Commuter Rail il and Transit Development Dis istrict Update CAF - - PowerPoint PPT Presentation

commuter rail il and transit
SMART_READER_LITE
LIVE PREVIEW

Commuter Rail il and Transit Development Dis istrict Update CAF - - PowerPoint PPT Presentation

Commuter Rail il and Transit Development Dis istrict Update CAF Economic Outlook November 1, 2019 9-mile extension to Dyer, Indiana Project Cost: Estimated $816 million In October NICTD received permission to enter into


slide-1
SLIDE 1

Commuter Rail il and Transit Development Dis istrict Update

CAF Economic Outlook

November 1, 2019

slide-2
SLIDE 2
  • 9-mile extension to Dyer, Indiana
  • Project Cost: Estimated $816 million
  • In October NICTD received

permission to “enter into engineering,” and complete all design and engineering work

  • Federal funding has begun to flow,

with some of the engineering costs and cost of refurbishing cars for the West Lake line eligible for federal reimbursement

  • Only projects cancelled by their

sponsor failed to receive federal funds after reaching this phase.

Northwest Indiana RDA 2

slide-3
SLIDE 3
  • 25 mile project area, 16 miles

new 2nd track, 4 new bridges, 3 new hi-level boarding platforms, 7 new hi-speed crossovers, closing 20 grade X-ings in Michigan City, train/car separation in Michigan City

  • Estimated cost: $416 million
  • Financial plan approved by RDA

board, IFA, NICTD and the State Budget Committee

  • The Double Track Project

application to the FTA was submitted at the end of June

Northwest Indiana RDA 3

slide-4
SLIDE 4

Northwest Indiana RDA 4

  • Appropriated $205 million for RDA to use on projects as needed
  • To cover potential cost increases for both projects
  • To cover possible funding requirements from the FTA
  • Funds are borrowed as needed from the Next Level Connection fund
  • If a project receives a Full Funding Grant Agreement (FFGA), the

project borrowing is forgiven with neither principal nor interest to be repaid

  • If a project does not receive a FFGA then RDA is required to repay the

loan over 25 years. RDA is at risk if NICTD is not successful in getting a FFGA for either project (if the project draws on the loan).

  • There will be separate loans for each project. Failure on one project

will not trigger repayment for the other project.

slide-5
SLIDE 5

Northwest Indiana RDA 5

  • Established by the General Assembly in 2018
  • Allows RDA to establish a Transit Development District (TDD) in ½ mile area

around train station

  • RDA and localities must negotiate a % of incremental property tax & local
  • ption income tax revenues from TDD to go to RDA to invest back into TDD
  • RDA will employ incremental revenues to finance needed infrastructure

improvements and to incentivize private development

  • Existing obligations have priority over any later obligations made by the

RDA, and any RDA obligations are subject to outstanding ones.

  • Revenues generated in a district must be spent in that district
  • Legislation created a steering committee of locally appointed

representatives to inform and guide development

slide-6
SLIDE 6

Northwest Indiana RDA 6

  • RDA has requested communities provide GIS and planning data for use in

drawing up the Transit Development District (TDD) boundaries and facilitate development planning within each district.

  • RDA has begun meeting with communities in order to begin drafting the
  • districts. We have focused primarily on West Lake communities since that

project is further along in the federal funding approval process.

  • To date the RDA team has initiated the TDD process with Dyer, Munster,

Hammond and Michigan City.

  • The districts will be planned in collaboration with development priorities in

each community.

  • By statute, RDA must hold two public meetings for each TDD to allow for

public review and comment. We hope to begin holding the first public meetings early next year.

slide-7
SLIDE 7

Northwest Indiana RDA 7

  • Independently,

several communities are already planning for Transit Oriented Development (TOD)

  • Dyer is incorporating

TOD into the town’s new comprehensive plan, currently under development

slide-8
SLIDE 8

Northwest Indiana RDA 8

  • West Lake:
  • Complete design and engineering - 2020
  • Negotiate Full Funding Grant Agreement - 2020
  • Construction begins - 2021
  • Service begins - 2024
  • Double Tracking:
  • Receive permission to enter into engineering from FTA - 2019-20
  • Complete design and engineering - 2020
  • Negotiate Full Funding Grant Agreement – 2020-21
  • Construction begins 2021-22
  • Transit Development Districts:
  • Hold public meetings and finalize TDDs over the course of 2020