Contractor Awareness and Contractor Awareness and Prequalification - - PowerPoint PPT Presentation

contractor awareness and contractor awareness and
SMART_READER_LITE
LIVE PREVIEW

Contractor Awareness and Contractor Awareness and Prequalification - - PowerPoint PPT Presentation

Contractor Awareness and Contractor Awareness and Prequalification Meeting Prequalification Meeting Agenda Agenda Program Overview Contract Package 1 Contract Package 2 Contract Package 3 Contract Package 4 Contract Package


slide-1
SLIDE 1

Contractor Awareness and Prequalification Meeting Contractor Awareness and Prequalification Meeting

slide-2
SLIDE 2

Agenda

Agenda

Program Overview

  • Contract Package 1
  • Contract Package 2
  • Contract Package 3
  • Contract Package 4
  • Contract Package 5
  • Contract Package 6

Program Schedule Contractor Prequalification

slide-3
SLIDE 3

Program Overview

slide-4
SLIDE 4
slide-5
SLIDE 5

Great Lakes Water Supply Program

City of Waukesha

  • Population – 71,970 (2015)
  • Incorporated in 1896
  • Urban hub of Waukesha County
  • Largely developed
  • Growth rate: less than 1% per year
  • Waukesha Water Utility – 20,250 Customers
  • 92% Residential
  • Department of Justice mandated
  • 50% Complete by May 1 2022
  • Operational by August 31, 2023
  • Abandon existing potable water source
  • Transition to Lake Michigan water source via

City of Milwaukee supply

slide-6
SLIDE 6

Great Lakes Water Supply Program

slide-7
SLIDE 7

Great Lakes Water Supply Program

Great Water Alliance

Owner: Construction Manager: Program Manager/ Design Engineer:

Dan Duchniak, P.E., General Manager Kelly Zylstra, P.E., Operations Manager Chris Walter, P.E., Technical Services Manager Catherine Richardson, P.E., Program Manager Ryan Christopher, P.E., Deputy Program Manager Chris DeSilva, P.E., Deputy Program Manager James Cobb, CCM, Construction Manager Jeff Champion, CCM, Deputy Construction Manager

slide-8
SLIDE 8

Great Lakes Water Supply Program

Contract Packages

  • CP1: Milwaukee Oklahoma Pumping Station
  • CP2: Return Flow Pipeline, BPS Discharge Pipeline, Water Supply Pipeline Section I, II and III and Station

Suction Pipeline

  • CP3: Booster Pump Station, Storage and Chemical Facilities
  • CP4: Return Flow Pumping Station
  • CP5: Return Flow Pipeline (Waukesha to I-43)
  • CP6: Return Flow Pipeline (I-43 to Outfall at Root River), 18-in Sanitary Sewer and Outfall Facilities
slide-9
SLIDE 9
slide-10
SLIDE 10

Great Lakes Water Supply Program

Funding

  • Environmental Protection Agency (EPA)
  • Water Infrastructure Finance and Innovation Act (WIFIA)
  • Wisconsin Department of Natural Resources (WDNR)
  • Safe Drinking Water Loan Program (SDWLP)
  • Clean Water Loan Program (CWLP)

Other Program Requirements

  • Disadvantaged Business Enterprise (DBE) 10%
  • Local Contractor Participation (State of Wisconsin) 30%
  • Davis-Bacon Requirements
  • American Iron and Steel
slide-11
SLIDE 11

Great Lakes Water Supply Program

CP1: City of Milwaukee – Oklahoma Pumping Station

  • Design by Greeley and Hansen
  • Administered by City of Milwaukee
  • West Oklahoma Avenue & South 76th Street
  • Packaged Pumping Station
  • Packaged Engine Generator System
  • Estimated Construction Cost: $7.9M
slide-12
SLIDE 12

Great Lakes Water Supply Program

CP1: Milwaukee Oklahoma Pumping Station

Proposed Oklahoma Pump Station Location

slide-13
SLIDE 13

Great Lakes Water Supply Program

CP2: Return Flow Pipeline, BPS Discharge Pipeline, Water Supply Pipeline Section I, II and III and Station Suction Pipeline

  • 65,000 LF of 24”, 30” and 36” DIP
  • Average Depth: 10-15 feet
  • Trenchless Technology
  • Jack and Bore
  • Steel Casing, Ductile Iron Carrier Pipe
  • 8 crossings; 1,550 LF total
  • Horizontal Direction Drill
  • 4 crossings; 2,500 LF total; HDPE
  • Currently 90% Design
  • Estimated Construction Cost: $49.9 - $63.8M
slide-14
SLIDE 14

Great Lakes Water Supply Program

CP2: Return Flow Pipeline, BPS Discharge Pipeline and Water Supply Pipeline

  • 70% Urban/Residential
  • 30% Rural
slide-15
SLIDE 15

Great Lakes Water Supply Program

CP2: Return Flow Pipeline, BPS Discharge Pipeline and Water Supply Pipeline

  • Potential Challenges
  • Natural Gas Transmission Main

Crossing

slide-16
SLIDE 16

Great Lakes Water Supply Program

CP3: Booster Pump Station, Storage and Chemical Facilities

  • South Racine Avenue (CTH Y) and South

Swartz Road

  • 15.8 MGD firm capacity
  • Two 8 MG Prestressed Concrete Reservoirs
  • Chemical Feed Facilities
  • Water Supply Control Building
  • Currently 90% Design
  • Estimated Construction Cost: $36.6 - $46.8M
slide-17
SLIDE 17

Great Lakes Water Supply Program

CP3: Booster Pump Station, Storage and Chemical Facilities

slide-18
SLIDE 18

Great Lakes Water Supply Program

CP3: Booster Pump Station, Storage and Chemical Facilities

slide-19
SLIDE 19

CP3: Water Supply Control Building

Great Lakes Water Supply Program

Proposed Point of Connection Location

slide-20
SLIDE 20

Great Lakes Water Supply Program

CP3: Water Supply Control Building

slide-21
SLIDE 21

Great Lakes Water Supply Program

CP4: Return Flow Pump Station and Miscellaneous CWP Improvements

  • Waukesha Clean Water Plant
  • Includes Phosphorous Upgrades
  • Design and Administered by Jacobs
  • Currently 60% Design
slide-22
SLIDE 22

Great Lakes Water Supply Program

CP4: Return Flow Pump Station

slide-23
SLIDE 23

Great Lakes Water Supply Program

CP5: Return Flow Pipeline

  • 47,000 LF of 24”, 30” and 36” DIP
  • Average Depth: 10-15 feet
  • Trenchless Technology
  • Jack and Bore
  • Steel Casing, Ductile Iron Carrier Pipe
  • 7 crossings; 1,300 LF total
  • Horizontal Direction Drill
  • 6 crossings; 4,000 LF total; HDPE
  • Currently 90% Design
  • Estimated Construction Cost: $28.2 - $39.9M
slide-24
SLIDE 24

Great Lakes Water Supply Program

CP5: Return Flow Pipeline

  • 20% Interstate
  • 10% Industrial
  • 25% Urban/Residential
  • 45% Rural
slide-25
SLIDE 25

Great Lakes Water Supply Program

CP5: Return Flow Pipeline Potential Challenges

  • 4 Railroad Crossing
  • Sunset Avenue between South West and Industrial Lane
  • Train runs approximately every 30 minutes to 1 hour
  • Jack and Bore under tracks
  • I-43 corridor and crossing
  • Racine Avenue to 1800 ft east of Calhoun Road
  • Jack and Bore crossing
slide-26
SLIDE 26

Great Lakes Water Supply Program

CP5: Return Flow Pipeline Potential Challenges

  • Natural Gas Transmission Main Crossing
  • South Racine Avenue south of West Lawnsdale Road
  • Horizontal Directional Drill under gas main
slide-27
SLIDE 27

Great Lakes Water Supply Program

CP6: Return Flow Pipeline, 18-in Sanitary Sewer and Outfall Facilities

  • 52,000 LF of 24”, 30” and 36” DIP
  • Average Depth: 10-15 feet
  • 4,000 LF of 18” PVC
  • Average Depth: 20-45 feet
  • Trenchless Technology
  • Jack and Bore
  • Steel Casing, Ductile Iron Carrier Pipe
  • 4 crossings; 800 LF total
  • Horizontal Direction Drill
  • 8 crossings; 6,200 LF total; HDPE
  • Currently 90% Design
  • Estimated Construction Cost: $42.1 - $64.6M
slide-28
SLIDE 28

Great Lakes Water Supply Program

CP6: Return Flow Pipeline, 18-in Sanitary Sewer and Outfall Facilities

  • 10% Industrial
  • 25% Residential
  • 65% Rural
slide-29
SLIDE 29

Great Lakes Water Supply Program

CP6: Return Flow Pipeline, 18-in Sanitary Sewer and Outfall Facilities Potential Challenges

  • Root River Crossing
  • West Ryan Road west of South 60th Street
  • Horizontal Directional Drill under river
slide-30
SLIDE 30

Great Lakes Water Supply Program

CP6: Return Flow Pipeline, 18-in Sanitary Sewer and Outfall Facilities Potential Challenges

  • 18” Sanitary Sewer
  • South 60th Street from Ryan

Road to 650 feet south of West Franklin Drive

  • 18” PVC
  • 20 to 45 ft deep
  • Manhole Spacing 500’ max.
slide-31
SLIDE 31

Great Lakes Water Supply Program

CP6: Return Flow Pipeline, 18-in Sanitary Sewer and Outfall Facilities Outfall Facilities

  • South 60th Street and West Oakwood Road at Root River
slide-32
SLIDE 32

Program Schedule

slide-33
SLIDE 33

Program Schedule

slide-34
SLIDE 34

Program Schedule

  • Contractor Prequalification
  • Questions: July 17, 2019
  • Applications Accepted through: July 31, 2019
  • Notification: Fall 2019
  • Bidding: Winter 2019/2020
  • One pipeline contract package and one facilities contract package likely to be bid in parallel
  • 2 – 4 Weeks between Bidding groups
  • Mandatory Pre-Bid Meeting for each Contract Package
  • Start of Construction: Spring 2020
  • D.O.J. Certification 50% Completion: May 1, 2022
  • Program must by 50% Complete
  • Program Final Completion: August 31, 2023
slide-35
SLIDE 35

Contractor Prequalification

slide-36
SLIDE 36

Contractor Prequalification

  • General Contractor
  • First-Tier Subcontractor (Major Subcontractors)

A first-tier subcontractor is defined as a subcontract awarded directly by the Contractor for the purpose of acquiring supplies or services (including construction) for performance of a prime contract. It does not include the Contractor's supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a contractor's general and administrative expenses or indirect costs.

  • Trenching and Excavation Contractor
  • Underground Utilities Installation Contractor
  • Trenchless Technologies Contractor
  • Electrical Contractor
  • Mechanical Contractor
  • Plumbing Contractor
slide-37
SLIDE 37

Contractor Prequalification

  • Procedure
  • Application
  • Prequalification Statement
  • Questionnaire
  • Essential Requirements
  • Organization, History, Compliance with Laws
  • Recent Projects
  • Scoring Form
slide-38
SLIDE 38

Contractor Prequalification

Prequalification Statement

  • Prequalification Request
  • Facilities Contract Packages (Contract Package 3)
  • Pipeline Contract Packages (Contract Packages 2, 5 & 6)
  • Both Facility and Pipeline Contract Packages
  • Contractor Status
  • General Contractor
  • First-Tier Subcontractor
  • Both
  • Company Structure
  • Corporation
  • Partnership
  • Sole Proprietor
  • Joint Venture (Teamed or Planning)
slide-39
SLIDE 39

Contractor Prequalification

Questionnaire

  • Part I – Essential Requirements for Prequalification
  • Contractor may be immediately disqualified if the answer to questions 1 through 7 is “No”
  • Contractor may be immediately disqualified if the answer to questions 8 through 11 is “Yes”
  • Part II – Organization, History, Performance, Compliance with Civil and Criminal Laws
  • Unless noted otherwise, each question, in section B through H, is scored either 0 or 5 points
  • The highest possible score for these questions is 185 points
  • A minimum score of 160 points is required for the contractor to be considered eligible
  • Part III – Recent Projects
  • Each question is scored either 0 or 5 points
  • The highest possible score for these questions is 140 points
  • A minimum score of 120 points is required for the contractor to be considered eligible
  • Part IV – Requested Additional Information
  • Each question is scored either 0 or 5 points
  • The highest possible score for these questions is 20 points
  • A minimum score of 20 points is required for the contractor to be considered eligible
slide-40
SLIDE 40

Contractor Prequalification

slide-41
SLIDE 41

Contractor Prequalification

Questions and Request for Information

  • In writing, e-mail
  • July 17, 2019 at 12:00 PM CDT
  • Directed to:
  • Jim Cobb, Black & Veatch – CobbJR@bv.com
  • Jeff Champion, Black & Veatch – ChampionJA@bv.com
  • Cc: Kelly Zylstra, Waukesha Water Utility – Kzylstra@Waukesha-water.com
  • Addendum notification through QuestCDN
slide-42
SLIDE 42

Question Answer

Using Great Lakes Water the Right Way