cigre us national committee 2014 grid of the future
play

CIGRE US National Committee 2014 Grid of the Future Symposium - PowerPoint PPT Presentation

CIGRE US National Committee 2014 Grid of the Future Symposium Initial Field Trials of Distributed Series Reactors and Implications for Future Applications I GRANT J COUILLARD Tennessee Valley Authority Smart Wire Grid Inc. USA USA J SHULTZ F


  1. CIGRE US National Committee 2014 Grid of the Future Symposium Initial Field Trials of Distributed Series Reactors and Implications for Future Applications I GRANT J COUILLARD Tennessee Valley Authority Smart Wire Grid Inc. USA USA J SHULTZ F KREIKEBAUM Tennessee Valley Authority Smart Wire Grid Inc. USA USA Ian Grant S OMRAN R BROADWATER Tennessee Valley Authority Virginia Tech Electrical Distribution Design (EDD) USA USA Presented by: BRUCE ROGERS, Director, Technology Innovation, TVA 1

  2. Distributed Series Reactor 2

  3. Background The Distributed Series Reactor is a self contained device, powered by induction from a transmission line conductor, that increases the series impedance of a circuit by injecting series reactance. The concept was first demonstrated in 2002 – 2003 and has been demonstrated in pilot installations on HV transmission lines. 3

  4. Equivalent Circuit With secondary winding shorted, injection is negligible 4

  5. DSR Characteristics (typical) Model Rated Injection Reactance added per DSR* (p.u.) Current Mode (A) Inductance at Rated Current (μH) 115 kV 138 kV 161 kV 230 kV 1.34e-4 9.30e-5 6.84e-5 3.35e-5 750 750 47 1.20e-4 8.31e-5 6.11e-5 2.99e-5 1000 1000 42 1.05e-4 7.32e-5 5.38e-5 2.64e-5 1500 1500 37 For a 161 kV line, assume 5 spans per mile and a device at each end of each span i.e. 10 devices per mile. Approximate impedance increase = 20% 5

  6. Example Application in Meshed Grid G8 39 BUS SYSTEM G10 37 26 25 28 29 30 38 – 2 Baseline MW: 18 27 1 17 G9 24 1904 MW 16 – Increase in ATC G6 G1 3 15 35 possible: 638 MW (33.5%) 21 22 39 4 14 – Increase in line availability 5 19 6 12 23 31 13 20 from 59% to 93% 11 7 36 8 10 G2 34 9 32 G7 G5 G4 G3 6

  7. Communication and Control Manual or automatic control through preset trigger points (e.g. line current), Power Line Carrier, Cell phone Individual information display available in control center for each DSR 7

  8. Pilot Test at TVA 100 DSRs installed on 17 spans of 21 mile 161 kV line at TVA Approximately 10 minutes to install each DSR 8

  9. Prototype DSR Installation at TVA TVA - 14.5 Miles of ACSR 795.0-26/7 9

  10. DSR Installation Clamshell construction. The two halves are positioned on the line and secured together with a torque wrench The devices run self diagnostics and can be remotely tested Each module can be triggered at a predefined set point or controlled remotely 10

  11. Pilot Test Results • Total Impedance Increase (33 DSRs / Phase @ 47 µH / DSR): .226 % (degree of control limited by number of available devices and a test line that was longer than optimal for the demonstration) • Devices performed as expected over 4-step range • Devices also successfully used to adjust phase imbalance • Single point failure of communication system identified for necessary design upgrade • DSRs presently considered unsuitable for bundled conductor use, although technically feasible 11

  12. Future Applications • Success of pilot opens path to more critical applications • Simplest application is reduction of maximum contingency load for postponement of line uprate • Ability to quickly relocate DSRs reduces cost to individual projects • Extreme case for portion of HV grid to have dynamically assigned line loading for selected goals, e.g. minimize system losses • Future designs may provide capacitive injection to reduce reactive impedance • Future designs with high speed controls may be low cost alternative to FACTS 12

  13. The IEEE 39 bus standard test system converted to a three phase system with 345kV lines 13

  14. The 345kV Line Configuration Structure Type: 3L11  Utility: Houston Lighting & Power Company Reference: EPRI, Transmission Line Reference Book - 345kV and above 14

  15. Line Impedance Models Unbalanced: Positive Sequence: Positive Sequence Z is derived from the Unbalanced Model Z using the symmetrical components transformation 15

  16. DSR Design for Load Growth Line5-6 Line6-7 Line13-14 Total 6000 5550 5000 No. of DSRs deployed 4000 3750 3525 3000 1950 2000 1650 900 1000 675 75 0 141% 143% 145% 147% 149% 141% 143% 145% 147% 149% Positive Sequence Unbalanced System Loading (%) 16

  17. Unbalanced vs. Positive Sequence Impedance Model Positive Sequence Unbalanced 40 35 30 Slope (MW/DSR) 25 20 15 10 5 0 141% 143% 145% 147% 149% System Loading (%) Slope (MW/DSR) for different System Loading % 141% 143% 145% 147% 149% Positive Sequence 33.60 2.93 1.41 0.81 0.54 Unbalanced 4.09 1.75 0.80 17

  18. DSR Design for Single Contingency: Unbalanced Impedance Model 18

  19. DSRs Deployed and Load Supplied 19

  20. The Selected Design at 140% System Loading Reinforced Lines with DSRs Lines 1500 DSR 75 DSR on on line5-6 line13-14 20

  21. DSR Design vs. Line Reinforcement for Single Contingency and Load Growth: Economic Evaluation 21

  22. Economic Evaluation • Determine the maximum MW supplied to load while handling all single contingencies – Case1: Three Lines Reinforced with No DSR – Case2: Three Lines Reinforced with DSR • Economic assessment of both cases 22

  23. Economic Evaluation Results • Case1: With Three Lines Reinforced • 125% loading is reached • Case2: With Three Lines Reinforced and DSRs Deployed • 140% loading is reached and selected as a desired DSR Design due to its technical merits – Fewer number of DSRs deployed. – Least % change in lines impedance. 23

  24. Data for the Economic Study • Max MW supplied at different % loading: Max MW MW Case % Loading supplied increase Base 100% 6309.4 Case1 125% 7886.6 1577.2 Case2 140% 8833.1 946.5 • Total length of the reinforced lines = 95 miles. Reinforced Line Length (miles) Line2-3 37 Line6-7 29 Line15-16 29 • Cost of 345 kV, single circuit = 1298 $k /mile 24

  25. Line Reinforcement Cost • Cost of 95 miles of line = 95 x 1298 k$ = 123.31 $M • Cost for 1577.2 MW of load increase = 123.31 $M • Cost per MW of load increase for reinforcing lines = 123.31 $M/1577.2 MW = 78,182 $/MW 25

  26. DSR Design Cost: Unbalanced Model • For the selected DSR design, a loading of 140% is achieved using 1575 DSR modules. • DSR worth in terms of transmission line value: – Cost of 946.5 MW of load increase = 946.5 MW x 78,182.8 $/MW = 74 $M – Thus the equivalent value of 1 DSR = 74 $M/1575 DSRs = 46,984 $/DSR 26

  27. Questions 27

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend