TIDA INFRASTRUCTURE AND TRANSPORTATION COMMITTEE (ITC) REVIEW Constru truction ction Acti tivi viti ties es Update July 20, 2016 AGENDA Construction Schedule Construction Traffic Management Plan Construction Activities YBI
AGENDA
- Construction Schedule
- Construction Traffic Management Plan
- Construction Activities
- YBI Abatement & Demolition
- TI Abatement & Demolition
- YBI Water Tank Improvements
- YBI Infrastructure Improvements
- Part-1
- Part-2
- TI Geotechnical Stabilization Improvements
- Causeway West
- Causeway East
- Phase 1A
- Phase 1B
- TI Infrastructure Improvements
- Phase 1A
- Phase 1B
- Q & A
2
3 Q3 2016 Q3 2017 Q4 2017 Q2 2017 Q4 2016 Q1 2017
TI Street Improvements
TREASURE ISLAND DEVELOPMENT CONSTRUCTION SCHEDULE JANUARY 2016 – DECEMBER 2017
Hilltop Park Improvements YBI Vertical Improvements TI Geotechnical Improvements YBI Abatement and Demolition TI Abatement and Demolition Water Tank Improvements YBI Street Improvements
Q1 2016 Q2 2016
YBI Abatement and Demolition TI Abatement and Demolition Interim Grading for Water Tanks & Water Tank Construction YBI Street Improvements TI Geotechnical Improvemenets TI Street Improvements Hilltop Park Improvements YBI Vertical Improvements
CONSTRUCTION TRAFFIC MANAGEMENT PLAN
4
- Per Approved Disposition and Development Agreement
- Mitigation Monitoring and Reporting Program, Transportation Mitigation Measure M-TR-1
- Designed to anticipate & minimize transportation impacts of various construction activities.
- Designed to minimize overall disruptions & ensure that overall circulation on the Islands is
maintained to the extent possible.
- CTMP shall supplement & expand rather than modify or supersede, any manual, regulations,
- r provisions set forth by SFMTA, DPW, or other City Departments and agencies.
- CTMP requires TIDA approval.
- Project specific Construction Traffic Control Plan implementation will be required for each
Prime General Contractor.
CONSTRUCTION ACTIVITIES – Yerba Buena Island Abatement & Demolition
CONSTRUCTION ACTIVITIES – Yerba Buena Island
Construction Traffic Management Plan (Abatement & Demolition)
6
CONSTRUCTION ACTIVITIES –Treasure Island Abatement & Demolition
7
CONSTRUCTION ACTIVITIES –Treasure Island
Construction Traffic Management Plan (Abatement & Demolition)
8
CONSTRUCTION ACTIVITIES – Yerba Buena Island Water Tank Improvements
9
1. WATER TANKS 2. EXISTING EUCALYPTUS TREES 3. NEW NATIVE TREES 4. NEW WATER TREATMENT BUILDING 5. EXISTING TELCOM BUILDING 6. PARKING LOT 7. HILLTOP PARK 8. ACCESS ROAD 9. EXISTING OAK TREES
CONSTRUCTION ACTIVITIES – Yerba Buena Island
Construction Traffic Management Plan (Water Tank Improvements)
10
11
CONSTRUCTION ACTIVITIES – Yerba Buena Island Infrastructure
- Macalla Road Widening
- Yerba Buena Road
Realignment
Includes New Water, Electric, Gas, Storm Drain, Sanitary Sewer, Telecom, Landscape and Hardscape Improvements.
12
CONSTRUCTION ACTIVITIES – Yerba Buena Island
Construction Traffic Management Plan (Infrastructure)
13
CONSTRUCTION ACTIVITIES – Yerba Buena Island
Construction Traffic Management Plan (Infrastructure)
14
TREASURE ISLAND – GEOTECHNICAL STABILIZATION
14
CONSTRUCTION ACTIVITIES – Treasure Island Geotechnical Stabilization
15
CONSTRUCTION ACTIVITIES – Treasure Island
Construction Traffic Management Plan (Geotechnical Stabilization)
16
CONSTRUCTION ACTIVITIES – Treasure Island
Construction Traffic Management Plan (Geotechnical Stabilization)
17
CONSTRUCTION ACTIVITIES – Treasure Island
Construction Traffic Management Plan (Geotechnical Stabilization)
18
CONSTRUCTION ACTIVITIES – Treasure Island
Construction Traffic Management Plan (Geotechnical Stabilization)
CONSTRUCTION ACTIVITIES –Treasure Island Infrastructure
19
Will follow Geotechnical Stabilization Includes New Water, Electric, Gas, Storm Drain, Sanitary Sewer, Telecom, Landscape and Hardscape Improvements
20
CONSTRUCTION ACTIVITIES – Treasure Island
Construction Traffic Management Plan (Infrastructure)
21
CONSTRUCTION ACTIVITIES – Treasure Island
Construction Traffic Management Plan (Infrastructure)
22