cryomodules standardization
play

Cryomodules Standardization S.K. Chandrasekaran International - PowerPoint PPT Presentation

Cryomodules Standardization S.K. Chandrasekaran International Workshop on CM Design & Standardization 09/06/2018 OR 06/09/2018 OR 6 Sept 2018 ??? 2 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design &


  1. Cryomodules Standardization S.K. Chandrasekaran International Workshop on CM Design & Standardization 09/06/2018 OR 06/09/2018 OR 6 Sept 2018 ???

  2. 2 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  3. 3 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  4. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 4 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  5. Outside CM systems • Alignment strategy – Fiducials; HBCAM vs Wire frame – Track during/after cool down? During transport? • Interfaces – RF, Cryogenic, Beam line, Vacuum • Instrumentation – Inside & outside CM – In VTS & test cave (e.g., radiation monitors for FE monitoring) – Connectors and flanges • In-tunnel transport • CM support stands • Performance measurement methods/techniques 5 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  6. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 6 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  7. Cavities – standardization • Interfaces – Lifting lugs Same for SSR1 & SSR2? – Cavity positioning lugs Same for LB650 & HB650? – Coupler & pick up port – Tuner attachment pads • Benefits of standardized parameters: – Tooling required can be the same for the cavities • Only remaining variation would be based on the existing facility – Single design operation and procurement cycle 7 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  8. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 8 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  9. Couplers – standardization • Coupler flange on cavity • Thermal stages Same for SSR1 & SSR2? – 2 K, 5 K, 50 K, 300 K Same for LB650 & HB650? • Thermal straps • Benefits of standardized parameters: – Single design operation – Larger procurement • Coupler procurement can be complex • Validated manufacturing procedures at vendor can be used on larger quantities – Lower QA issues & greater reliability • Potentially lower cost per coupler due to volume discounts 9 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  10. 650 MHz coupler, conventional (backup) design. Adjustable coupling at assembly In backup design the vacuum outer conductor is ‘conventional’ type: SS tube coated by copper. "Experience in the design of fundamental couplers", S. Kazakov, Mumbai 10 9/6/2018

  11. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 11 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  12. 650MHz Tuner LCLS II Tuner Tuner characteristic (based on warm measurements and LCLS II test) Coarse tuner range ~300kHz Coarse tuner res. ~1Hz/step Back/lash coarse tuner ~40Hz Fine tuner range ~6-8um (1.5kHz) Fine tuner resolution ~ 0.1Hz Yuriy Pischalnikov, Resonance Control, September 4, 2018, BARC, India 12

  13. Tuners – standardization • Tuner interface with cavity • Piezo & motors Same for SSR1 & SSR2? • Stiffness of the system Same for LB650 & HB650? • Algorithm development • Benefits of standardized parameters: – Single design operation – Larger procurement • Piezo & motors are long lead and expensive items if purchased individually – Potentially lower cost per item due to volume discounts – Cavity may be different, but tuner the same for algorithm 13 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  14. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 14 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  15. Cavity support system • Spaceframe, strongback are options for PIP-II (not for HWR) 15 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  16. Cavity support system – standardization • Strongback? – Validate in SSR1 Same for SSR1 & SSR2? • Spaceframe? Same for LB650 & HB650? – 650 MHz only • Benefits of standardized parameters: – Design for individual module types would be derivations – Concept validated earlier with one module type – Tooling for assembly will also be similar in concept 16 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  17. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 17 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  18. 3. Cryogenic layout of the cryomodules All cryomodules have the same layout and the same pressure design values. All cryomodules need to be compatible with a fast cool down: • Above 20 K/hour through the Q-disease regime 90 - 175 K. • Above 120 K/hour through the superconducting transition at 9.2 K Pipe B - Pumping line Pipe G - 2 phase He & chimney MAWP: 2.05 bar warm, 4.1 bar cold MAWP: 2.05 bar warm, 4.1 bar cold Pipe I - Helium guard of the current leads MAWP: 4.1 bar Pipe A - 2 K supply Pipe C & D - 5 K line MAWP: 20 bar MAWP: 20 bar Pipe H - Cool down / Pipe E & F - 35-50 K line warm up line MAWP: 20 bar MAWP: 20 bar 18 4-7 September 2018 Vincent Roger | PIP-II Cryomodule Design Overview

  19. Cryogenic system – standardization • Heat exchangers • Valves Same for SSR1 & SSR2? • U-tubes Same for LB650 & HB650? • Benefits of standardized parameters: – Concept validated earlier with one module type – Reliability increased – Vendors validated 19 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  20. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 20 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  21. 21 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  22. Tooling – standardization • Includes cleanrooms, processing facilities, assembly – Each facility to have separate tooling – Interfaces to the components may be standardized • Constraints: – Facility interfaces – may be difficult to standardize across Partners • Benefits of standardized parameters – Tooling changes for facilities (e.g. cleanroom) takes time • Configuration changes can be few weeks to months – Increases reliability – Decreases cost for the facility 22 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  23. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 23 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  24. Multiple methods available 24 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend