOR, STAIR, LOBBY 100 PSF WIND DESIGN PRESSURE, P, VARIES WITH BLDG. HEIGHT, (**REDUCED PER CODE SECT. 1608.0 USE MAXIMUM VALUE OF 25 PSF FOR ENTIRE HEIGHT FOR FLOOR AND COLUMN DESIGN) EARTHQUAKE DESIGN DATA ROOF LEVEL - GENERAL AREAS: CODE MINIMUM DESIGN LOADS BASED ON THE FOLLOWING: SUPERIMPOSED DEAD LOADS - PEAK VELOCITY-RELATED ACCELERATION, Av, 0.5

  • MEP. CEILING, ETC.

10 PSF PEAK ACCELERATION, Aa, O.5 ROOFING, INSULATION, ETC. 15 PSF SEISMIC HAZARD EXPOSURE GROUP=GROUP I SEISMIC PERFORMANCE CATEGORY=A LIVE LOAD - SNOW (MINIMUM) 20 PSF+DRIFTING PER CODE SECT. 1612.1, EXCEPTION 3, DESIGN NEED ONLY COMPLY WITH SECT. 1612.3.6.1 CODE MINIMUM SNOW LOADS BASED ON THE FOLLOWING: GROUND SNOW LOAD, Pg=25 PSF FLAT ROOF LOAD, Pf=17.5 PSF SNOW EXPOSURE FACTOR, Ce=0.7 SNOW IMPORTANCE FACTOR, I=1.0 ROOF LEVEL - MECHANICAL EQUIPMENT AREAS: SUPERIMPOSED DEAD LOAD - MEP, CEILING, ETC. BELOW SLAB 10 PSF ROOFING, INSULATION, ETC. 15 PSF LIVE LOAD - (INCLUDES MECH. EQUIPMENT, SCREEN WALLS, SNOW + DRIFTING) 55 PSF OTHER LOADS: LIVE LOAD AT ELEV. MACH. RM. 150 PSF (OR ACTUAL) ROOF TOP SCREEN WALL WEIGHT AS CALCULATED

slide-39
SLIDE 39

David Knapp Oak Brook Pointe

Steel – Mechanical Integration

GIRDER OPENINGS

Large opening – cantilever support Wide opening – Reinforced web opening Center web openings

A L T . 2

E X T E N S I V E I N T E N S I V E E X T E N S I V E A R E A ( f t 2 ) 3 0 , 8 0 0 6 , 6 7 5 3 7 , 4 7 5 S Y S T E M $ 2 1 5 , 6 0 0 $ 1 4 6 , 8 5 0 $ 2 6 2 , 3 2 5 P L A N T S $ 6 1 , 6 0 0 $ 2 3 3 , 6 2 5 $ 7 4 , 9 5 0 I N S T A L L A T I O N $ 1 5 4 , 0 0 0 $ 8 6 , 7 7 5 $ 1 8 7 , 3 7 5 G U A R D R A I L

  • $ 1 0 , 5 0 0
  • B U I L D I N G
  • $ 1 6 , 5 0 0
  • T O T A L S

$ 4 3 1 , 2 0 0 $ 4 9 4 , 2 5 0 $ 5 2 4 , 6 5 0 O V E R A L L T O T A L $ 5 2 4 , 6 5 0 M A I N T A I N E N C E $ 4 6 , 2 0 0 / y r $ 1 0 , 0 0 0 / y r $ 5 6 , 2 0 0 / y r

A L T . 1

$ 9 2 5 , 4 5 0

slide-40
SLIDE 40

David Knapp Oak Brook Pointe

Mechanical Redesign - Roof