City of Ann Arbor Sanitary Sewer Improvements Preliminary - - PowerPoint PPT Presentation

city of ann arbor
SMART_READER_LITE
LIVE PREVIEW

City of Ann Arbor Sanitary Sewer Improvements Preliminary - - PowerPoint PPT Presentation

City of Ann Arbor Sanitary Sewer Improvements Preliminary Engineering (SSIPE) Project Neighborhood Public Meeting December 5, 2017 OHM-ADVISORS.COM ARCHITECTS. ENGINEERS. PLANNERS. Welcome & Introduction Brian Slizewski City of Ann


slide-1
SLIDE 1

OHM-ADVISORS.COM

City of Ann Arbor

Sanitary Sewer Improvements Preliminary Engineering (SSIPE) Project

Neighborhood Public Meeting December 5, 2017

  • ARCHITECTS. ENGINEERS. PLANNERS.
slide-2
SLIDE 2

Brian Slizewski

  • City of Ann Arbor

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Welcome & Introduction

slide-3
SLIDE 3

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Team Overview

  • City of Ann Arbor:

– Brian Slizewski – Project Manager – Troy Baughman – Modeling and Data Support

  • Technical and Public Engagement Consultants:

– Robert Czachorski, Consultant Project Manager – Mackenzie Johnson, Engineering Analysis – Lori Byron, Public Engagement

slide-4
SLIDE 4

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Meeting Outcomes

  • Background on sanitary sewer system and

previous projects

  • Overview of the SSIPE project
  • Findings in your neighborhood
  • Next steps
slide-5
SLIDE 5

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Project Background

Troy Baughman

slide-6
SLIDE 6

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Definitions – Stormwater System

  • Storm sewer conveys

most of the stormwater runoff from buildings and streets

  • Catch basin is a part
  • f a storm drain that is

designed to trap debris so that it cannot enter the drainage pipes.

  • Roof drains convey

storm water from the roof to the storm sewer or retaining area.

slide-7
SLIDE 7

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Definitions – Sanitary Sewer System

  • Sanitary sewer

conveys domestic and commercial sewage, as well as some groundwater and stormwater that finds its way into the system

  • Footing drain drain

pipes beneath a structure to drain ground water away

  • Basement backup

the backup of flow from the sanitary pipe into a basement

slide-8
SLIDE 8

Sewer lateral connection Catchbasin Cleanout Connected footing drain Roof drain

STORM SEWER SANITARY SEWER

Property owner is responsible for the footing drains, cleanout and sanitary sewer lateral connection, all the way until it taps into the sanitary main.

slide-9
SLIDE 9

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Ann Arbor’s Sanitary Sewer System

10 20 30 40 50 60 70 80 90 100 Length (miles) Decade of construction

360+

Miles of sewer pipes

Allen School Area

slide-10
SLIDE 10

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Wet Weather Projects

  • Sanitary Sewer Wet

Weather Evaluation Project​

  • Footing Drain

Disconnection Program

  • Stormwater Model

Calibration and Analysis

  • Upper Malletts Drainage

Study

  • Sanitary and

Stormwater Systems Asset Management Plan

PLUS: continuous annual sewer maintenance and improvements (sewer televising, sewer cleaning, manhole repair, sewer lining, etc.)

  • Green Streets Program
slide-11
SLIDE 11

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Wet Weather Projects

Sanitary Sewer Wet Weather Evaluation Project – 2013-2014 Sanitary Sewer Improvements Preliminary Engineering Project – 2016-2017 Capital Improvements Program funded construction projects (if needed) – 2019 or later

slide-12
SLIDE 12

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Wet Weather Projects

  • -> Sanitary Sewer Wet Weather

Evaluation Project – 2013-2014 Sanitary Sewer Improvements Preliminary Engineering Project – 2016-2017 Capital Improvements Program funded construction projects (if needed) – 2018 or later

slide-13
SLIDE 13

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Wet Weather Evaluation (SSWWE)

SSWWE project objectives:

  • Evaluate the overall capacity of the sanitary

sewer collection system

  • Evaluate the past Footing Drain

Disconnection (FDD) program and assess the future risk of sewer backups in the City

  • Recommended methods to further reduce

wet weather impacts to the sanitary sewer system

slide-14
SLIDE 14

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

SSWWE Project Findings

SSWWE project looked at the sanitary sewer across the entire city and found five areas with potential capacity issues during wet weather, including the Allen School expansion area. These five areas are being analyzed in depth, as the Sanitary Sewer Improvements Preliminary Engineering (SSIPE) project.

slide-15
SLIDE 15

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Wet Weather Projects

Sanitary Sewer Wet Weather Evaluation Project – 2013-2014 Sanitary Sewer Improvements Preliminary Engineering Project – 2016-2017 Capital Improvements Program funded construction projects (if needed) – 2018 or later

slide-16
SLIDE 16
slide-17
SLIDE 17

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Improvements Preliminary Engineering Project

Project goals:

  • 1. Use field engineering techniques to

determine if capacity issues exist.

  • 2. Analyze field data and determine the

cause of the capacity issues.

  • 3. Determine the best solution for the area,

based on public input and solution effectiveness.

slide-18
SLIDE 18

Allen School Expansion Area

slide-19
SLIDE 19

Arbor Woods Expansion Area

slide-20
SLIDE 20

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Arbor Woods Area

SSWWE project’s computer modeling showed that some sanitary sewer pipes are

  • verloaded during wet weather.
slide-21
SLIDE 21

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Arbor Woods Area

Questions and field investigation tools: Q1: Is the computer model reflecting what’s happening in real world? (Flow metering) Q2: Are residents seeing impacts of

  • verloaded pipes? In what areas? (Resident

survey) Q3: Where are the flows coming from? (CCTV, manhole inspection, smoke testing)

slide-22
SLIDE 22

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Inflow & Infiltration (I&I)

How stormwater groundwater gets into the sanitary sewer system

Infiltration: Connected footing drain Broken sewer lateral Root intrusion into lateral Cracked or broken pipe Inflow: Roof drain connection Uncapped cleanout Storm cross-connection Deteriorated manhole

slide-23
SLIDE 23

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

I&I: Potential Sources

  • Pipe Defects
  • Manhole Defects
  • Smoke Testing Sources (uncapped

cleanouts, connected catch basins, roof drains)

  • Connected Footing Drains
slide-24
SLIDE 24

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Field Investigation

  • Resident Survey
  • Flow Metering
  • Sanitary Sewer Evaluation

– CCTV – Manhole inspection – Smoke testing

slide-25
SLIDE 25

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Improvements Preliminary Engineering Project

Mackenzie Johnson

slide-26
SLIDE 26

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Field Investigation

  • Resident Survey
  • Flow Metering
  • Sanitary Sewer Evaluation

– CCTV – Manhole inspection – Smoke testing

slide-27
SLIDE 27

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Resident Survey

  • 500 surveys mailed

Sep 12, 2017

  • 10 questions
  • 111 responses
  • 22% response rate
slide-28
SLIDE 28

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Resident Survey Findings

  • 53% have a full basement
  • 14% experienced sanitary sewage

basement backups in the last 10 years

  • 30% experienced basement flooding

(groundwater or stormwater) in the last 10 years

  • 34% have their private service leads

cleaned or rodded every 1-5 years

slide-29
SLIDE 29

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Resident Survey Findings

A few respondents mentioned tree roots in the system Several experienced backups until private service leads were replaced

slide-30
SLIDE 30

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Field Investigation

  • Resident Survey
  • Flow Metering
  • Sanitary Sewer Evaluation

– CCTV – Manhole inspection – Smoke testing

slide-31
SLIDE 31

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Field Investigation

Flow Metering: A flow meter is a device used to measure the flow rate of liquid moving through the sanitary sewer pipe. Field technicians installed flow meters at various locations in the area.

slide-32
SLIDE 32

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Flow Metering – Aug. 16, 2016

0.1 0.2 0.3 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2

17:40 18:25 19:10 19:55 20:40 21:25 22:10 22:55 23:40 0:25 1:10 1:55 2:40 3:25 4:10 4:55 5:40 6:25 7:10 7:55 8:40 9:25 10:10 10:55 11:40 12:25 13:10 13:55 14:40 15:25 16:10 16:55 17:40 18:25 19:10 19:55

Rainfall (in) Flow (cfs) Time 19D 24D 19D+24D Rainfall

slide-33
SLIDE 33

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Arbor Woods Area Field Investigation

  • Sanitary Sewer Evaluation

– CCTV – Manhole inspection – Smoke testing

slide-34
SLIDE 34

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation - CCTV

Closed Circuit Television (CCTV) is a technology used to inspect pipes in the sewer system.

A small robotic device with a television camera is run through the sewer main to locate and identify sources of water entering the system, such as leaks, cracks, and broken pipe.

slide-35
SLIDE 35

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Pipeline Condition Grading System

  • Defects within a pipe are graded based on

the severity of the defect

  • Scale ranges from Grade 1 to Grade 5 with

a Grade 5 defect being the most severe

slide-36
SLIDE 36

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Pipeline Condition Grading System

Grade 4 defects

  • Fracture Multiple (FM)
  • Broken Pipe (B)
  • Root Ball at a Joint

(RBJ)

  • Infiltration Runner (IR)

Grade 5 defects

  • Deformed Pipe (DR)
  • Surface Damage

Missing Wall (SMW)

  • Infiltration Gusher (IG)
  • Broken Soil Visible

(BSV)

slide-37
SLIDE 37

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Grade 4 Defect Examples

Broken Pipe (B)

slide-38
SLIDE 38

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Grade 4 Defect Examples

Infiltration Runner (IR)

slide-39
SLIDE 39

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Grade 5 Defect Examples

Broken Soil Visible (BSV)

slide-40
SLIDE 40

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Map of Spot Issues Found

Orange = Grade 4 Defects Purple = Grade 5 Defects

slide-41
SLIDE 41

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Arbor Woods Area Field Investigation

  • Sanitary Sewer Evaluation

– CCTV – Manhole inspection – Smoke testing

slide-42
SLIDE 42

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation – Manhole Inspection

Field crews locate and collect information on manholes, their depth and condition.

slide-43
SLIDE 43

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation – Manhole Inspection

slide-44
SLIDE 44

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Arbor Woods Area Field Investigation

  • Sanitary Sewer Evaluation

– CCTV – Manhole inspection – Smoke testing

slide-45
SLIDE 45

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation – Smoke Testing

Smoke testing is a method to find ways that groundwater and stormwater are entering the sanitary sewer system.

A non-toxic mist travels throughout the system, identifying problems such as leaks, connected downspouts

  • r roof drains.
slide-46
SLIDE 46

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation – Potential Sources

Cleanout

slide-47
SLIDE 47

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation – Potential Sources

Manhole Cone Wall

slide-48
SLIDE 48

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Sanitary Sewer Evaluation – Potential Sources

Ground

slide-49
SLIDE 49

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Smoke Testing Results

Purple = Manhole Cone Orange = Manhole Frame Seal Yellow = Cleanout Red = Ground

slide-50
SLIDE 50

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Footing Drains

  • Approximately 500 parcels in the Arbor

Woods area

  • Estimated 302 connected footing drains
  • Estimated 25 footing drains disconnected

through the Developer Offset Mitigation (DOM) program

  • Estimated 169 homes with no basements

(no footing drains)

slide-51
SLIDE 51

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Footing Drains

Connected Disconnected through DOM

25 302 (approximately)

slide-52
SLIDE 52

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Inflow & Infiltration Water Budget

A water budget shows the components that make up the inflow and infiltration (I&I) in a system. In this project, the I&I sources are:

  • Manhole defects
  • Pipe defects
  • Smoke testing
  • Connected footing drains
slide-53
SLIDE 53

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Manhole Defects 3% Pipe Defects 10% Smoke Testing 1% Connected Footing Drains 86%

slide-54
SLIDE 54

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Basis for Modeling Scenario

Computer modeling of the system using design flows recommended by the 2013-2014 Sanitary Sewer Wet Weather Evaluation project’s Citizens Advisory Committee (CAC):

25 year event frequency + 10% additional flow (for climate change, growth, etc.) + system conditions observed in the field

slide-55
SLIDE 55

Model Results

slide-56
SLIDE 56

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Improvement Options

Option A: Pipe bursting– upsize pipes with insufficient capacity

Total Length = 2000 Cost per Linear Foot = $500 Total Cost = $1,000,000

slide-57
SLIDE 57

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Improvement Options

Option B: Disconnect footing drains Disconnect approximately 30% of connected footing drains to eliminate surcharging with the existing pipes

Number of FDD Cost per FDD Total Cost 100 $10,000-$15,000 $1.0 - $1.5 M

slide-58
SLIDE 58

Brian Slizewski

  • City of Ann Arbor

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Group Discussion of Options

slide-59
SLIDE 59

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Small Group Activity

  • 1. Review improvement options A & B
  • 2. Review engineers’ pros and cons

considerations

  • 3. Pick one person from your group to scribe

and report out

  • 4. Discuss the engineers’ pros and cons,

and your own with your group

slide-60
SLIDE 60

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Small Group Activity

Discussion questions:

  • What are your questions about the

problem?

  • What are your questions about the
  • ptions?
  • What concerns do you have about the

pros and cons listed by engineers?

  • What are the pros and cons from your

group?

slide-61
SLIDE 61

Brian Slizewski

  • City of Ann Arbor

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Summary & Next Steps

slide-62
SLIDE 62

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

What’s Next

  • 1. Ongoing maintenance – clean, repair pipes with

structural defects

  • 2. Fix inflow sources found via smoke testing and

uncapped cleanouts

  • 3. Voluntary Developer Offset Mitigation program
  • 4. Capital Improvement Programming – if

warranted, residents will be engaged prior to construction

slide-63
SLIDE 63

OHM-ADVISORS.COM

  • ARCHITECTS. ENGINEERS. PLANNERS.

Project updates: A2gov.org/SSIPE