cons truction pres entation to altaveedan community liais
play

CONS TRUCTION PRES ENTATION TO ALTAVEEDAN COMMUNITY LIAIS ON - PowerPoint PPT Presentation

CONS TRUCTION PRES ENTATION TO ALTAVEEDAN COMMUNITY LIAIS ON GROUP JUNE 2015 DEVELOPMENT & CONS TRUCTION TEAM: GARTH MCGIMPSEY SENIOR DEVELOPMENT PROJECT MANAGER, RES VICTORIA GRAHAM COMMUNITY RELATIONS MANAGER, RES JOHN BOYCE


  1. CONS TRUCTION PRES ENTATION TO ALTAVEEDAN COMMUNITY LIAIS ON GROUP JUNE 2015 DEVELOPMENT & CONS TRUCTION TEAM: GARTH MCGIMPSEY SENIOR DEVELOPMENT PROJECT MANAGER, RES VICTORIA GRAHAM COMMUNITY RELATIONS MANAGER, RES JOHN BOYCE PROJECTS MANAGER, RES FERGAL DUFFY CONSTRUCTION PROJECT MANAGER, RES NOEL BESLIN CONSTRUCTION SITE MANAGER, RES

  2. RES Who we are ? • RES is one of the world's leading renewable energy developers • Quarter of a century since RES was formed, • Play a central role in the development of the global renewable energy market • Portfolio of low-carbon energy technologies and a range of services which together can meet demand from the industrial, public and commercial sectors on whatever scale.

  3. RES CONS TRUCTION • Responsible for safety in preparation and execution of construction of wind farm proj ects • Ensuring quality of installation through accurate design, organisation, planning and documentation • Ensuring protection of the environment. • Manage programme, budget and client’ s specification. • Management of contracts and contractors to build the construction team on and around site • Liaise with public during construction.

  4. S ITE INFRAS TRUCTURE AND S TAKEHOLDERS FOR A S UCCES S FUL PROJECT General Public Contractors Landowners Consultative Bodies Client & RES resources 4

  5. PRELIMINARY CONS TRUCTION PROGRAMME – KEY DATES • Offsite Turbine Delivery & Enablement Works – July 2015 • S tart On S ite (Main Civil Works) – September 2015 • Civil Works - Tracks and Hard-standings – September 15 – October 16 • Civil Works – Turbine Foundations – - November 15 – February 16 • Electrical Works – Cabling – September 16 - October 16 • Electrical Works – Equipment Installation October 16 – December 16 • Turbine Works – Delivery – October 16 • Turbine Works – Erection and Commissioning – November 16 – March 17 5

  6. ALTAVEEDAN WIND FARM - PROJECT BRIEF Civil : • Public Road Modifications • Construction of new S ite Tracks • Turbine Foundations & Crane Hard S tandings • S pecial Purpose Control Room Electrical : • 4 Panel Vacuum Type S witch Gear • Pre Insertion Resistor • Miscellaneous Protection and Control panels • Grid Controller Turbines : • 9 No – 2 MW Machines with a 60m Hub Height

  7. PUBLIC ROAD WORKS – Haulage and Turbine Delivery

  8. Potential S tone Delivery Route 1 8

  9. Potential S tone Delivery Route 2 9

  10. 170

  11. 170

  12. P57

  13. P57

  14. P157

  15. 44

  16. CONTROL BUILDING

  17. 91

  18. Wind Turbine Erection Time Lapse https://www.youtube.com/watch?v=9u_Eyx SVL5o

  19. 91

  20. INDICATIVE CONSTRUCTION MILESTONES • S hould there be dirt on the road? • Can you not build the turbines with helicopters? • Can the turbine lorry not drive any faster.. we need to get to work? • Who is in Charge here! • Are you not finished yet? Headaches

  21. 21

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.