cryo path forward
play

CRYO Path Forward April 6, 2020 Presented by: Gunther Haller - PowerPoint PPT Presentation

CRYO Path Forward April 6, 2020 Presented by: Gunther Haller Director, Advanced Instrumentation for Research Division Technology Innovation Directorate Consortium agreed on a Downselect Process DUNE DocDB 6658 (12/17/2018) CRYOs role is


  1. CRYO Path Forward April 6, 2020 Presented by: Gunther Haller Director, Advanced Instrumentation for Research Division Technology Innovation Directorate

  2. Consortium agreed on a Downselect Process DUNE DocDB 6658 (12/17/2018) CRYO’s role is defined to be an “alternative” to baseline. NOT just a “risk mitigation” • “Testing Strategy and Decision Tree” treats 3-chip and CRYO completely symmetrically • “DUNE will plan for systems tests of the baseline and alternative options in both the CERN Cold Box and in the LArIAT cryostat with a small liquid argon TPC.” • Decision to be based on criteria defined by the consortium • Plan is for downselect to happen in February 2021

  3. CRYO Technical Status Full all-in-one system functionality demonstrated in DUNE v1 (very first prototype) ● Performance agreed with simulations in almost all aspects ● Measured noise levels higher than simulated. However: Discrepancy due to system issues, such as test board layout. ○ New cold test board correcting layout noise issues is currently being fabricated at PCB factory ● A couple of minor technical issues were fixed in nEXO version 1 (front-end optimized for nEXO) ● Bench tests can start as soon as when PCB board is received First nEXO version 1 received from foundry in February 2020 (development and fabrication funded by nEXO) ● This version is optimized for nEXO ● Stepping stone towards next 2nd prototype DUNE Cryo ASIC, might be final version. ● Front-end in nEXO V1 optimized for nEXO low capacitance, but simulated noise is within 10% of DUNE-optimized version nEXO V1 is suitable for system test at FNAL ICEBERG ● In schedule for Summer 2020 2nd prototype optimized for DUNE (V2) is planned for system test on ProtoDUNE Cold Box (mainly cable driver and putting back DUNE amplifier, minor modification) ● 2nd DUNE Cryo V2 ASIC expected back from fabrication August 2020 ● Cold Box test in schedule for late fall 2020/early winter 2021 CRYO will be ready by the down-select date Feb 2021

  4. Remaining work for the two options 3 ASIC type solution (amplifier, ADC, communication ASICs) • At least one more iteration is planned for each of the 3 ASICs • There is still a PCB to be implemented with all three types of ASIC mounted and tested: warm or cold - Functionality and performance of the three-ASIC system still needs to be shown • Initial tests from testing of LArASIC+ColdADC+FPGA (instead of COLDATA) on 40% APA reveal issues Cryo ASIC • J ust received nEXO V1 (also works for DUNE) - All three function blocks (amplifier, ADC, communication) has been shown to work in one ASIC - Noise performance to be tested (DUNE V1 had higher noise, but likely cause PCB, new PCB is in fabrication) - nEXO V1 ASIC (in bench testing this month) will be tested in ICEBERG - Demonstration of cold noise and system performance already before DUNE V2 - Opportunity to demonstrate complete system performance in TPC environment planned for Summer 2020 - The Feb-2020 review comment that 3-ASIC solution is further ahead is not an accurate assessment of the situation in our view, in fact the Cryo ASIC is much closer to having a complete system running on a board DUNE Cryo ASIC path forward is simpler, shorter, cheaper, and lower risk (which will be retired with ICEBERG test) ○ All three system blocks already working together (in one ASIC) ○ Iteration of only one ASIC (DUNE V2), versus 3 different types

  5. Considerations for future budget impact to DUNE project Remaining cost for DUNE project will be lower for single ASIC solution • Prototyping and Production - Single ASIC effort for further iterations, ASIC costs, design and testing labor will be less than for a 3-ASIC solution - Final board design and system testing will be less complex in the single ASIC system

  6. Sharing of Schematics: Will be solved ● DUNE requested to have the schematic shared since DUNE pays for the design ● SLAC’s honoring of its NDA with TSMC has up to now prevented sharing of schematics ● SLAC legal has been looking into how to mitigate this ● We are confident to resolve this ● Possibly need to execute simple NDA’s between SLAC and collaborators ○ Work in process

  7. Additional SLAC physicist to work on DUNE: Bill Wisniewski • Bill Wisniewski is planned to start working on DUNE • Concentrating on SLAC contribution on Cryo ASIC and related instrumentation • Bill has substantial experience in HEP detector instrumentation (Extensive project management experience, BaBar Technical Coordinator, LZ, etc) • Bill just came off the LBNF-DUNE detailee assignment at DOE Headquarters March 30 • Could not start before for obvious reasons • Very positive addition for DUNE in many ways

  8. Path Forward: Recognizing and help mitigating DUNE’s budget problems DUNE plans to support testing of nEXO version 1 which was just received (main items) • Coordinated with Nuclear Physics to share development and testing - Bench test • ICEBERG test - Hawaii FEMB fabrication - WIB firmware (BNL, Penn,...) To complete the remaining work required for the down-selection: • SLAC will internally support development, fabrication and bench test of Cryo DUNE V2, tailored prototype in preparation for ProtoDUNE Cold Box test • No cost to DUNE to develop, fabricate, bench test optimized Cryo DUNE V2 prototype ASIC

  9. Consortium agreed on a Downselect Process DUNE DocDB 6658 (12/17/2018) There is no justification to modify the Downselect process that was agreed to by all parties • SLAC’s contribution relieves budget pressure • DOE and SLAC have invested substantial funds and the cost to go to down-select is small compared to the investment • Engineers have put in substantial effort based on agreement

  10. Conclusion ● Cryo ASIC development on track and large likelihood that Cryo DUNE V2, tailored to DUNE, will meet requirements ● Cryo schematics on path to be shared between collaborators ● Clear potential benefits to DUNE of single integrated version ASIC: Lower future project cost (only one type of ASIC to produce and test, board simpler, etc) ● Addition of experienced physicist Bill Wisniewski on Cryo, just coming off being the LBNF-DUNE detailee at DOE ● All cost for development, fabrication, and bench testing of Cryo DUNE V2 will be contributed by SLAC All concerns have been addressed and it is vital that the agreed down-select process be followed with both solutions on equal footing

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend