Contract R-39093 I-69 Added Travel Lanes and Preventive Maintenance Delaware and Madison County Contract R-39093 ROADWAY IMPROVEMENTS: Limits of Added Travel Lanes (8 miles) vs. Pavement Rehabilitation (6 miles) Rehabilitation of 20


  1. Contract R-39093 I-69 Added Travel Lanes and Preventive Maintenance Delaware and Madison County

  2. Contract R-39093 ROADWAY IMPROVEMENTS:  Limits of Added Travel Lanes (8 miles) vs. Pavement Rehabilitation (6 miles)  Rehabilitation of 20 bridges 2

  3. Contract R-39093 Project Scope (continued)  New Signs  New Interchange Lighting  New Traffic Signals  New Pavement Markings  New Guardrail / Safety Features  Wetland Mitigation 3

  4. Contract R-39093 I-69 MAINTENANCE OF TRAFFIC:  Work Zone Speed Limit shall be 55 mph.  Work Site Speed Limit shall be 45 mph.  Two lanes of traffic shall be maintained in each direction with the use of crossovers and contra-flow lanes.  Night-time lane closures will be used  Local detour routes will be used during closure of Columbus Ave. and CR 400 W 4

  5. Contract R-39093 ASPHALT TEST STRIPS :  In the Added Travel Lanes Sections, twenty two different test strips will be constructed.  Primary objective: to explore options for more cost-effective pavement structures 5

  6. I-69 Design Build

  7. Added Travel Lanes Phase 2 Build Inside Lanes Shoulder and Median Southbound Northbound

  8. Added Travel Lanes Phase 3 Patch and Mill Proposed Center Lanes Southbound Northbound

  9. Added Travel Lanes Phase 4 Patch and Mill Existing Right Lane Southbound Northbound

  10. Preventative Maintenance Overlay Phase 3A Construction Phasing Southbound Northbound

  11. Preventative Maintenance Overlay Phase 4A Construction Phasing Southbound Northbound

  12. Contract R-39093 Project Schedule  Begin Construction: Late June / Early July 2018  Columbus Avenue Closure: Fall 2018  CR 400 W Closure: April – July 2019  SR 9 / 109 Restrictions: 2019  SR 9 / 67 Restrictions: 2019  Project Completion: - November 2019 1 2

  13. Thank you! 1 3

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.