Construction Fire Safety in British Columbia Presenters: Katarina - - PowerPoint PPT Presentation
Construction Fire Safety in British Columbia Presenters: Katarina - - PowerPoint PPT Presentation
Construction Fire Safety in British Columbia Presenters: Katarina Burgess, P.Eng., CP John Bolduc, BASc, EIT CFT Engineering Inc. Brad Walton, AScT Background and Purpose Background: CFT Engineering Inc. was contracted by Forestry
Background and Purpose
Background: CFT Engineering Inc. was contracted by Forestry Innovations Investments to prepare a report on construction fire safety in British Columbia. For this project CFT Engineering collaborated with members of the Building Safety Standards Branch, WorkSafe BC and the Wood Enterprise Coalition
Background and Purpose
Purpose: To review current legislation regulating construction fire safety and current industry practice, and to provide recommendations for potential changes to legislation and enforcement practices governing construction fire safety in British Columbia
Background and Purpose
Context: The report was published prior to the adoption of the 2012 BC Fire Code and the 2012 BC Building Code.
Outline for this Presentation
Introduction Levels of Risk during Construction Key Legislative Requirements (2006 BCFC & BCBC) Enforcement Alberta Perspective IBC and NFPA Perspective Reported Fires (2005-2011) Findings from Site Investigations Fire Department Response to Construction Fires Conclusions from Report Recommendations from Report Adoption of the 2012 BC Fire Code (Time permitting)
What Makes Construction Fire Safety Risk Unique?
Incomplete fire separations (passive protection) Lack of functional/commissioned fire suppression and
detection systems (active protection)
Inadequate water supply for manual firefighting Fire Department response effectiveness Increased risk of incendiary fires due to periods where
the site is unoccupied, and the incompleteness of security devices
Hazardous operations that take place at construction
sites (e.g. hot works)
Levels of Risk during Construction
Phased Occupancy:
There is a greater risk when buildings under
construction are partially occupied
BC Fire Code requires a 1 hr separation BC Fire Code requires alarms or watched
tours
Water Supply
The water supply needed to fight fires in
buildings under construction is often greater than what is needed for completed buildings
Risk Level for Construction Phases
2006 Legislative Requirements
Objectives: To provide a framework for reducing
- r eliminating identifiable risks to fire and life
safety
BC Fire Code contains the majority of legislative
requirements for construction fire safety
BCBC addresses the issue through the
requirement in Part 8 of the BC Building Code to conform with the BC Fire Code
BC Occupational Health and Safety Standard
contains some supplementary requirements
2006 Legislative Requirements
Fire Safety Plan
Required by the
2006 BC Fire Code
Checklists have
been developed by the Office of the Fire Commissioner and municipalities including the Surrey Fire Service
2006 Legislative Requirements
Active System (e.g. detection and fire
suppression systems)
BC Fire Code requires that a system is provided to
alert site personnel of a fire. Air horns are typically provided.
Does not require a fixed automatic detection system
Passive System (e.g. fire separations)
BC Fire Code requires that one usable exit be
maintained
BC Fire Code requires a 1 hour separation between
- ccupied areas and areas under construction.
2006 Legislative Requirements
Manual Suppression Systems
BC Fire Code requires that extinguishers be provided in specific areas
The BC Fire Code requires standpipe systems be installed progressively
Limiting Combustible Materials
Combustible refuse in sufficient quantities to constitute a fire hazard is required to be moved to a safe location
Barricades
BCBC requires perimeter barricades
BC Fire Code requires fencing for outdoor storage
See Appendix A note
2006 Legislative Requirements
Hot Works
BC Fire Code requires that hot works be monitored with
a fire watch during hot work and after completion
Smoking
BC Fire Code limits smoking to permitted areas.
Heating Equipment
The BC Fire Code requires clearances between
combustible materials and temporary heating equipment to conform with Part 6 of the BC Building Code or minimum clearances shown on certified heating equipment.
Enforcement of Legislative Requirements
The Authority Having Jurisdiction (Fire and
Building Authority) is responsible for auditing construction fire safety plans and practices
Ultimate responsibility lies with the owner, who
typically delegates the implementation of safety practices to the general contractor
Many municipalities now require the submission
- f a construction fire safety plan before
construction commences
Construction Fire Safety in Alberta
The 2006 Alberta Fire Code has additional or
more detailed “unique to Alberta” requirements. Key requirements that differ from the BC Fire Code are as follows:
Requirements for adjacent buildings or facilities to be
protected from buildings under construction.
Additional requirements for access for firefighting.
This is also a requirement of the BCBC, but the wording in the Alberta Fire Code is more specific.
Extensive additional requirements for the progressive
installation of standpipe systems
Construction Fire Safety in Alberta
Alberta Standatas have been developed
to address:
Fire Department access Water supply Standardization of requirements for
construction fire safety
Construction Fire Safety in the United States
2012 International Building Code requires:
At least one lit stairway be provided where a building
is at least 50 ft. or four storeys
A specific requirement for standpipe installation An acceptable water supply be provided as soon as
combustible material is on site
NFPA 241, “Standard for Safeguarding
Construction, Alteration and Demolition Operations” has additional information for construction fire safety
Construction Fire Data
CFT Engineering Inc. obtained information
from the Office of the Fire Commissioner regarding reported construction fires from 2005 to 2009 in BC
Reports are now also available for 2010
and 2011
Construction Fire Data
Reported Fires on Construction/Demolition Sites
between 2005 and 2009:
275 were reported Resulted in 10 injuries and one fatality Resulted in equipment and property loss valued at
- ver $53 million
Additional fires during 2010 and 2011:
94 additional fires reported (369 total) One additional injury and one additional fatality Equipment and property loss valued at over $65
million ($118 million total)
Total Reported Cost of Construction Fires
$0 $50,000,000 $100,000,000 2004 2005 2006 2007 2008 2009 2010 2011 2012
Number of Reported Constuction Fires in British Columbia
50 100 2004 2005 2006 2007 2008 2009 2010 2011 2012 Incendiary and Suspicious Fires in Construction 223, 60% 146, 40%
Incendiary/Suspicious Other
Incendiary Fires Occuring vs. Time of Day
5 10 15 20 25 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
Number of Incendiary Fires
Non Incendiary Fires Occuring vs. Time of Day
5 10 15 20 25 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
Number of Non Incendiary Fires
Site Investigations
CFT Engineering Inc. reviewed construction
sites to assess fire protection practices in BC
Legislative requirements were largely adhered to Hazards specific to construction activities that
were noted included:
Accumulation of combustibles Delayed communication with the Fire Department
regarding available systems
Delays in charging installed fire protection systems Delayed installation of fire pumps for highrises
Not commissioned prior to occupancy
Fire Department Response to Construction Fires
The Fire Department’s response to a
construction site which is not anticipated to have persons in the buildings will typically be less aggressive
If the site is expected to be vacant and adjacent
properties are at risk, the Fire Department may prioritize the protection of adjacent properties
Pre-incident response planning can improve the
effectiveness of Fire Department operations
Conclusions from the Report
A key element of fire safety in construction is the
development of a working active construction fire safety plan
Current requirements lack sufficient guidance on
how to incorporate procedures to mitigate site specific risks
Additional guidance and education for risk
mitigation is needed
Mitigating strategies should become industry
practice
Recommendations
Linking of BC Building Code and Fire Code:
In order to increase the awareness of the requirements
for construction fire safety of professionals and contractors involved in the construction industry, it is recommended that there be a reference to the BC Fire Code requirements relating to construction fire safety within Division B, Part 3 and Division B, Part 9, Article 9.10.1.2, of the BC Building Code
Division B, Part 1, Subsection 1.1.4 of the BC Building
Code should be revised to include a reference to the construction fire safety plan
Recommendations
Assignment of a Fire Safety Coordinator
In order to provide continual monitoring of risks
throughout the different construction phases
Should keep workers up to date on with
emergency procedures
Should monitor the site with respect to the
construction fire safety plan
Should provide a single point of contact to the
fire services
Should be trained to identify basic hazards
Recommendations
Fire Warning and Alarm:
BCFC Article 5.6.1.9 should be amended to
include a fire warning system when the site is not active, such as after hours
A fire warning system may be a fire watch or
active detection systems or a combination of fixed detection and manual fire watch, potentially supplemented by lighting and security cameras
Recommendations
Coordinating Registered Professional:
BC Building Code Part 2, Division C, Article
2.2.7.3 (Appendix A) should provide general direction to inform the owner and constructor that as part of the project planning, a CFSP is required by the BC Fire Code, Section 5.6, “Construction and Demolition Sites”.
Recommendations
Adequate Water Supply for Fire Fighting:
BCFC Article 5.6.1.4 should be amended to
require the provision of a water supply for firefighting to the site as soon as combustible material arrives onsite
This may require early coordination with the
City, Engineering Department, consultants and trades, or a temporary water supply for firefighting could be provided
Recommendations
Fire Risk Assessment Management BC Fire Code Division B, Appendix A 5.6 should
add an explanatory note stating that it is essential that a risk assessment of potential fire hazards be carried out
Risk assessment should include risks to adjacent
property, facilities and wildland
Findings and recommendations from the risk
assessment would form the approach to risk mitigation in the construction fire safety plan
A review and analysis of risks associated with
adjacent properties or facilities should be completed by a knowledgeable professional for complex or higher risk sites
Recommendations
Pre-construction Meeting:
There should be a suggestion within the BC
Fire Code, Division B, Appendix A, for a pre- construction meeting upon issuance of building permit
The Fire Department and/or local assistant to
the fire commissioner should be invited to this meeting
Recommendations
Construction Fire Safety Plan
Universal and detailed guidelines should be provided to
the industry concerning the development of a construction fire safety plan and the implementation of construction practices
Current minimum requirements should be expanded to
include the submission and review of the plan by the Fire Department and/or the Authority Having Jurisdiction
The plan should be required to be updated at regular
intervals
The City of Surrey bulletin could be used as an
example for other municipalities
Recommendations
Development of Fire Protection Practice to
Mitigate Risk during Construction
Guidelines should be established and
reviewed with WorkSafe BC with respect to requirements for construction sites in order to establish industry practice
Recommendations
Development of Fire Protection Practice to Mitigate Risk
during Construction
Examples may include:
Provision of an unobstructed stair at each floor level Priority given to fire separation, firewall and closure installation
Security measures
Exposure Protection Charging the sprinkler system where practical Installation of fire pumps for standpipes, hydrants and hose
stations
Industry practice cannot be legislated, but through a
combination of legislation, comprehensive guidelines and education, these practices should become the standard practice for all sites
Recommendations
Provision and Maintenance of Fire
Department Access:
A Code conforming Fire Department access
route to the construction site should be available as soon as work commences at the site
A drawing showing the layout of the site and
the fire protection features should be available at the main Fire Department response point
Recommendations
Management of Ignition Source and
Combustible Content:
Procedures should be developed and
implemented to control sources of ignition and also to prevent accumulation of combustible materials
Recommendations
Responsibility and Enforcement:
A method should be established for regular
auditing of fire safety at construction sites
Ownership and responsibility for construction
fire safety should be clearly established
This could be achieved through the requirement of