SLIDE 1
SAME, Honolulu HI November 12, 2013 Melek YALCINTAS, Ph.D., P.E., CxA, LEED-AP AMEL Technologies, Inc. Manoa Innovation Center 2800 Woodlawn Drive, Suite 251 Honolulu, HI 96822 Phone: 988-0200 E-mail: melek@ameltech.com
Common Commissioning Problems
SLIDE 2 SAME, Honolulu HI November 12, 2013
LEED Certified Buildings – where Commissioning is a mandatory requirement Claim:
- Saves Energy
- Better Indoor Air Quality
- Protects Environment
- Conserves Resources
SLIDE 3
SAME, Honolulu HI November 12, 2013
LEED Certified Buildings - Energy
The Claimed benefits of LEED Certified facilities are being questioned: Recent peer reviewed research papers: “Do LEED-certified buildings save energy? Yes, but …” (Newsham, et al., 2009) http://archive.nrc-cnrc.gc.ca/obj/irc/doc/pubs/nrcc51142.pdf “Do LEED-certified buildings save energy? Not really…” Schofield (2009) http://www.sciencedirect.com/science/article/pii/S037877880900187X Then, USGBC States (2013) Once again, GSA recognizes that LEED works http://www.usgbc.org/articles/once-again-gsa-recognizes-leed-works
SLIDE 4 SAME, Honolulu HI November 12, 2013
LEED Certified Buildings - Energy
Energy Consumption Evaluation of U.S. Navy LEED-Certified Buildings (Menassa et al., 2012): 9 of 11 LEED buildings did not achieve a 30% savings in electricity consumption, while seven of eleven met water consumption savings requirements http://ascelibrary.org/doi/abs/10.1061/(ASCE)CF.1943-5509.0000218 Post-Occupancy Energy Consumption Survey of Arizona’s LEED New Construction Population (Oates and Sullivan, 2012)
http://ascelibrary.org/doi/abs/10.1061/%28ASCE%29CO.1943-7862.0000478?journalCode=jcemd4&
The LEED NC sample also underperformed both the design and baseline energy use simulations
SLIDE 5 SAME, Honolulu HI November 12, 2013
LEED Certified Buildings - IAQ
Indoor Air Quality- Occupant Satisfaction in LEED and non-LEED Certified Buildings (Altomonte and Schiavon, 2013) http://escholarship.org/uc/item/4j61p7k5
- 144 buildings (65 LEED certified) and 21,477 individual occupant response
(10,129 LEED Buildings)
- Not a significant influence of LEED certification on occupant satisfaction with
indoor environment quality
SLIDE 6 SAME, Honolulu HI November 12, 2013 What is the true story? Why LEED certified buildings save energy or cannot save energy?
- Design team has to demonstrate/prove the facility is energy efficient
What Makes a LEED Certified Building to Save Energy and Provide Better Indoor Air Quality?
COMMISSIONING
SLIDE 7
SAME, Honolulu HI November 12, 2013
What is New-Construction Commissioning?
A systematic quality assurance process of verifying that building systems are designed, installed, tested, and they are capable of being operated, and maintained to perform as intended, or as the owner expects.
SLIDE 8 SAME, Honolulu HI November 12, 2013
What does Owner Expect from Commissioning Authority?
CxA conducts a series of tests to see how the building will work under normal operating conditions. These tests will detect any faults and problems before the
- wner takes possession and occupies the building.
SLIDE 9 SAME, Honolulu HI November 12, 2013
Commissioning Benefits
Benefits to Owner:
- Improved Indoor Air Quality (IAQ) and Occupant Comfort
- Documented Maintenance Requirements
- Improved Staff Training
- Increased Life of Equipment
- Reduced Operating Costs
- Fewer Comfort Problems
Benefits to Contractor:
- Reduced Warranty Issues
- Reduced Contractor Callbacks
SLIDE 10 SAME, Honolulu HI November 12, 2013
Commissioning Process
- Review Owner’s Project Requirements
- Coordinate Basis of Design Document
- Commissioning Specifications
- Commissioning Plan
- Design review
- Review submittals
- Construction observation
- Pre-functional checks
- Functional testing
- Cx Issue resolution
- Training
- Review O&M manuals
- Systems manual
- Re-Commissioning
- Commissioning Report
SLIDE 11 SAME, Honolulu HI November 12, 2013
Commissioning Team
Owner’s Team:
- Construction Engineer
- Project Manager
- Facility Manager
- Maintenance Team
Contractor’s Team:
- Project Manager
- Quality Control Manager
- Subcontractors: HVAC, Plumbing, Electrical, Controls Test & Balance
Design Team:
- Architect, Mechanical Designer, Electrical Designer
Commissioning Authority:
- Certified by ACG (AABC Commissioning Group), ASHRAE, BCA
(Building Commissioning Association), NEBB (National Environmental Balancing Bureau)
SLIDE 12 SAME, Honolulu HI November 12, 2013
- Related to Design
- Related to Installation
- Related to Owner
- Related to Contractor
- Related to Commissioner
Commissioning Problems
SLIDE 13 SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Design
- Sequence of Operation does not
Integrate Energy Savings Operations
- Important IAQ Details for Building
Pressurization Missing
- Demand Control Ventilation at Minimum
VFD Position does not Perform
- Sufficient Maintenance Clearance not
Provided
SLIDE 14
SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Design
SLIDE 15
SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Design
SLIDE 16 SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Installation
- Duct Leakage
- Weather Proofing
- Corrosive Couplings, Bolts & Nuts
- Un-insulated/Incomplete Duct Work
- Modulating Dampers/Actuators not Installed
Correctly, & therefore not Responding to Control Commands
- Condensation because of Improper Installation
SLIDE 17
SAME, Honolulu HI November 12, 2013 Duct Leakage
Commissioning Problems Related to Installation
SLIDE 18
SAME, Honolulu HI November 12, 2013 Weather Proofing
SLIDE 19
SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Installation
SLIDE 20
SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Installation
Corrosive Couplings, Bolts & Nuts
SLIDE 21
SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Installation
SLIDE 22 SAME, Honolulu HI November 12, 2013
- Condensation because of Improper Installation
Commissioning Problems Related to Installation
SLIDE 23
SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Installation
SLIDE 24 SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Owner
- OWNER needs to take part in commissioning activities
- OWNER needs to respond to comments in Cx issue
resolution log
- OWNER needs to actively monitor the building
performance after turnover
- OWNER’s input and support is strongly needed
especially when CxA makes recommendations that will effect building energy performance, but not necessarily included in the original construction documents
SLIDE 25 SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Contractor
- Contractor needs to understand that they benefit most from
commissioning: reduced warranty issues, reduced contractor call- backs.
- Contractor needs to understand Cx comments are not to show
contractors mistakes but to coordinate successful completion and turn
SLIDE 26 SAME, Honolulu HI November 12, 2013
Commissioning Problems Related to Commissioner
- Less involvement during design phase
- HVAC and building system sequences are nor verified
during commissioning
- Functional Tests are developed for individual equipment
but not whole systems
- Sensor calibration not verified
- Building schedule is not coordinated
- Rigorous of commissioning testing is brief, not detailed
enough
SLIDE 27
SAME, Honolulu HI November 12, 2013
Commissioning can Delay Equipment Failure
SLIDE 28
SAME, Honolulu HI November 12, 2013
“Do LEED-certified buildings save energy? Yes, but …”
http://archive.nrc-cnrc.gc.ca/obj/irc/doc/pubs/nrcc51142.pdf
“Do LEED-certified buildings save energy? Not really…”
http://www.sciencedirect.com/science/article/pii/S037877880900 187X
You Decide/Answer:
Energy Savings Potential is Still Real
SLIDE 29 SAME, Honolulu HI November 12, 2013
Conclusions
RECOMMENDATIONS
- Commissioning Authority should be hired by Owner, independent of
design team and contractor
- Measurement and verification must be mandatory
- Measurement and verification must be conducted continuously
- LEED Certification is not a guarantee for energy saving and better
indoor air quality
- Commissioning is the key for saving energy and better indoor air
quality, provided that Commissioning Comments are taken into consideration during Design and Construction.
- Commissioning can extend the life of the building and equipment;
resulting less maintenance time.
SLIDE 30
SAME, Honolulu HI November 12, 2013 Melek YALCINTAS, Ph.D., P.E., CxA, LEED-AP AMEL Technologies, Inc. Manoa Innovation Center 2800 Woodlawn Drive, Suite 251 Honolulu, HI 96822 Phone: 988-0200 E-mail: melek@ameltech.com
Thank You