Citizens Transportation Advisory Committee December 15, 2010 PROJECT - - PowerPoint PPT Presentation

citizens transportation advisory committee
SMART_READER_LITE
LIVE PREVIEW

Citizens Transportation Advisory Committee December 15, 2010 PROJECT - - PowerPoint PPT Presentation

Citizens Transportation Advisory Committee December 15, 2010 PROJECT NEEDS & BENEFITS Provide direct connection from Port to Interstate Highways from I 395 via Watson Island Maintain Port as Countys second leading Economic


slide-1
SLIDE 1

Citizens’ Transportation Advisory Committee

December 15, 2010

slide-2
SLIDE 2

PROJECT NEEDS & BENEFITS

  • Provide direct connection from Port to

Interstate Highways from I‐395 via Watson Island

  • Maintain Port as County’s second‐leading

Economic Generator

  • Relieve congestion from Downtown Streets
  • Keep Port Competitive
slide-3
SLIDE 3

PROJECT PARTNERS

90% Equity Partner 10% Equity Partner Contractor VMS Operator Public Sponsors Federal Support

slide-4
SLIDE 4

PUBLIC‐PRIVATE PARTNERSHIP‐ P3

  • Design‐Build‐Finance‐Operate‐Maintain

Concession Agreement

  • 35‐year contract between FDOT & MAT

Concessionaire

  • Design and Construction period is 55 months
  • Operation and Maintenance period is the

remaining 30+ years

Contract Overview

slide-5
SLIDE 5

PUBLIC PRIVATE PARTNERSHIP – P3

  • Upon Tunnel opening, FDOT begins making

availability payments adjusted yearly for inflation

  • Maximum Availability Payment $32.5M/yr
  • Payment is subject to reduction if Tunnel not
  • perational during required hours
  • Contract includes ‘Handback’ requirements to ensure

Tunnel is returned to FDOT in first‐class condition

Payments during O&M

slide-6
SLIDE 6

FUNDING THE POMT

  • FDOT contributing $457.5M
  • Miami‐Dade County contribution $357.5M
  • City of Miami contribution $50M
  • R/W donations (County & City) $50M
  • FDOT funding Tunnel Operations & Maintenance from

statewide maintenance funds (about $200 million over 30 years)

PUBLIC PRIVATE PARTNERSHIP – P3

Project Funding

slide-7
SLIDE 7

SCOPE OF WORK

Shifting of EB MacArthur Cswy MacArthur Cswy Bridge Widening Twin tunnels under Government Cut Modification of Dodge Island Roadway System

slide-8
SLIDE 8

PROJECT STATUS:

Watson Island

  • Construction of New Parrot Jungle

Trail is 95% Complete

  • EB MacArthur Causeway has been

shifted south to new alignment

  • Site Installation Permits for

Support Operations under Bridge:

  • Water Treatment Plant
  • Concrete and Grout Batch Plant
  • Cooling and Power Systems
  • Mechanic Shop
  • Barge to Receive Spoils
slide-9
SLIDE 9

PROJECT STATUS:

MacArthur Causeway & Bridge

  • Widening of MacArthur Bridge for Tunnel Traffic
  • Widening of the Median for Launching Pit – Tunnel

Starting Point

  • Tunnel Support Operations located below Bridge
slide-10
SLIDE 10

PROJECT STATUS:

Dodge Island

  • 60% Roadway Design Plans are

under review process

  • Exploratory Geotechnical Borings

performed and analyzed

  • Sub‐sea Ground Investigation

performed in Channel

  • Construction began early in

December 2010

  • Ongoing Stakeholder Meetings

with Cruise, Cargo & Port Reps

slide-11
SLIDE 11

TUNNEL BORING MACHINE

  • Tunnel Boring Machine

(TBM) is currently being designed and fabricated in Germany.

  • 43’ diameter & +600 ft.

long train

  • Expected Arrival is

scheduled for May 2011

  • EB Bore to begin

September 2011

  • Completion of WB

Bore Spring 2013

slide-12
SLIDE 12

TUNNEL VERTICAL ALIGNMENT & SECTION

  • Tunnels are 3900 ft. long
  • +40 ft. under the Bottom
  • f Channel
  • 5% Grade
  • Precast Lining Segments

fabricated Off‐Site

slide-13
SLIDE 13

CONSTRUCTION SCHEDULE

*THESE DATES ARE SUBJECT TO CHANGE BASED ON THE CONSTRUCTION SCHEDULE

May 24, 2010 – Construction began on Watson Island December 2010 – Construction begins on Dodge Island Spring 2011 – Arrival of TBM in Miami Fall 2011 – Beginning of eastbound tunnel boring Spring 2012 – Completion of eastbound tunnel Spring 2013 – Completion of westbound tunnel Spring 2014 – Completion of Dodge Island roadway improvements May 15, 2014 – Grand opening of the Port of Miami Tunnel

slide-14
SLIDE 14

MAINTENANCE OF TRAFFIC (MOT)

  • Weekly MOT releases
  • Full‐time Communications Manager
  • Full‐time Traffic Manager
  • Full‐time Health & Safety Manager
  • Emergency Response vehicles
  • Live Cameras (Sunguide.org)
slide-15
SLIDE 15

TUNNEL RENDERING

slide-16
SLIDE 16

QUESTIONS?

Visit www.portofmiamitunnel.com