Contents A Typical PPP Structure Key Investor Issues Key - - PowerPoint PPT Presentation

contents
SMART_READER_LITE
LIVE PREVIEW

Contents A Typical PPP Structure Key Investor Issues Key - - PowerPoint PPT Presentation

Public Private Partnerships Opportunities and Challenges 22 February 2005 Jonathan Drew HSBC Corporate, Investment Banking and Markets 1 Contents A Typical PPP Structure Key Investor Issues Key Bankability Issues Successful


slide-1
SLIDE 1

1

Public Private Partnerships – Opportunities and

Challenges

22 February 2005

Jonathan Drew

HSBC Corporate, Investment Banking and Markets

slide-2
SLIDE 2

Contents

  • A Typical PPP Structure
  • Key Investor Issues
  • Key Bankability Issues
  • Successful Implementation of a PPP Programme
  • PPP Implementation Process
  • Finance Instruments
  • Sources of Private Capital
  • Hong Kong Market – key developments
  • Hong Kong Case Studies

2

slide-3
SLIDE 3

A Typical PPP Structure

Government Special Purpose Vehicle Debt Operation Construction

Payment for service Finance Services

Equity

3

slide-4
SLIDE 4

Key Investor Issues

  • Clear policy and commitment for the Investment programme

– Government obligation undertaken by appropriate entities – Letting authorities adequately resourced and empowered for decision making – Clarity on budget and affordability constraints – Clarity on competing or complementary developments

  • Allocation of Risk and Reward

– Risks must be clearly defined and appropriately allocated by contractual framework – Appropriate level of returns to private sector for risks undertaken

  • Project Structure

– Contractual arrangements structured to facilitate debt financing and optimise

  • verall cost of capital

– Output specification clearly defined on long term basis

4

slide-5
SLIDE 5

Key Bankability Issues

  • Clear contractual framework for allocation of risks
  • Adequate security on project assets
  • Proven track record of payment and performance by participants
  • Ability to step into project
  • Alternative suppliers
  • Adequate reorganisation or protection against changes in underlying project economics

and specifications

5

slide-6
SLIDE 6

Successful Implementation of a PPP Programme

  • Good project selection
  • Transparency of evaluation approach
  • Engage in prequalification and expression of interest to some broad stakeholder support

and commitment to project

  • Well defined bid package with clear assessment criteria and output specifications
  • Establishment of enabling legislative and regulatory framework
  • Project teams with appropriate skills to structure and evaluate the bids and negotiate the

contracts

6

slide-7
SLIDE 7

PPP Implementation Process

  • Identify the requirement
  • Initial feasibility and assessment of

value to Government - PSC

  • Initial prequel and expression of

interest

  • Request for proposal
  • Review and evaluation of

submissions

  • Negotiations and selection of

preferred bidder

  • Negotiation with preferred bidder
  • Commercial close

Procurement

Involve industry private sector?

Financing Process

  • Obtain financing proposals
  • Due diligence

– Insurance – Technical/Environmental – Financial – Commercial – Legal Due Diligence

  • Documentation
  • Syndication of loan
  • Financial Close

7

slide-8
SLIDE 8

Finance Instruments

Senior Debt – 60 – 90% of Capital Value Project Equity – 10 – 30% of Capital Value Project Funding Project Cashflows Senior Debt (Bank / Bond)

  • Typically long dated debt, amortising over the

period of the Infrastructure Asset / Concession Contract: Generally fixed rate debt Equity

  • Typically injected either as share capital or

subordinated debt

  • Stable base yield can be enhanced by tax

benefits, third party recourse or residual value

  • f asset

8

slide-9
SLIDE 9

Sources of Private Capital

  • Long term senior debt provided through domestic or international banking and capital

markets

  • Developed capital markets can offer longer dated fixed price financing than bank

markets – will require rating

  • Bank financing may offer more flexible financing structure than capital markets
  • Primary Equity providers remain the sponsors. Increasing interest to provide equity by

financial institutions and investors attracted to stable long term yield

9

slide-10
SLIDE 10

Hong Kong Market - key developments

  • Fewer international banks operating locally are seeking to book project assets
  • But the local Hong Kong and PRC banks remain very keen – subject to relationships and

policy

  • The local HK$ capital markets have been greatly developed – including the retail investor

base – monolines willing to wrap - however, the loan market will offer long maturities in HK$

  • Hong Kong economic and currency issues remain in lenders and investors focus
  • Several Government initiatives to test the local and international appetite for Hong Kong

project risk post 1997

  • HK sponsors remain strong enough to invest in Hong Kong, but are opportunities better

elsewhere?

10

slide-11
SLIDE 11

Case Study - Infrastructure - AsiaWorld Expo

Project Description

  • Design, build and operate a new 100,000m2 exhibition centre at Hong

Kong International Airport over a 25 year concession period

  • Initial phase of 66,000m2 to be followed by an expansion to take it up to

100,000m2

  • Tender invitations issued to 4 short listed bidders after more than 20

parties who have expressed interest

  • Project involves the formation of a JV between public and private

sectors with Government contributing HK$2bn in equity and the land. Size

  • Construction costs of approx HK$4bn (HK$2.4 for Phase 1 and

HK$1.6bn for Phase 2) HSBC Role

  • Advisor to the successful bidding consortium led by Dragages et

Travaux Publics HK Ltd (Bouygues)

Asia World Expo Hong Kong

(Dragages et Travaux Publics, NEC, Yu Miing Investments)

Project International Exhibition Cen Awarding Authority Hong Kong SAR Government tre

11

slide-12
SLIDE 12

Case Study - Infrastructure - AsiaWorld Expo

Contractual Structure

Asia World Expo Hong Kong

(Dragages et Travaux Publics, NEC, Yu Miing Investments)

Project International Exhibition Cen Awarding Authority Hong Kong SAR Government tre

12

slide-13
SLIDE 13

Case Study - Infrastructure - AsiaWorld Expo

Project Structure

  • JVCO to be formed between with Government and Airport Authority

(“Holdings” : 76.5%) and the private consortium (“JVP” : 13.5%)

  • Airport Authority contributed land deemed worth 10%, meaning effective

project cost of HK$2.65bn

  • Holdings shareholding via ordinary shares and JVP via preference

shares, allowing JVP priority access to dividends over Holdings

  • JVCO separated from OPCO to minimise risks to JVP shareholders from
  • perational and market risks
  • Government sought to create a structure such that it was in the interests
  • f the private consortium to minimise construction costs, but also to

ensure an operationally efficient design to ensure project value for money

  • Financing for Phase 1 via equity from Government (HK$2bn) & private

consortium (HK$0.4bn)

  • Phase 2 expected to be debt financed with no Government contribution

Asia World Expo Hong Kong

(Dragages et Travaux Publics, NEC, Yu Miing Investments)

Project International Exhibition Cen Awarding Authority Hong Kong SAR Government tre

13

slide-14
SLIDE 14

Case Study - Transport - Western Harbour Crossing

Western Harbour Tunnel Company Limited

(CHT, China Merchants, CITIC, Kerry)

Project Western Harbour Crossing Awarding Authority Hong Kong SAR Government

Project Description

  • Design, build and operate a dual three lane tunnel crossing linking Kowloon to Hong

Kong Island

  • 100% private sector financing
  • Automatic toll adjustment mechanism
  • Challenging legislative process

Size

  • HK$5.2bn (of HK$7.5bn)

HSBC Role

  • Advisor and Arranger to private sector consortium

Financial close Dec 1993 Loan tenor 15 years Loan pricing 100 – 150 bp Leverage 70% Structural Complexity moderate Bank appetite >20 after syndication

14

slide-15
SLIDE 15

Case Study - Transport - Western Harbour Crossing

WHC Ordinance Deed of guarantee Deed of shareholder support Shareholders HK Government Project Agreement (30 year franchise)

Project Company

Loan Agreement Construction Contract (LSTK) Lenders Contractors Independent Traffic study Independent Traffic Consultant WHC Ordinance Deed of guarantee Deed of shareholder support Shareholders HK Government Project Agreement (30 year franchise)

Project Company

Loan Agreement Construction Contract (LSTK) Lenders Contractors Independent Traffic study Independent Traffic Consultant Western Harbour Tunnel Company Limited

(CHT, China Merchants, CITIC, Kerry)

Project Western Harbour Crossing Awarding Authority Hong Kong SAR Government

Contractual Structure

15

slide-16
SLIDE 16

Case Study - Transport - Western Harbour Crossing

Western Harbour Tunnel Company Limited

(CHT, China Merchants, CITIC, Kerry)

Project Western Harbour Crossing Awarding Authority Hong Kong SAR Government

Project Structure

  • Innovative swap mechanism to reduce interest rate risk borne by the project

company

  • Development of a completely new toll adjustment mechanism based on the

cashflows available to the project company which achieved a low initial toll and steady increases thereafter such that the project company was insulated to a great extent from volume risk.

  • The mechanism was included in the Ordinance and avoided the need for

Government approvals. This allowed for a significantly long debt tenor of 15 years, competitive pricing and set the standard for future toll road financings in Hong Kong.

  • Investor has an agreed rate of return:
  • if cashflow is above return cap, then extra cashflow is channelled into a

“toll stability fund”

  • if cashflow if below return floor, investor has the right to:
  • draw from the stability fund
  • adjust the toll level
  • Government does not take traffic volume risk

16

slide-17
SLIDE 17

Thank You

17