CONTAMINATION FEASIBILITY STUDY Stakeholder Meeting Wednesday, - - PowerPoint PPT Presentation

contamination feasibility
SMART_READER_LITE
LIVE PREVIEW

CONTAMINATION FEASIBILITY STUDY Stakeholder Meeting Wednesday, - - PowerPoint PPT Presentation

Item XI. LMRWMO Meeting 11-13-13 THOMPSON LAKE PAH CONTAMINATION FEASIBILITY STUDY Stakeholder Meeting Wednesday, October 30, 1:00 pm PRESENTATION OVERVIEW Project Overview/Project 1. History PAH Contamination 2. Current Project Goals


slide-1
SLIDE 1

THOMPSON LAKE PAH CONTAMINATION FEASIBILITY STUDY

Stakeholder Meeting Wednesday, October 30, 1:00 pm

Item XI. LMRWMO Meeting 11-13-13

slide-2
SLIDE 2

PRESENTATION OVERVIEW

1.

Project Overview/Project History

2.

PAH Contamination

3.

Current Project Goals

4.

Initial List of Alternatives / Pros & Cons – STAKEHOLDER INPUT NEEDED

5.

Regulatory Issues – STAKEHOLDER INPUT NEEDED

6.

Other Questions / Suggestions / Concerns / Next Steps

slide-3
SLIDE 3

Location Map and Drainage Area

slide-4
SLIDE 4

Lake Inlet and Area of Concern

Inlet Area (Potential Sediment Forebay Area) Main Inlet

slide-5
SLIDE 5

Lake Inlet and Area of Concern

Inlet Area (Potential Sediment Forebay Area) Sediment Plume Main Inlet

slide-6
SLIDE 6

Lake Inlet and Area of Concern

Inlet Area (Potential Sediment Forebay Area) Contamination Extents – Initial Testing Main Inlet

slide-7
SLIDE 7

Additional Sampling

Further testing indicated that PAH contamination is present throughout the lake

slide-8
SLIDE 8

PAHs – Description

  • What are PAHs?
  • Polycyclic Aromatic Hydrocarbons – specific group of over 100

chemicals, natural and man-made

  • Most bound to sediment
  • Products of incomplete combustion (fossil fuels, forest fires, coal

tar, etc.) – very common in nature and in urban environments

  • Coal tar based sealant identified as a major contributor (already

banned in West St. Paul; banned statewide as of Jan. 1, 2014)

slide-9
SLIDE 9
  • Primary Concerns
  • Ecological health risks – bottom-dwelling organisms, others
  • Human health risks - many are known or probable carcinogens
  • PAHs accumulate in water bodies (sediment)
  • Dredged PAH-contaminated sediment considered a health risk
  • Two categories of PAH concern:

1.

PAHs in sediment dredged out of water body (more exposure)

2.

PAHs in sediment that stays in water body (less exposure)

PAHs – Concerns

slide-10
SLIDE 10

PAHs: Stormwater Pond Vs. Lake

  • Stormwater Treatment Ponds
  • Stormwater treatment requires a certain amount of storage volume
  • Many ponds have reached their design life and require

maintenance dredging

  • PAH contamination showing up at high concentrations - in many

ponds at levels requiring landfilling of dredged material (high cost)

slide-11
SLIDE 11

PAHs: Stormwater Pond Vs. Lake

  • Lakes and Wetlands
  • Natural water bodies – not designed “stormwater ponds”
  • Not the same impetus (storage volume) for maintenance
  • Many act as a “treatment” areas for stormwater runoff
  • Retrofitting a treatment “forebay” provides a defined area for

sediment accumulation

slide-12
SLIDE 12

Current Project Goals

  • Improve Problem

Definition

  • Review Latest PAH

Research

  • Evaluate All

Management Options

  • Address Stakeholder

Goals / Concerns

slide-13
SLIDE 13

Initial List of Alternatives / Pros & Cons

1) No-Action Alternative 2) Construct Settling Basin and Dredge Sediment Plume –

Disposal in Landfill

3) Construct Settling Basin and Dredge Limited Area –

Disposal in Landfill

4) Construction of Settling Basin Only 5) Alternative: Nearby Disposal Site – MPCA Pilot Project 6) Alternative: In-Situ Treatment Pilot Project – Methods

Under Consideration

STAKEHOLDER INPUT NEEDED

slide-14
SLIDE 14
  • 1. No-Action Alternative
  • Leave as-is; no excavation or construction
  • May include continued studies/monitoring
  • Pros
  • No immediate costs for construction or excavation
  • Maintains status quo – low risk of making things drastically worse
  • May be able to take advantage of future technical or regulatory

developments

  • Cons
  • Does nothing to address ongoing pollution of the Lake
  • Pushes the problem into the future
  • Largely wastes the effort and funding invested up to this point
  • Cost Range: $0 - $50,000 (studies/monitoring)
slide-15
SLIDE 15
  • 2. Construct Settling Basin and Dredge

Sediment Plume – Disposal in Landfill

  • Original proposed alternative
  • Full cleanout and construction of sediment pond
  • Pros
  • Takes contaminated and excess sediment out of Lake
  • Landfilling sediment eliminates any further exposure risk
  • Provides stormwater treatment at Lake inlet
  • Cons
  • High cost
  • Uncertain level of benefit
  • Potential risk of contaminant resuspension during excavation
  • Cost Range: $1,000,000 - $1,500,000
slide-16
SLIDE 16
  • 3. Construct Settling Basin and Dredge

Limited Area – Disposal in Landfill

  • Reduced dredging footprint – based on level of

contamination, budgetary limits, or other considerations

  • Construct sediment pond at inlet
  • Pros
  • Removes some sediment from Lake based on specific criteria
  • Reduced cost relative to the “full cleanout” option
  • Still provides stormwater treatment at Lake inlet
  • Cons
  • Still involves substantial excavation costs
  • Uncertain benefit / contaminant resuspension concerns remain
  • Cost Range: $500,000 - $1,000,000 depending on

specifics

slide-17
SLIDE 17
  • 4. Construct Settling Basin Only
  • Construct proposed sediment pond/forebay at Lake inlet

(storm sewer outfall)

  • Highly contaminated sediments would be landfilled
  • Do not excavate or do other work in main body of Lake
  • Pros
  • Provides stormwater treatment at Lake inlet
  • Eliminates costs of dredging within main body of Lake
  • Reduces or eliminates concerns about contaminant resuspension
  • Cons
  • Does not immediately address concerns in main body of Lake
  • Cost Range: $300,000 - $500,000
slide-18
SLIDE 18
  • 5. Alternative: Nearby Disposal Site – MPCA

Pilot Project

  • Place sediment nearby and cap (per MPCA guidance)
  • Disposal alternative for any of the listed options
  • Pros
  • Eliminates need for landfilling, drastically reducing disposal costs
  • Adds to knowledge base regarding sediment management options
  • Cons
  • Land required nearby; PAHs are present (but not exposed)
  • Consumes / modifies landscape area
  • Cost Range: Can reduce project cost by 50% or more
slide-19
SLIDE 19
  • 6. Alternative: In-Situ Treatment Pilot Project
  • In-situ remediation pilot project in main body of Lake (along

with forebay construction)

  • Pacific Northwest National Laboratory has done similar

research in saline environment; interested in participating

  • Phytoremediation and bioaugmentation
  • Pros
  • Stormwater treatment at Lake inlet would still be provided
  • Could result in reduction of PAH concentrations in sediment
  • Adds to knowledge base regarding PAH remediation
  • Cons
  • Pilot project is experimental; may not achieve desired results
  • Cost Range: Adds cost of pilot project ($50,000 - $150,000)
slide-20
SLIDE 20
  • MnDNR – Public Waters Work Permit, Other

Requirements

  • MPCA – Construction Permit, Endorsement/Assistance for

Pilot Project

  • Dakota County – Approval for Pilot Project (Alternative

Disposal Site)

  • Other Stakeholder Requirements / Restrictions

Regulatory Issues

STAKEHOLDER INPUT NEEDED

slide-21
SLIDE 21

Initial List of Alternatives / Pros & Cons

1) No-Action Alternative 2) Construct Settling Basin and Dredge Sediment Plume –

Disposal in Landfill

3) Construct Settling Basin and Dredge Limited Area –

Disposal in Landfill

4) Construction of Settling Basin Only 5) Alternative: Nearby Disposal Site – MPCA Pilot Project 6) Alternative: In-Situ Treatment Pilot Project – Methods

Under Consideration

STAKEHOLDER INPUT NEEDED

slide-22
SLIDE 22
  • 6. Other Questions / Suggestions /

Concerns / Next Steps