challenges to cost loading a project schedule
play

Challenges to Cost-Loading a Project Schedule Beverley M. Sheafer - PowerPoint PPT Presentation

2004 AACE International Annual Meeting Challenges to Cost-Loading a Project Schedule Beverley M. Sheafer Assistant Professor Construction Management Program California State University, Sacramento Challenges to Cost-Loading a Project Schedule


  1. 2004 AACE International Annual Meeting Challenges to Cost-Loading a Project Schedule Beverley M. Sheafer Assistant Professor Construction Management Program California State University, Sacramento

  2. Challenges to Cost-Loading a Project Schedule WELCOME Ladies and Gentlemen 2004 AACEI Annual Meeting Sheafer / page 2

  3. Challenges to Cost-Loading a Project Schedule The Question Is it possible to adequately "cost- load" a project schedule to reflect the true costs of the project? 2004 AACEI Annual Meeting Sheafer / page 3

  4. Challenges to Cost-Loading a Project Schedule The Assumptions � Applicable to all contract types � lump sum � unit price � GMP � Important to all parties involved � Includes all components of cost � resources � overhead � profit � Incorporated into schedule 2004 AACEI Annual Meeting Sheafer / page 4

  5. Challenges to Cost-Loading a Project Schedule The Discussion � Contract requirements � Parties involved � Cost definitions � Schedule development � Approaches 2004 AACEI Annual Meeting Sheafer / page 5

  6. Challenges to Cost-Loading a Project Schedule Pareto’s Rule (Vilfredo Pareto, Italian economist, 1848-1923 ) “80 percent of the outcome of any project is determined by 20 percent of its included elements” 2004 AACEI Annual Meeting Sheafer / page 6

  7. Challenges to Cost-Loading a Project Schedule � Contract requirements 2004 AACEI Annual Meeting Sheafer / page 7

  8. Challenges to Cost-Loading a Project Schedule � Contract requirements � Purpose � To establish goals for project � To allow measurement of project progress � To allow forecasting of end result 2004 AACEI Annual Meeting Sheafer / page 8

  9. Challenges to Cost-Loading a Project Schedule � Contract requirements � It is typical for a project contract to have a requirement that the project baseline schedule be cost-loaded. � The project schedule is usually the basis for progress payment applications. 2004 AACEI Annual Meeting Sheafer / page 9

  10. Challenges to Cost-Loading a Project Schedule � Contract requirements � Sample 1 – Schedule (see note 1) � The Project Schedule shall be cost loaded. Precedence scheduling format shall be used in accordance with accepted practice and the scheduling references described in Section 5.2, insofar as they pertain to precedence format and cost-loading. 2004 AACEI Annual Meeting Sheafer / page 10

  11. Challenges to Cost-Loading a Project Schedule � Contract requirements � Sample 2 - Payment (see note 2) � Payment shall be based on actual progress achieved against the cost loaded Project Schedule. � Each invoice shall (a) document the progress of the Work by activity number, (b) set forth the amount then due associated with such progress in accordance with the approved Project Schedule, … 2004 AACEI Annual Meeting Sheafer / page 11

  12. Challenges to Cost-Loading a Project Schedule � Parties involved 2004 AACEI Annual Meeting Sheafer / page 12

  13. Challenges to Cost-Loading a Project Schedule � Parties involved � Each party has the intent to fulfill the contract requirements � Each party may have a different concept as to what “cost-loaded” infers. 2004 AACEI Annual Meeting Sheafer / page 13

  14. Challenges to Cost-Loading a Project Schedule � Parties involved � Owner � Designer (not typically involved) � Construction Manager � General Contractor / Sub-Contractors 2004 AACEI Annual Meeting Sheafer / page 14

  15. Challenges to Cost-Loading a Project Schedule � Parties involved � Owner � Wants to stay within budget � Construction Manager � Wants to monitor costs � General Contractor / Sub-Contractors � Wants control over how “costs” are entered 2004 AACEI Annual Meeting Sheafer / page 15

  16. Challenges to Cost-Loading a Project Schedule � Cost definitions 2004 AACEI Annual Meeting Sheafer / page 16

  17. Challenges to Cost-Loading a Project Schedule � Cost definitions � Project Budgeted Cost � Establishes the baseline project cost � Cost Breakdown Structure (CBS) � Provides the framework by which cost information is gathered and reported � Includes all elements in the budget that have been given a dollar amount 2004 AACEI Annual Meeting Sheafer / page 17

  18. Challenges to Cost-Loading a Project Schedule � Cost definitions � Sample 3 (see note 3) � Level 8: Cost Code - The cost code of the Project will be defined by the Contractor. However, the cost code needs to follow the guidelines of WBS herein. 2004 AACEI Annual Meeting Sheafer / page 18

  19. Challenges to Cost-Loading a Project Schedule � Schedule development 2004 AACEI Annual Meeting Sheafer / page 19

  20. Challenges to Cost-Loading a Project Schedule � Schedule development � Work Breakdown Structure (WBS) � Establishing activities for the Scope of Work � Activity development � Should all activities be cost-loaded? 2004 AACEI Annual Meeting Sheafer / page 20

  21. Challenges to Cost-Loading a Project Schedule � Schedule development � Sample 4 (see note 4) � The WBS provides a hierarchical structure to segregate Project elements to facilitate the collection and analysis of Project Data and to serve as a mechanism for payment and scheduling for Project design, procurement and construction. 2004 AACEI Annual Meeting Sheafer / page 21

  22. Challenges to Cost-Loading a Project Schedule � Schedule development � Sample 4 continued � The WBS for the Double Track Corridor Improvement Program consists of eight levels of detail, which are: 1) Full Funded Grant Agreement (FFGA), 2) TRI-RAIL Phases, 3) Category, 4) Location, 5) Subcategory, 6) Work Element, 7) Work Detail, and 8) Cost Code. 2004 AACEI Annual Meeting Sheafer / page 22

  23. Challenges to Cost-Loading a Project Schedule � Approaches 2004 AACEI Annual Meeting Sheafer / page 23

  24. Challenges to Cost-Loading a Project Schedule � Approaches � Purpose � To provide framework by which information is gathered and stored on a project 2004 AACEI Annual Meeting Sheafer / page 24

  25. Challenges to Cost-Loading a Project Schedule � Approaches � Accounting structures � Schedule of Values In conjunction with Bid Estimate � Assembly loading To analyze cost and efficiency of different operations (assembly) � Resource loading To manage labor, material, equipment and o&p 2004 AACEI Annual Meeting Sheafer / page 25

  26. Challenges to Cost-Loading a Project Schedule The Conclusion 2004 AACEI Annual Meeting Sheafer / page 26

  27. Challenges to Cost-Loading a Project Schedule The Conclusion � Schedules can be adequately cost- loaded. � Contract should stipulate cost-loading structure. � Multiple coding and accounting structures should be used. 2004 AACEI Annual Meeting Sheafer / page 27

  28. Challenges to Cost-Loading a Project Schedule Pareto’s Rule Applied to Construction A project control system needs to identify the major cost elements of the project early and develop a system of controls to monitor and manage these elements. 2004 AACEI Annual Meeting Sheafer / page 28

  29. Challenges to Cost-Loading a Project Schedule Questions ? 2004 AACEI Annual Meeting Sheafer / page 29

  30. Challenges to Cost-Loading a Project Schedule Notes 1. Taken from Book II: Contractual Terms and Conditions, Section 5 – Project Schedule Requirements, Subsection 5.5 of Agreement No. 01-839 between Tri-County Commuter Rail Authority and The Washington Group International for TRI- RAIL Double Track Improvement Program New River Bridge Project. 2. Taken from Book II: Contractual Terms and Conditions, Section 10 – Payment, Subsection 10.4 of Agreement No. 01- 839 between Tri-County Commuter Rail Authority and The Washington Group International for TRI-RAIL Double Track Improvement Program New River Bridge Project. 2004 AACEI Annual Meeting Sheafer / page 30

  31. Challenges to Cost-Loading a Project Schedule Notes 3. Taken from Book III: Project Provisions, Section 8 – Work Breakdown Structure, Subsection 8.3 of Agreement No. 01- 839 between Tri-County Commuter Rail Authority and The Washington Group International for TRI-RAIL Double Track Improvement Program New River Bridge Project. 4. Taken from Book III: Project Provisions, Section 8 – Work Breakdown Structure, Subsections 8.1 and 8.2 of Agreement No. 01-839 between Tri-County Commuter Rail Authority and The Washington Group International for TRI-RAIL Double Track Improvement Program New River Bridge Project. 2004 AACEI Annual Meeting Sheafer / page 31

  32. Challenges to Cost-Loading a Project Schedule References � Managing the Construction Process by F.E. Gould, PE, AIC � Construction Project Planning and Scheduling by C. Patrick, PE, CSIT � Construction Planning and Scheduling by J.W. Hinze, PhD � TRI-RAIL Double Track Improvement Program New River Bridge Project Agreement No. 01-839 2004 AACEI Annual Meeting Sheafer / page 32

  33. Challenges to Cost-Loading a Project Schedule Contact information Beverley M. Sheafer Assistant Professor Construction Management Program California State University, Sacramento 6000 J Street Sacramento CA 95819-6029 Phone – 916.278.5349 Email – sheaferb@ecs.csus.edu 2004 AACEI Annual Meeting Sheafer / page 33

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend