Citizens Millage Advisory Committee April 25, 2019 AGENDA Program - - PowerPoint PPT Presentation
Citizens Millage Advisory Committee April 25, 2019 AGENDA Program - - PowerPoint PPT Presentation
Citizens Millage Advisory Committee April 25, 2019 AGENDA Program Budget Status General Items Project Updates Career Tech Center Update Northside High School Update Southside High School Update Ramsey Jr High Update
2 Citizens Millage Advisory Committee
AGENDA
- Program Budget Status
- General Items
- Project Updates
- Career Tech Center Update
- Northside High School Update
- Southside High School Update
- Ramsey Jr High Update
- Darby Jr High Update
- Morrison Elementary Update
- Barling, Cook, Woods Elementary Updates
- Security Packages Update
BUDGET STATUS
Citizens Millage Advisory Committee
BUDGET STATUS: Source and Use of Funds
Bond Issue $90,000,000.00 Interest Earnings $1,273,411.16 Total Sources $91,273,411.16
Uses of Funds:
Bond Issue Costs $1,474,212.95 Program Costs $890,403.57 Total Uses $2,364,616.52
Net Cash Position
Sources of Funds $91,273,411.16 Less: Uses of Funds ($2,364,616.52) Net Cash Position $88,908,795.64
Sources of Funds:
Active Proje jects
Millage Project Budget Cost to Date Remaining Northside High School $34,696,035.00 $251,059.38 $34,444,975.62 Southside High School $43,826,514.00 $329,911.26 $43,496,602.74 Morrison Elementary School $1,821,247.00 $29,072.56 $1,792,174.44 Security Packages $5,500,000.00 $59,189.85 $5,440,810.15
GENERAL ITEMS
7
NHS-SHS Gym Scope Alignment
Citizens Millage Advisory Committee
Ramsey Jr High Building Committee Meeting General
- The project management team has
conducted numerous outreach and coordination meetings including:
- NHS Building Committee
- SHS Building Committee
- Ramsey Jr High Building Committee
- Campus programming sessions
- Campus scope alignment meetings
- Contractor orientation meeting
- EDA Grant application meetings
- City of Fort Smith coordination
- Citizens Millage Advisory updates
- Student Leadership Council updates
- Fort Smith Public Schools Board of
Education updates
KEY ACCOMPLISHMENTS
8
General
- Contractor Orientation Meeting held
- n April 8, 2019.
- Excellent turnout with over 50
members of the contractor community in attendance
- Discussed:
- Contract delivery methods
- High level schedule of events
- All project descriptions
- Requested feedback
Contractor Orientation Meeting
Citizens Millage Advisory Committee
KEY ACCOMPLISHMENTS
PROJECT UPDATES
Career Tech Education Center
- Donation of building on Zero Street approved by Fort Smith Public Schools Board of Education
- Property transfer pending
- General program offerings under development
- Economic Development Authority (EDA) Federal Grant for additional funding submitted (4/25)
- Conceptual building façade options under review by project team
- Design team developing building program concepts for review by Fort Smith Public Schools
- Boundary Survey of property complete
- Laser scanning of existing building underway
- Collaborating with Arkansas Department of Transportation (ARDOT) on the Zero Street
expansion project to minimize impact to Fort Smith Public School Property
KEY ACCOMPLISHMENTS
11 Citizens Millage Advisory Committee
SCHEDULE UPDATE Career Tech Center Proforma Timeline – program TBD
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
Interior Finishes Final Completion CDs Complete NTP
- CDs = Construction Documents (plans and specifications)
- NTP = Notice to Proceed. NTP is a contract instrument to establish the start date for construction
12 Citizens Millage Advisory Committee
Conceptual Sketches Career Tech Center INDUSTRIAL MODERN TRADITIONAL
KEY ACCOMPLISHMENTS Northside High School-
- All Architect contracts executed
- Toured Fayetteville and North Little Rock High Schools
- Meeting with the state to continue partnership funding
- Submitted request for extension of start date (10/28-storm shelters)
- Comparison Study of Competition Gym equity complete
- Schematic budget in review
- Master Schedule complete
- Request for Qualifications (RFQ) issued 4/5 for Construction Manager at Risk (CMAR)
- Campus programming complete
- Campus Master Plan complete
- Schematic Design (SD) phase nearing completion
- Elevations and floor plans of Freshman Center, Administration Addition, Cafeteria, and Competition
Gymnasium complete
- Civil engineering started
- Design Development (DD) phase started
- Includes: 1) structural engineering, 2) mechanical/electrical/plumbing (MEP) engineering, 3) Fire suppression system
requirements, 4) food service consulting, 5) Fine tuning architectural layouts and components
14 Citizens Millage Advisory Committee
SCHEDULE UPDATE: Northside High School
CIVIL RENOVATIONS / ADDITIONS COMPETITION GYM + STORM SHELTERS
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
Civil Design Complete Civil Construction Final Completion Civil NTP R&A CDs Complete R&A Final Completion
- Comp. Gym CDs
Complete
- Comp. Gym + Storm Shelter
Final Completion Storm Shelter CDs Complete R&A NTP
- Comp. Gym + Storm
Shelter NTP
April 25, 2019
- CDs = Construction Documents (plans and specifications)
- NTP = Notice to Proceed. NTP is a contract instrument to establish the start date for construction.
- R&A = Renovations and Additions
Building Perspective – Administrative Entry
Building Perspective – Southeast Corner
New Gymnasium Entry
Southside High School-
- All Architect contracts executed
- Toured Fayetteville and North Little Rock High Schools
- Meeting with the state to continue partnership funding
- Submitted request for extension of start date (10/28-storm shelters)
- Comparison Study of Competition Gym equity complete
- Schematic budget in review
- Master Schedule complete
- Request for Qualifications (RFQ) issued 4/5 for Construction Manager at Risk (CMAR)
- Campus programming complete
- Campus Master Plan complete
- Schematic Design (SD) phase nearing completion
- Elevations and floor plans of Freshman Center, Administration Addition, Cafeteria, and Competition Gymnasium
complete
- Civil engineering started
- Design Development (DD) phase started
- Includes: 1) structural engineering, 2) mechanical/electrical/plumbing (MEP) engineering, 3) Fire suppression system
requirements, 4) food service consulting, 5) Fine tuning architectural layouts and components
KEY ACCOMPLISHMENTS
19 Citizens Millage Advisory Committee
SCHEDULE UPDATE: Southside High School
CIVIL RENOVATIONS / ADDITIONS COMPETITION GYM + STORM SHELTERS
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
Civil Design Complete Civil Construction Final Completion Civil NTP R&A CDs Complete R&A Final Completion
- Comp. Gym CDs
Complete
- Comp. Gym + Storm Shelter
Final Completion Storm Shelter CDs Complete R&A NTP
- Comp. Gym + Storm
Shelter NTP
April 25, 2019
- CDs = Construction Documents (plans and specifications)
- NTP = Notice to Proceed. NTP is a contract instrument to establish the start date for construction.
- R&A = Renovations and Additions
Media Center- First Floor
Freshman Center Interior Perspective- First Floor
New Competition Gym Entry Rendering
Interior Perspective
Ramsey Jr High School
- Campus programming complete
- Met with the state to coordinate partnership funding
- Submitted request for extension of start date (10/28/19). The request has been granted.
- Schematic Design Complete
- Schematic Budget in review
- Master schedule complete
- Advertisement for Bid template drafted
- Design Development ongoing
- Bid day currently scheduled: September 26, 2019
- Start construction: October/November 2019
- Completion: no later than April 2021
KEY ACCOMPLISHMENTS
25 Citizens Millage Advisory Committee
SCHEDULE UPDATE: Ramsey Jr. High School
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
Construction Documents Complete NTP Final Completion
April 25, 2019
- CDs = Construction Documents (plans and specifications)
- NTP = Notice to Proceed. NTP is a contract instrument to establish the start date for construction.
Administrative Addition Plan
Darby Jr High School
- Architect agreement executed
- Campus programming continues
- Public utilities coordination complete
- Design progress meetings ongoing
- Schematic Design nearing completion
- Schematic Budget in review
- Master schedule complete
- Design Development pending
KEY ACCOMPLISHMENTS
28 Citizens Millage Advisory Committee
SCHEDULE UPDATE Darby Jr. High School
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
Construction Documents Complete NTP Final Completion
April 25, 2019
- CDs = Construction Documents (plans and specifications)
- NTP = Notice to Proceed. NTP is a contract instrument to establish the start date for construction.
Morrison Elementary School
- Campus programming complete
- Schematic Design (SD), Design Development (DD), Construction Documents (CD)
Complete
- CDs submitted to state for approval on 4/5/19
- Plumbing review approved by Arkansas Department of Health on 4/9/19
- Advertisement for Bid template drafted
- Advertising for Bid on 4/28 and 5/5
- Mandatory pre-bid conference currently scheduled: May 9, 2019
- Bid day currently scheduled: May 16, 2019
- Start construction: June 1, 2019
- Completion: no later than August 15, 2019
KEY ACCOMPLISHMENTS
30 Citizens Millage Advisory Committee
SCHEDULE UPDATE Morrison Elementary School
MEP/FP INTERIOR FINISHES
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
MEP/FP CDs Complete MEP/FP Final Completion MEP/FP NTP June 1, 2019 Interior Finishes Final Completion Interior Finishes CDs Complete NTP June 1, 2019
ONE YEAR AHEAD OF OTHER ELEMENTARY SCHOOLS – AN OPPORTUNITY TO OPTIMIZE 1. Evidence Based Design. 2. Decision Based Planning - schedule management / constructability / process. 3. Improved financial management / procurement / sourcing.
Existing Floor Plan
Existing Conditions
Floor Plan – New Construction (“Demountable” Wall System)
34 Citizens Millage Advisory Committee
SCHEDULE UPDATE Elementary Schools Barling; Cook; Woods
MEP/FP INTERIOR FINISHES
JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC | JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV| DEC | JAN | FEB | MAR | APR | MAY |JUN | JUL | AUG | SEP 2019 2020 2021
MEP/FP CDs Complete MEP/FP Final Completion MEP/FP NTP Interior Finishes Final Completion Interior Finishes CDs Complete NTP
Security Packages
- (4) campuses projected for completion Summer ’19
- Cavanaugh, Fairview, Spradling, Sunnymede
- Advertisement for Bids: 3/31/19 and 4/7/19
- Mandatory pre-bid: 4/9/19
- Met at Fairview Elementary
- Buses arranged to take attendees to each campus
- Bid Day: 4/16/19
- Notice to Proceed (NTP) for construction: 6/1/2019
- Completion: 8/7/2019
KEY ACCOMPLISHMENTS
WRAP UP