Construction Contract Award Jeffrey Chambers, Director, Design and - - PowerPoint PPT Presentation

construction contract award
SMART_READER_LITE
LIVE PREVIEW

Construction Contract Award Jeffrey Chambers, Director, Design and - - PowerPoint PPT Presentation

Arlington Tech Summer 2020 Construction Contract Award Jeffrey Chambers, Director, Design and Construction School Board Information and Action Item May 7, 2020 Arlington Tech Expansion The School Boards a dopted FY 2019-28 Capital


slide-1
SLIDE 1

Arlington Tech Summer 2020 Construction Contract Award

Jeffrey Chambers, Director, Design and Construction School Board Information and Action Item May 7, 2020

slide-2
SLIDE 2

Arlington Tech Expansion

  • The School Board’s adopted FY 2019-28 Capital Improvement Plan (CIP) includes:
  • Arlington Tech Expansion for 250 high school seats to be completed by start of school

September 2021 for a maximum total project cost of $18,750,000, bringing the total capacity of Arlington Tech to 600 seats.

  • In summer 2017, 2018, and 2019 staff completed projects to accommodate the growing

enrollment of Arlington Tech.

  • Construction to prepare for Arlington Tech’s enrollment for SY 2020-21 will occur this summer

and include: (1) renovating a portion of the existing school to add a new science lab and right- size several existing classrooms and (2) installing relocatable classrooms on the existing parking lot.

  • COVID-19 disrupted plans to consolidate the Columbia Pike Branch Library on the first floor to

provide shared APS/County classrooms on the second floor. Staff recommend proceeding with construction as soon as reasonable in coordination with pandemic recovery.

2

slide-3
SLIDE 3

Project Budget (Exhibit A)

  • Of the $18.75 million of funding approved in the FY 2019-28 CIP, all but $5.00

million in bonds have been sold.

  • Of the $13.75 million in bonds already sold, approximately $7.60 million remains

to support the project.

  • Proposed budget for summer 2020 renovations and library renovation is

$7.50 million.

3

*Owner costs include design, project management, and other professional services fees, utility/permitting fees, furniture, and equipment.

Project Budget Summer 2020 Renovation and Library Renovation Package 1 Construction - Summer 2020 $ 891,747 Package 2 Construction - Library Conversion (Estimated) $ 3,800,000 Construction Contingency $ 563,000 Subtotal - Construction (Hard Costs) $ 5,254,747 Owner (Soft) Costs* $ 2,245,253 Total Project Costs $ 7,500,000

slide-4
SLIDE 4

Recommendations

The following recommendations are within the current funding approved by the Board so no change to funding is necessary:

  • Approve an Early Release

Construction Work Package contract award in the amount of $891,747 to Gilbane Building Company; and

  • Approve the project budget as

proposed in Exhibit A and authorize staff to encumber funds as necessary to meet the project schedule.

4