County DSS Directors Update October 2017 1 Project 3 Updates - - PowerPoint PPT Presentation
North Carolina Department of Health & Human Services County DSS Directors Update October 2017 1 Project 3 Updates Child Care Attendance and roster submission for providers serving children from Pilot and Groups A, B and C took
1
North Carolina Department of Health & Human Services
2
Groups A, B and C took place in early October.
November – currently targeting November 7th.
requests from the NC FAST team to ensure case activation in November is as successful as possible.
cases obligate from the desired funding source at activation. This is strongly preferred to handling obligation transfers to change the funding source for a case after activation.
before November 1st if they are to be paid along with November services.
3
just each child) in order for payment to be processed timely.
and 20th of the month, not specifically on the 15th.
deposit in their account and no longer receive payments for individual children.
exception of a recertification packet or when a child is pulled off of the waiting
service plan functionality which will improve how the system reacts to changes
error, that providers sometimes encounter in the provider portal.
4
enrollment by the end of 2017, if they have not done so already. A report on FAST Help contains the current contract end date for each provider, please review the report and begin encouraging your providers to begin completing re- enrollment.
longer be able to participate in the subsidy program and all subsidy children in care at that facility will need to be moved or the parent will need to begin paying the private pay rate.
Portal reminding them to complete re-enrollment.
November 30th. In order to allow a 10 day notification period, termination notices will need to be sent to any provider that does not re-enroll by mid- December.
5
Implementation statewide delayed two months. Will still comply with NC legislation intent for P4 Child Services be operational by the end of 2017. Full deployment to all counties is planned over 18 months through the end of 2018. Extended Pilot county deployment to allow adequate time for application stability, user training, and process reviews. Release 3 is planned, subject to federal and state budget approval. Primary features are additional interfaces to external systems and deployment of Social Enterprise Collaboration features.
We are here
2019
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
★
G 2 G 3 G 4 G 5 G 2 G 3 G 4 G 5
★
G 2 G 3 G 4 G 5
★
Conversion and Implementation Deploy Mobile App Pilot Functional Design / JAD (Rel 3) Sprint Development and Test (Rel 3)
Post-Prod Support, Closeout
Subject to Fed and State approval 2Q16 3Q16 4Q16 1Q17 2Q17 User Check Point #3 3Q17 4Q17 1Q18 Pilot 2Q18 3Q18 4Q18
* Denotes phase has been completed
Pilot Group 1 Group 1 Group 1 Start of JADs INT & UAT Fit Gap * Sprint Development and Test Cycles (Rel 1 & 2) Test Planning* User Check Point #1* User Check Point #2* Deploy Release 1 Deploy Release 2 Deploy Release 3
Planning * INT & UAT Functional Design / JAD *
6
7
October
and when data conversions take place
8
via email viewed as “showstoppers” to be addressed before further implementations:
August 7
Checkpoints, UAT)
some of the items raised by the Directors had multiple root cause issues that needed to be addressed individually in order to provide a complete solution
implementing this enhancement requires a complex architectural change to the system
product vendor), to define a solution and resolution timeframe
list – bringing the issue total to 37
9
items
Group 1 Go-Live: Jan. 22 Release 2 Go- Live: Dec. 29
10
system enhancements – further clarification is needed to confirm the projected implementation dates
cleansing) and planning for January go-live
their initial implementation
11
12
New system functionality and change requests (enhancements) for Medicaid will be prioritized by the Business and worked by the development team in Sprints.
Project Team / Role Name Jun-1 7 Jul-1 7 Aug-1 7 Sep-1 7 Oct-1 7 Nov-1 7 Dec-1 7 Jan-1 8 Feb-1 8 M ar-1 8 Apr-1 8 M ay-1 8 Jun-1 8 Jul-1 8 Aug-1 8 Sep-1 8 Oct-1 8 Nov-1 8 Dec-1 8 Jan-1 9 Feb-1 9 M ar-1 9 Apr-1 9 M ay-1 9 Jun-1 9
Deploy ePass Authorize d Rep Phase 1, Linked Accounts Pilot, CR changes for MA Pending Deploy O&M Defect fixes[COC issue, Secure Inbox batch intermitten t failure,Ac Deploy eNotices,P ending app Report changes for dual apps MAD/MQB, Sending emails for enabling/di Deploy QC/Appli cation Monitorin g Redesign ,Foster Care, ePASS Auth Rep Add new Deploy Presum ptive Defect fixes,R eport Card - Discora gement/ Reopen s n Deploy Presum ptive CRs, Revisit system calculat ions for earned income, COLA/ Deploy 8110 Part- 3,NT- Person Registr ation Deploy Presump tive Eligibility reports, 8109, ePASS Renew al s, Gap Filling Rules, Deploy Revamp ePASS, Linked a/cs- RIDP Deploy ePASS Renew a ls Phase 2 (Non- MAGI) Deploy ETL and Report Optimiza tion Phase-1 Deploy Consolid ated Forms/N
Deploy Coordin ated eligibility notice w ith FFM "last touch" Deploy Telepho nic Signatur e Deploy Identity Proofing Deploy Presump tive Eligibility Reports, Add Presump tive Link to Provider Portal Deploy IMD AtRisk batch to chunk based
number
participa nts Deploy Mobility Deploy ABLE Account Project Close-Out
Note:- This deployment schedule for releasing new P9 functionality is subject to change based on several factors like change in priority from business, successful regression testing, performance testing, timing conflicts with other NCFAST functionality etc.
Test Planning Post Production and Rollout Support Requirements
NC FAST P9 Timeline
Pilot Rollout Planning Design/JAD Development Test Execution Test Planning Enterprise Program Integrity Medicaid Self Service Test Execution Design Development
13
The case worker will have the capability to handle discouragement for MAGI and Traditional applications without a signed application.
We have a hospital that is ready to utilize the Presumptive functionality. Several
As part of the corrective action from State Audit finding, Income calculations will be captured in the system.
The Cost of living adjustment process has been automated with a new batch.
For MAGI applications where there is no income evidence, recertification will be carried out by the system without case worker intervention.
The reasons and outcome for the 8110 form are being automated for both Traditional and MAGI products.
14
Scope
NC FAST functionality to support the entry of referrals, investigations, and the tracking of substantiated claims for over-issuances for FNS, Medicaid and Work First programs Requirements Phase
Design-Develop-Test Phase
during design reviews from Alamance, Guilford and Pitt Counties respectively.
15 15
Project 11 – New Medicare Card (Social Security Number Removal Initiative (SSNRI)
Background
removal of the social security number (SSN) from Medicare cards which now displays as a part of the health insurance claim number (HICN).
(MBI) number.
theft. Implementation
downstream partners in February 2018.
16 16
Project 11 – New Medicare Card (Social Security Number Removal Initiative (SSNRI)
Project Status
System Interfaces System Validations Screen Changes
been made, tested and implemented.
upstream file process is being tested. The file has been received from NCTracks and sent to CMS by NC FAST for HICN/MBI validation.
downstream file process testing will occur soon.
CSDW interface file testing is now underway.
validation changes have been made, tested and implemented.
have been made, tested and implemented.
17
Document Management System (DMS) Enhancement (Project 12)
Initial Timeline
18
Status
Document Management System (DMS) Enhancement (Project 12)