Data Subcommittee (DS) RAC Meeting Stephanie Imamovic, DS Chair October 9, 2018 W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L 2 Overview Recently Approved Items (Sep 25-26,


  1. Data Subcommittee (DS) RAC Meeting Stephanie Imamovic, DS Chair October 9, 2018 W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  2. 2 Overview • Recently Approved Items (Sep 25-26, 2018 DS Meeting) – Revisions to DS Charter – Changes to 2019 Base Case Compilation Schedule – 2019 Data Preparation Manual – ADS PCM Changes – Additional PCM Changes in a PCM master switch file • New and Ongoing Activities – Loads and Resources Task Force – Other Major Activities • Upcoming Meetings W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  3. 3 2019 Base Case Compilation Schedule • The following changes were approved: – Minor schedule adjustments – PDCI targets – 30LSP1-S case description W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  4. 4 2019 Data Preparation Manual • 2019 DPM Approved – Includes approved change requests since 2018 DPM • Bus low/high voltage limits • Addition of GWT – Clarified lat/long requirements, BA/BAA term, and general edits W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  5. 5 ADS PCM V2.0 • Approved Changes (Corrections) to ADS PCM V1.0: – Change in bus ownership to eliminate Pancake Wheeling on PDCI – Adjustment to make NW Tier 1 Energy match target – Align Wind/Solar Commitment and Dispatch Shapes – Correct Beacon Solar Area model for appropriate technology – Correct Interface Definitions – Model Updates for Antelope Nuclear Operation – Updates to Correct Hydro Modeling Data Issues – Negative Pricing on Hydro outside of CA – Modify Model for Hyatt and Thermalito Hydro Units – Correct Model for Klamath Falls Area Transmission – Correct Model for Specified Thermal Plants – Correct Model of Units Disconnected in PF as identified in NTTG Edits – Adjust Coal Prices • ADS PCM V2.0 will be posted by October 15, 2018 W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  6. 6 Supplemental Resources in PCM • Approved to be made available in a standalone PCM master switch file: – NTTG Edits – PNM & TEP Edits – CAISO & LADWG Edits – Any additional edits provided by the data owner prior to posting • File will be posted by October 15, 2018 W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  7. 7 Loads and Resources Task Force • In response to ADSTF Request Letter to the DS • Draft charter was discussed at Sep DS Meeting • A DS Meeting is being arranged for late Oct or early Nov to approve the charter • Purpose: To provide guidance in the development and coordination of processes to reconcile and address inconsistencies between LAR information, base case data, and PCM data W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  8. 8 Other Major Activities • Drafting PCM Data Development & Validation Manual (DDVM) – Targeting DS approval of the 1 st version at Jan DS 2019 meeting • Developing next steps for Base Case Management System (BATF follow up) • Enhancing Steady-state and Dynamics Dashboard (SADD) to improve data quality • GIC Data due October 19, 2018 W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  9. 9 Upcoming Meetings • Subcommittee Meetings on Jan 28-31, 2018 • Work Group Meetings on Nov 27-30, 2018 – SDWG on Nov 27-28 – PDWG on Nov 28-29 – EDWG on Nov 30 – Additional PDWG webinars are held weekly on Tues W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  10. 10 Questions? Stephanie Imamovic, DS Chair Puget Sound Energy Stephanie.Imamovic@pse.com W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.