Contract award status Includes enhancements to the station access - - PowerPoint PPT Presentation

contract award status
SMART_READER_LITE
LIVE PREVIEW

Contract award status Includes enhancements to the station access - - PowerPoint PPT Presentation

P OTOMAC Y ARD M ETRORAIL S TATION P ROJECT Potomac Yard Civic Association Project Update August 20, 2018 M EETING P URPOSE Contract Award Next Steps Station Access Ongoing Communication 2 PYCA| August 20, 2018 WMATA D ESIGN -B


slide-1
SLIDE 1

POTOMAC YARD METRORAIL STATION PROJECT

Potomac Yard Civic Association Project Update August 20, 2018

slide-2
SLIDE 2

PYCA| August 20, 2018

MEETING PURPOSE

  • Contract Award
  • Next Steps
  • Station Access
  • Ongoing Communication

2

slide-3
SLIDE 3

PYCA| August 20, 2018

WMATA DESIGN-BUILD CONTRACT AWARD

  • Contract award status
  • Includes enhancements to the station access from

East Glebe Road

  • Contractor’s representative will be at next PYMIG

meeting on September 26.

3

slide-4
SLIDE 4

PYCA| August 20, 2018

CITY PLAN APPROVAL PROCESS

  • Initial application for DSUP amendment submitted by staff on

July 18, 2018

  • PYMIG meeting on September 26, October, and November
  • Planning Commission and City Council Public Hearings

anticipated in December

  • Board of Architectural Review meetings

4

slide-5
SLIDE 5

PYCA| August 20, 2018

PROJECT DESIGN AND PERMITTING

  • Design will commence in Fall 2018 and continue thru the

Fall of 2019

  • Integrated Project Team

– Contractor – WMATA – City

  • Permitting

5

slide-6
SLIDE 6

PYCA| August 20, 2018

STATION ACCESS

  • Contract includes enhancements to access from

East Glebe Road

  • Refine station access from Potomac Greens
  • Public input will be sought on design options at

PYMIG meetings

6

slide-7
SLIDE 7

PYCA| August 20, 2018

STATION ACCESS POINTS

7

slide-8
SLIDE 8

PYCA| August 20, 2018

CONSTRUCTION ACTIVITY

8

slide-9
SLIDE 9

PYCA| August 20, 2018

CONSTRUCTION TIMELINE

  • Late 2018 – Pre-design site activity
  • Late 2019 – Site preparation
  • Early 2020 – Initiation of station construction
  • Early 2022 – Project completion
  • Contractor will provide a schedule

9

slide-10
SLIDE 10

PYCA| August 20, 2018

INITIAL ON-SITE ACTIVITIES

  • Contractor information gathering activities on-

site

  • Mobilize office trailers, laydown areas, and

parking facilities

  • Bulk of the effort for the first year will be

Design and Permitting

  • Pre-construction survey of surrounding

properties

10

slide-11
SLIDE 11

PYCA| August 20, 2018

INITIAL ON-SITE ACTIVITIES

  • Pre-design activities:

– Land Surveying – Geotechnical Investigations – Pre-Construction Assessment of Adjacent Buildings – Utility Locations and Condition Assessment

  • Fencing, clearing, and erosion protection

measures associated with this work

11

slide-12
SLIDE 12

PYCA| August 20, 2018

PROJECT MAP

12

slide-13
SLIDE 13

PYCA| August 20, 2018

CONSTRUCTION IMPACTS AND MITIGATION

13

Potential Impacts Potential Mitigation

Construction Traffic & Parking Hour of Operation Bus Workers Secure Site Inspector Presence Contaminated Soils Testing of Materials Prior to Removal Ensure Proper Handling Soil Management Plan Night Work Provide Advance Notice Minimize Frequency

slide-14
SLIDE 14

PYCA| August 20, 2018

COMMUNICATION

  • Project updates provided:

– PYMIG meetings – Briefings at regular PYCA meetings – Pertinent information provided to PYCA leadership, and disseminated to members – Project website – Alexandria eNews – Call or email Jason or Mitch directly

14

slide-15
SLIDE 15

PYCA| August 20, 2018

UPCOMING PROJECT SCHEDULE

15

Aug 2018 Sep Oct Nov Dec Jan 2019

WMATA Contract Award and Notice to Proceed

DSUP Amendment Initial Submission

Community Outreach PYMIG

DSUP PC and City Council Consideration

Initial On-Site Activities* * survey, geotechnical investigations, utility locations, construction trailers