Cultural Resources Collaboration and Innovation Towards Continuous - - PowerPoint PPT Presentation

cultural resources collaboration and innovation towards
SMART_READER_LITE
LIVE PREVIEW

Cultural Resources Collaboration and Innovation Towards Continuous - - PowerPoint PPT Presentation

Cultural Resources Collaboration and Innovation Towards Continuous Improvement: Traffic Signal Upgrades Memorandum of Understanding Eric Duff State Environmental Administrator At GDOT, we are at our best when faced with a challenge 2017


slide-1
SLIDE 1

Cultural Resources Collaboration and Innovation Towards Continuous Improvement: Traffic Signal Upgrades Memorandum of Understanding

Eric Duff State Environmental Administrator

slide-2
SLIDE 2

At GDOT, we are at our best when faced with a challenge… 2018 Hurricane Michael 2017 I-85 Bridge Collapse

slide-3
SLIDE 3

Environmental Challenges are no different

The Challenge– Statewide Signal Upgrades

  • Large Survey

Areas

  • Huge

Documents

  • Big Budgets
  • Extended

Schedules

74 page History Report 220 page Archaeology Report

slide-4
SLIDE 4

Traffic Operations Signal Upgrades

The Traffic Signal Upgrade Program

  • GDOT is responsible for over 6,000 on-system signals

throughout the state

  • Signalized intersection upgrades from span wires to mast

arms, where feasible

slide-5
SLIDE 5

Section 106 of the National Historic Preservation Act

A Procedural Law

  • There are four separate required activities under the law that

require documentation and coordination with agencies

  • Typical agency review time is 30 days for each round of

review

  • Change to the Section 106 process requires coordination

with SHPO and FHWA

slide-6
SLIDE 6

Collaboration Between GDOT Offices and Agencies

  • Coordinated with Traffic Operations

Management

  • Analyzed Signalization Projects from

2006 with Span Wire to Mast Arm Upgrades

  • Consulted with SHPO and FHWA

GDOT Cultural Resources Managers…

slide-7
SLIDE 7
slide-8
SLIDE 8
slide-9
SLIDE 9

The Innovation: A Memorandum of Understanding with SHPO and FHWA

How is this innovative?

  • Shorter timelines
  • Less potential for

Section 4(f)

  • Fewer disagreements

with agencies

  • More time spent on the

important issues

Consistent on-time project delivery!

slide-10
SLIDE 10

The Results – Historic Resources

Example: Upgrades to 20 Signal Locations

20 1 5 10 15 20 25 Then Now

Number of Weeks for Survey and Reporting

#of Weeks

slide-11
SLIDE 11

The Results – Historic Resources

Example: Upgrades to 20 Signal Locations

$150,000 $2,500 WITHOUT MOU WITH MOU $0 $20,000 $40,000 $60,000 $80,000 $100,000 $120,000 $140,000 $160,000

Survey and Reporting Costs

Without MOU With MOU

Cost Savings: $222,500!

$225,000 $2,500 WITHOUT MOU WITH MOU $0 $50,000 $100,000 $150,000 $200,000 $250,000

Survey and Assessment of Effect Costs

Without MOU With MOU

slide-12
SLIDE 12

The Results – Archaeological Resources

Example: Upgrades to 20 Signal Locations

1040 720 200 400 600 800 1000 1200 Then Now

# of Shovel Tests

#of Shovel Tests 13 2 5 10 15 Then Now

#of Sites

#of Sites

slide-13
SLIDE 13

The Results – Archaeological Resources

Example: Upgrades to 20 Signal Locations

$72,000 $42,000 WITHOUT MOU WITH MOU $0 $10,000 $20,000 $30,000 $40,000 $50,000 $60,000 $70,000 $80,000

Survey and Reporting Costs

Without MOU With MOU

Cost Savings: $30,000!

slide-14
SLIDE 14

Continuous Improvement

The MOU significantly cuts down on project costs and delivers projects faster

Potential Total Cost Savings for GDOT per Project: $252,500

slide-15
SLIDE 15

“Obligation to be Great”

Office of Environmental Services Office of Traffic Operations