CONCRETING 1 3/4/2015 2 3/4/2015 3 3/4/2015 ACI DEFINITION OF - - PDF document

concreting
SMART_READER_LITE
LIVE PREVIEW

CONCRETING 1 3/4/2015 2 3/4/2015 3 3/4/2015 ACI DEFINITION OF - - PDF document

3/4/2015 COLD WEATHER CONCRETE PRACTICES CRMCA SOUTHERN MARKETING O SUCCESSFUL COLD WEATHER CONCRETING 1 3/4/2015 2 3/4/2015 3 3/4/2015 ACI DEFINITION OF COLD WEATHER Cold Weather - A period when, for more than 3 consecutive days, the


slide-1
SLIDE 1

3/4/2015 1

CRMCA SOUTHERN MARKETING O

COLD WEATHER CONCRETE PRACTICES

SUCCESSFUL COLD WEATHER CONCRETING

slide-2
SLIDE 2

3/4/2015 2

slide-3
SLIDE 3

3/4/2015 3

slide-4
SLIDE 4

3/4/2015 4

ACI DEFINITION OF COLD WEATHER

Cold Weather - A period when, for more than 3 consecutive days, the following conditions exist:

  • The Average daily air temperature is less than 40 ºF (5 ºC), and
  • The air temperature is not greater than 50 ºF (10 ºC) for more than
  • ne-half of any 24 hour period.
slide-5
SLIDE 5

3/4/2015 5

9

U.S. FREEZE / THAW ZONE MAP

Annual average number

  • f days temperatures

fall below 32 °F (0 °C) Less than 30 30 to 90 91 to 150 151 to 210 More than 210

10

Temperature, °F

  • Approx. Setting Time, hrs.

70 6 60 8 50 11 40 14 32 Concrete Freezes

CONCRETE FREEZES! Setting Time of Concrete at Various Temperatures

slide-6
SLIDE 6

3/4/2015 6

11

Effect of Early Freezing

12

A 10 degree drop in concrete temperature will DELAY set time by approximately 2 – 2 ½ hours Rule of Thumb

slide-7
SLIDE 7

3/4/2015 7

Increased Contractor Labor Costs

Extended Concrete Setting Times

14

Increased Contractor Labor Costs

slide-8
SLIDE 8

3/4/2015 8

15

  • Prevent damage to concrete due to freezing at early stages
  • Assure that the concrete develops the required strength for safe

removal of forms

  • Maintain curing conditions that foster normal strength

development

  • Limit rapid temperature changes
  • Provide protection consistent with the intended serviceability of

the structure

OBJECTIVES OF SUCCESSFUL COLD WEATHER CONCRETING

  • Materials
  • Mix Design
  • Placement Conditions
  • Curing conditions and length of time
  • Protection

What Can We Influence

slide-9
SLIDE 9

3/4/2015 9

  • GOAL is to ACCELERATE and INCREASE

Maximum Temperature

  • Provide concrete with predictable setting

times

  • Maintain Air entrainment and workability
  • Minimize Plastic and Drying shrinkage

Materials & Mix Design

Speed up the early hydration (heat gain) of concrete can be obtained by using one or more

  • f the following:
  • Additional portland cement
  • Use Type III Cement
  • Hot water
  • Heat Aggregate
  • Use of calcium chloride
  • Use of a non-chloride accelerating admixture

Cold Weather Concreting (Producer)

slide-10
SLIDE 10

3/4/2015 10

19

2 4 6 8 10 12 14

12:35 10:40 8:55 Effect of Cement Content on Setting Time Performance

Concrete and Ambient Temperature: 50 °F (10 °C) Initial Time of Set - Hours Cement Content, lb/yd³ (kg/m³) 420 (250) 520 (310) 600 (355)

20

An increase of 1 sack of cement, will improve the set time by about 1 hour Why? Lower unit water content Rule of Thumb

slide-11
SLIDE 11

3/4/2015 11

21

Age of Test, Days Compressive Strength, % of 28 Day, 73°F (23°C) Cured Concrete

40 20 60 80 1 3 7

Mixed and cured at 55°F (13°C)

Age of Test, Days Compressive Strength, % of 28 Day, 73°F (23°C) Cured Concrete

40 20 60 80 1 3 7

Mixed and cured at 55°F (13°C)

Early Age Compressive Strength for Type I and Type III Cement

22

Age of Test, Days Compressive Strength, % of 28 Day, 73°F (23°C) Cured Concrete

40 20 60 80 1 3 7

Mixed and cured at 40°F (4°C)

Type III T y p e I

Early Age Compressive Strength for Type I and Type III Cement

slide-12
SLIDE 12

3/4/2015 12

23

“An accelerating admixture is a material added to concrete for the purpose of reducing the time of setting and accelerating early strength development.” “Accelerating admixtures are useful for modifying the properties of concrete, particularly in cold weather, to:”

Chemical Admixtures for Concrete

ACI 212.3

24

  • Expedite the start of finishing operations
  • Reduce the time required for proper curing

and protection

  • Increase the rate of early strength

development to permit earlier removal of forms and earlier opening of construction for service

Chemical Admixtures for Concrete

ACI 212.3

slide-13
SLIDE 13

3/4/2015 13

25

Accelerated setting time characteristics

  • Earlier finishing of slabs
  • Increased early and ultimate strength
  • Reduced protection time in cold weather
  • Earlier stripping and reuse of forms

Accelerating Admixtures

26

Calcium Chloride Accelerating admixtures containing calcium chloride Non-chloride accelerating admixtures Non-chloride accelerating admixtures for use in concrete placed in sub-freezing temperatures

Classes of Accelerating Admixtures

slide-14
SLIDE 14

3/4/2015 14

  • Concrete should never be placed on a

frozen subgrade

  • On a frozen subgrade, heat will migrate

rapidly away from the bottom of the concrete retarding setting time

  • Thaw the subgrade not just the surface
  • Reschedule for a warmer day!!

Placing Concrete on Ground

Concrete bleeding Bleed water can freeze on surface Bleed water capillary channels can freeze within the concrete Cold subgrades Rapid migration of heat from concrete will affect setting time Uneven settlement may occur, causing cracking

Plastic Concrete Problems in Cold Weather

slide-15
SLIDE 15

3/4/2015 15

29

Surface crusting which can cause: Blisters Delamination Scaling (premature/over finishing)

Finishing Problems in Cold Weather

slide-16
SLIDE 16

3/4/2015 16 All snow, ice and frost must be removed from forms, reinforcement and other embedments Must protect from all sides Use of Type III cement, additional cement and/or non-chloride accelerators will reduce the length

  • f protection period, HOWEVER, know the effects

each will have on the plastic and hardened properties

Cold Weather Concreting Above Ground

slide-17
SLIDE 17

3/4/2015 17

slide-18
SLIDE 18

3/4/2015 18

36

1 2 4 Minimum Concrete temperature as placed and maintained Minimum concrete temperature as mixed for indicated air temperature Air Temperature

  • Above 30 °F

Below 0 °F <12 in. 12-36 in. 55 °F 50 °F 60 °F 55 °F 3 0 to 30 °F 65 °F 60 °F 70 °F 65 °F

Table 3.1 – Recommended Concrete Temperatures

37

DURATION OF RECOMMENDED PROTECTION FOR % OF STANDARD-CURED 28-DAY STRENGTH

50 6 9 3 65 11 14 5 85 21 28 16 95 29 35 26 Percentage of Standard-cured 28-day strength At 50 °F (10 °C), days Type of Cement I II III

slide-19
SLIDE 19

3/4/2015 19

slide-20
SLIDE 20

3/4/2015 20

41

8.1 – Introduction ― “Newly placed concrete must be protected from drying so that adequate hydration can occur. Normally, measures must be taken to prevent evaporation of moisture from concrete. During cold weather, when the air temperature is below 50 ºF(10 ºC), atmospheric conditions in most areas will not cause excessive drying.”

Concrete Curing

42

8.2 - Curing during the protection period When dry heating is used, the concrete should be covered with an impervious material or curing compound. Water curing is not recommended.

Concrete Curing

slide-21
SLIDE 21

3/4/2015 21 Things to watch

Carbonation CO2 Vent or have heat source from outside

Watch Carbonation from other trades equipment Watch blowing hot air across a fresh slab

Heating

slide-22
SLIDE 22

3/4/2015 22

45

8.3 - Curing following the protection period “…if a curing compound is applied during the first period of above-freezing temperature after protection is removed, the need to conduct further curing

  • perations if the temperature should rise

above 50 ºF(10 ºC) is eliminated.”

Concrete Curing

46

Strength

Age, Days

125 100 75 50 25 150 3 7 28 90 180

Moist-cured entire time In air after 7 days In air after 3 days In air entire time

Compressive strength, percent of 28-day moist-cured concrete

Effect of Curing on Compressive Strength

slide-23
SLIDE 23

3/4/2015 23 Cylinders should be protected and stored in protective area between 60°F and 80°F for the first 24 hours. Record field storage conditions with a high / low thermometer. Field cure cylinders for form removal should be representative of the structure and not used for quality assurance. Recommend using maturity meter for in place strength data.

Testing

49

110 100 80 60 40 20 3 6 9 12 18 24 Standard 28-Day Compressive Strength Age at which specimens were frozen, in hours

Effect of Freezing on 28-Day Compressive Strength

slide-24
SLIDE 24

3/4/2015 24

50

“Work on your project named here shall conform to all requirements of ACI 306.1,Standard Specification for Cold Weather Concreting, published by the American Concrete Institute, Detroit, Michigan, except as modified by the requirements of these Contract Documents.”

Sample Cold Weather Spec.

51

The entire team must: Plan ahead Be prepared Be concerned Schedule work Instruct and inspect

Successful Cold Weather Concreting Practices

slide-25
SLIDE 25

3/4/2015 25

52

Quality concrete can be successfully placed at low ambient temperatures ACI 306R Guide, ACI 306 specification and ACI 308 Guide should be followed More cement, Type III Cement, heat and/or accelerating admixtures may all be used to accelerate concrete setting time and increase early strength development

Conclusions and Recommendations

53

“Cold Weather Concreting” Reported by ACI Committee 306 “Standard Specification for Cold Weather Concreting” Reported by ACI Committee 306 “Standard Practice for Curing Concrete” Reported by ACI Committee 308

Resources