construction contract award
play

Construction Contract Award Jeffrey Chambers, Director, Design and - PowerPoint PPT Presentation

Arlington Tech Summer 2020 Construction Contract Award Jeffrey Chambers, Director, Design and Construction School Board Information and Action Item May 7, 2020 Arlington Tech Expansion The School Boards a dopted FY 2019-28 Capital


  1. Arlington Tech Summer 2020 Construction Contract Award Jeffrey Chambers, Director, Design and Construction School Board Information and Action Item May 7, 2020

  2. Arlington Tech Expansion • The School Board’s a dopted FY 2019-28 Capital Improvement Plan (CIP) includes: • Arlington Tech Expansion for 250 high school seats to be completed by start of school September 2021 for a maximum total project cost of $18,750,000, bringing the total capacity of Arlington Tech to 600 seats. • In summer 2017, 2018, and 2019 staff completed projects to accommodate the growing enrollment of Arlington Tech. • Construction to prepare for Arlington Tech’s enrollment for SY 2020 -21 will occur this summer and include: (1) renovating a portion of the existing school to add a new science lab and right- size several existing classrooms and (2) installing relocatable classrooms on the existing parking lot. • COVID-19 disrupted plans to consolidate the Columbia Pike Branch Library on the first floor to provide shared APS/County classrooms on the second floor. Staff recommend proceeding with construction as soon as reasonable in coordination with pandemic recovery. 2

  3. Project Budget (Exhibit A) • Of the $18.75 million of funding approved in the FY 2019-28 CIP, all but $5.00 million in bonds have been sold. • Of the $13.75 million in bonds already sold, approximately $7.60 million remains to support the project. • Proposed budget for summer 2020 renovations and library renovation is $7.50 million . Project Budget Summer 2020 Renovation and Library Renovation Package 1 Construction - Summer 2020 $ 891,747 Package 2 Construction - Library Conversion (Estimated) $ 3,800,000 Construction Contingency $ 563,000 Subtotal - Construction (Hard Costs) $ 5,254,747 Owner (Soft) Costs* $ 2,245,253 Total Project Costs $ 7,500,000 *Owner costs include design, project management, and other professional services fees, utility/permitting fees, furniture, and equipment. 3

  4. Recommendations The following recommendations are within the current funding approved by the Board so no change to funding is necessary: • Approve an Early Release Construction Work Package contract award in the amount of $891,747 to Gilbane Building Company; and • Approve the project budget as proposed in Exhibit A and authorize staff to encumber funds as necessary to meet the project schedule. 4

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend