CHUTES International
LEAN JOURNEY 2019 - 2020
CHUTES International LEAN JOURNEY 2019 - 2020 INTRODUCTION - - PowerPoint PPT Presentation
CHUTES International LEAN JOURNEY 2019 - 2020 INTRODUCTION Compelling Needs For Change Increase output to meet / satisfy customer demand and eliminate delivery issues which could lead to potential loss of customers. Need to organize the
LEAN JOURNEY 2019 - 2020
2 | CHUTES INTERNATIONAL
INTRODUCTION
Compelling Needs For Change
to potential loss of customers.
business.
manufacturing systems.
its sales capabilities, allowing the sales team to go after business, rather than rationing business.
3 | CHUTES INTERNATIONAL
4 | CHUTES INTERNATIONAL
Making Our Team Members Work Easier!
manufacturing processes.
new ways of working to eliminate these difficult processes. From their input, they helped us implement better and safer practices.
their work and happier because they didn’t feel as fatigued as before.
5 | CHUTES INTERNATIONAL
Improving the Work for Welding
lot of lifting and turning to do of heavy items.
demand was causing fatigue for employees.
6 | CHUTES INTERNATIONAL
Improving the Work for Welding
floor frames to the paint booth in a more ergonomically friendly fashion.
and weld the chute sections and intakes.
7 | CHUTES INTERNATIONAL
Making Life Easier in The Door Department!
how many quality issues were happening in our Door Department that were not being addressed. We began to change from a culture of “making it work” to a culture of Root Cause Analysis, so the problems don’t reappear
8 | CHUTES INTERNATIONAL
Making Life Easier in The Door Department!
team and door department collaborated on a new design to
issues with our door trim.
90%
Savings to process step
9 | CHUTES INTERNATIONAL
10 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
product together which meant we wouldn’t complete jobs for days at a
taking hours instead of days.
processes and set up lines for bumping and the most efficient output in order to meet our customer demand.
11 | CHUTES INTERNATIONAL
Transitioning from Batching to One-Piece-Flow
understand how One-Piece Flow (OPF) worked and how it is better than
12 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
us to punch material for one job at a time.
we had a mixed model of items that are fabricated, and the lines needed to be set up to accommodate this.
implementation of an order traveler we can see where all the work is placed in
13 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
the product through the line in the most efficient manner.
14 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
batch types of doors we needed for a week at a time.
have some of the parts they needed to complete the job which resulted in a lot of WIP sitting around and doors on the floor.
15 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
determined typical jobs would take days to complete because
itself to a lot of excess walking from area to area.
the labor time to get one door done was 27 minutes.
16 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
realize we needed to streamline
bumping to the team.
down to 12 minutes per door and we are continuing to reduce that through current and future engineering improvements.
17 | CHUTES INTERNATIONAL
Setting Up our Teams for Success!
The door department’s new motto is “No Doors on the Floor!”
18 | CHUTES INTERNATIONAL
19 | CHUTES INTERNATIONAL
Managing the New System
fires all day.
management to meet and discuss potential issues as they happen.
as leader standard work for the department supervisors.
increase the value-added work from our weld team.
20 | CHUTES INTERNATIONAL
Managing the New System
which jobs needed to be completed.
meeting to discuss and tackle any issues that arise.
21 | CHUTES INTERNATIONAL
Managing the New System
standard work audits to ensure the team members are working to the standards created.
give the supervisors a framework each day about what needed to be accomplished
22 | CHUTES INTERNATIONAL
Managing the New System
developed with the supervisors to determine each team member’s skill level.
ensuring team members are being trained in various areas as needed.
23 | CHUTES INTERNATIONAL
Managing the New System
performing PDCA that a water spider was needed in the weld department.
removes all the non-value added activity from the welders. The removal of the waste from the build sequence has allowed us to increase our output.
24 | CHUTES INTERNATIONAL
25 | CHUTES INTERNATIONAL
Changing our Mindset
26 | CHUTES INTERNATIONAL
Changing our Mindset
27 | CHUTES INTERNATIONAL
Changing our Mindset
28 | CHUTES INTERNATIONAL
Changing our Mindset
29 | CHUTES INTERNATIONAL
Changing our Mindset
the BASICS™ method was critical for everyone involved to understand the road we needed to go down.
30 | CHUTES INTERNATIONAL
Changing our Mindset
members, vendors and management lead to breakthroughs.
regarding a nonvalue added activity we were performing. The vendor is now doing this for us before the material arrives in
Before: We had to cut
insulation to accommodate a part. After: We have our vendor making the cut in the insulation.
31 | CHUTES INTERNATIONAL
Changing our Mindset
the supervisors regarding quality issues or problems was few and far between.
an Andon light so they can notify the supervisor immediately when problems arise.
different interpretation of our motto, “whatever it takes”.
32 | CHUTES INTERNATIONAL
Changing our Mindset
ideas for improvements in their department.
“I’d like a light to go off when we have a problem” My supervisor would know when I have a problem
Gina March 2, 2020
Andon light installed at production line with switch for operators Alvin
March 2, 2020
When I have a problem I want to make sure we can address it Quickly
Example of card given by team member
33 | CHUTES INTERNATIONAL
34 | CHUTES INTERNATIONAL
Lessons Learned
company.
done.
ingenuity.
management and help from Business Improvement Group.
35 | CHUTES INTERNATIONAL
Project Results
additional 858 sq. ft. of usable space for future business and equipment.
additional 960 sq. ft. of usable space for future business and equipment.
36 | CHUTES INTERNATIONAL
Our AWESOME Teams!
37 | CHUTES INTERNATIONAL
Our AWESOME Teams!
38 | CHUTES INTERNATIONAL
The Road Ahead....
long way to go but we are extremely proud
accomplished in the past seven months.
39 | CHUTES INTERNATIONAL