Contractor: RJV Construction Corporation Contract Value: $11,235,500 - - PowerPoint PPT Presentation

contractor rjv construction corporation contract value 11
SMART_READER_LITE
LIVE PREVIEW

Contractor: RJV Construction Corporation Contract Value: $11,235,500 - - PowerPoint PPT Presentation

Massachusetts Water Resources Authority MWRA Pipeline Contract No. 7448 Contractor: RJV Construction Corporation Contract Value: $11,235,500 Schedule: November 2014 May 2017 February 11, 2015 MWRA Service Area MWRA provides wholesale


slide-1
SLIDE 1

Massachusetts Water Resources Authority

MWRA Pipeline Contract No. 7448

February 11, 2015

Contractor: RJV Construction Corporation Contract Value: $11,235,500 Schedule: November 2014 – May 2017

slide-2
SLIDE 2

2

MWRA Service Area

  • MWRA provides wholesale water and wastewater services to over 2.5 million customers

in 61 communities

  • On average, MWRA delivers about 200 million gallons per day to its water customers, with

a peak demand of 350 million gallons

  • MWRA collects and treats an average of 350 million gallons of wastewater per day, with a

peak capacity of 1.2 billion gallons

slide-3
SLIDE 3

3 3

Abundant Reservoirs

Quabbin Reservoir Storage: 412 billion gallons Depth: 150 feet Length: 17.9 miles Width: 3 miles Wachusett Reservoir Storage: 65 billion gallons Depth: 129 feet Length: 8.5 miles Width: 1 mile

slide-4
SLIDE 4

4

John J. Carroll Water Treatment Plant

  • Complete in July 2005
  • Treatment Processes:

– Ozone and UV for primary disinfection – Corrosion control – Chloramination for secondary disinfection – Fluoridation

slide-5
SLIDE 5

5

  • Construction of UV facilities at the Carroll Treatment Plant completed last Spring

Addition of UV Disinfection At Carroll Treatment Plant

slide-6
SLIDE 6

Drinking Water Quality I s Excellent

  • MWRA sends an annual report to every

household in the service area

  • Water quality is consistently excellent

6

slide-7
SLIDE 7

7

Renewable Energy At MWRA

slide-8
SLIDE 8

MWRA Metropolitan Water System

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

16

slide-17
SLIDE 17

17

slide-18
SLIDE 18

18

slide-19
SLIDE 19

19

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

MWRA Section 36 Replacement

23

slide-24
SLIDE 24

New MWRA Pipeline – Brunswick Ave and Hillsdale Road

24

slide-25
SLIDE 25
  • To improve the condition of the

existing water main − Hydraulic Capacity − Reliability MWRA Section 36 Replacement - Project Goals

25

  • To provide redundancy and flexibility
  • Avoid potential service disruption (breaks,

leaks)

slide-26
SLIDE 26

MWRA Section 36 - Robbins Road

26

Replace old 16-inch water main with new 24-inch water main

slide-27
SLIDE 27

Replace old 16-inch water main with new 24-inch water main Hawthorne Avenue

slide-28
SLIDE 28
  • Replacement of an existing 16-inch water main with

a new 24-inch water main, valves and appurtenances

  • Installation of a new 36-inch water main, valves and

appurtenances

  • Relocation and replacement of utilities including

water, sewer and drain lines

  • Pavement restoration

MWRA Section 36 Replacement – Project Elements

28

slide-29
SLIDE 29
  • Department of Public Works
  • Police Department - Traffic Unit
  • Fire Department
  • Private Utility Companies
  • Community Residents
  • Conservation Commission

Project Coordination

29

slide-30
SLIDE 30
  • 1. Sewer line inspection and cleaning
  • 2. Conduct pre-construction videos

a. Streetscape b. Residences

  • 3. Rodent Survey
  • a. Develop baseline
  • b. Determine application

Construction Measures

30

slide-31
SLIDE 31

Construction Measures (continued)

31

  • 4. Tree Inspection

a. Trimming/pruning b. Fertilizing c. Removal

  • 5. Pre-drilling on Brunswick (March 2015)
  • 6. Paving

a. Temporary paving for 1 construction season b. Permanent paving approximately 1 season later

  • 7. Post construction survey
slide-32
SLIDE 32

Construction Measures (continued)

32

  • 8. Temporary water bypass installation with

service interruptions (100 houses)

  • Advance notice to residents
  • Hours 9:00AM – 4:00PM
slide-33
SLIDE 33

Tentative Construction Schedule continued

33

STREET SCHEDULE Brattle St to Massachusetts Ave Installing 24” MWRA water main March – May 2015 Massachusetts Ave Installing 24” MWRA water main May – June 2015 Robbins Rd from Mass Ave to Gray St Installing 24” MWRA water main, 8” sewer and portions of 8” water and 15” drain June – September 2015 Robbins Rd from Gray St to Hawthorne Ave Installing 24” MWRA water main August – November 2015 Hawthorne Ave from Robbins Rd to Park St Installing 24” MWRA water main November - December 2015 Park Ave Installing 24” MWRA water main and 12” drain March 2016 – August 2016

slide-34
SLIDE 34

Tentative Construction Schedule

34

STREET SCHEDULE Brunswick Rd Installing 36” MWRA water main, 8” sewer and 8” water March 2015 – July 2015 Hillsdale Rd Installing 36” MWRA water main, 8” sewer and 8” water July 2015 – September 2015 Pleasant St at Brunswick Rd Installing 54” MWRA water main, 8” sewer and 8” water September 2015 – November 2015 Spring St at Hillsdale Rd Installing 36” MWRA water main, 8” water and 12” drain October 2016 – December 2016

slide-35
SLIDE 35

Similar Construction

35

slide-36
SLIDE 36

Similar Construction

36

slide-37
SLIDE 37

Jeff McLaughlin (617) 305-5762 jeffrey.mclaughlin@mwra.com

MWRA Contact I nformation

37