Charting a Path Forward MARCH 6, 2019 Agenda 1. Introduction 2. - PowerPoint PPT Presentation

COMPTON HIGH SCHOOL Charting a Path Forward MARCH 6, 2019 Agenda 1. Introduction 2. Selected Site Option 3. Board Recommendation DLR Group COMPTON HIGH SCHOOL 1 OCTOBER 10, 2017 Schematic Design Cost Estimate Funding Available Dr. Dre


  1. COMPTON HIGH SCHOOL Charting a Path Forward MARCH 6, 2019

  2. Agenda 1. Introduction 2. Selected Site Option 3. Board Recommendation DLR Group COMPTON HIGH SCHOOL 1

  3. OCTOBER 10, 2017 Schematic Design Cost Estimate Funding Available Dr. Dre $10M CTE Programs $24M Modernization $11M Potential Additional $15M Funding Special ED Funding $3.5M Total Funding $63M Bond $199M Project Budget $262.5M Soft Costs – $50M Construction Budget $212.5M SD Estimate $210M DLR Group COMPTON HIGH SCHOOL 2

  4. JANUARY 29, 2019 Preliminary Project Budget Total Construction Cost should be $118M in order to maintain a Total Project Cost of $210M Measure S Contingency $13M DLR Group COMPTON HIGH SCHOOL 3

  5. GENERAL STRATEGIES • Reduce Student Capacity to 1800 • Simplify Buildings and Materials $174,326,831 SD Estimate +7% • Reduce PAC to 900 Seats • CIF Competition Pool $51 M Reduce Construction Time • Site Consolidation • $118,287,000 Initial Construction Target DLR Group COMPTON HIGH SCHOOL 4

  6. GENERAL STRATEGIES • Reduce Student Capacity to 1800 • Simplify Buildings and Materials $174,326,831 SD Estimate +7% • Reduce PAC to 900 Seats • CIF Competition Pool Reduce Construction Time • $130,821,202 Proposed Budget $12.5 M Site Consolidation • $118,287,000 Initial Construction Target DLR Group COMPTON HIGH SCHOOL 5

  7. Selected Site Option

  8. Schematic Design Site Plan DLR Group COMPTON HIGH SCHOOL 7

  9. SD Condensed Proposed design matches the previous schematic design deliverable, including: • Prominent location of the PAC • Academic building links fitness with performing arts Student promenade • • Strong street presence Total Construction Cost $130,821,201 Total of 400 Parking Spaces 8 DLR Group COMPTON HIGH SCHOOL

  10. SD Condensed Academic Building 1,800 Students $ 60,187,899 *Future expansion to accommodate 450 students, not included here $118M $60,187,899 9 DLR Group COMPTON HIGH SCHOOL

  11. SD Condensed Gymnasium Single Story, No Practice Court $23,068,716 $118M $83,256,614 +$23,068,716 10 DLR Group COMPTON HIGH SCHOOL

  12. SD Condensed Pool • CIF Competition • Bleachers with 112 Seats $2,054,395 $118M $85,311,009 +$2,054,395 11 DLR Group COMPTON HIGH SCHOOL

  13. SD Condensed Performing Arts Center 900 Seats. $19,907,721 $118M $105,218,730 +$19,907,721 12 DLR Group COMPTON HIGH SCHOOL

  14. SD Condensed Stadium, Track and Field $4,288,800 $118M $109,507,530 +$4,288,800 13 DLR Group COMPTON HIGH SCHOOL

  15. SD Condensed Base Site Site Preparation and Earthwork • • Covered Area - Lunch shelters • Parking • Hardscape & Landscape • Hard Courts Native and Adaptive • • Site Utilities $21,313,672 $130,821,202 +$21,313,672 $118M 14 DLR Group COMPTON HIGH SCHOOL

  16. SD Condensed $130,821,202 $118M 15 DLR Group COMPTON HIGH SCHOOL

  17. Board Recommendation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.