CERN Info Point 2 Status Cosmic data taking finished. SM-II - - PowerPoint PPT Presentation
CERN Info Point 2 Status Cosmic data taking finished. SM-II - - PowerPoint PPT Presentation
CERN Info Point 2 Status Cosmic data taking finished. SM-II (sector 0) Un-installation done. Disassembly done. Problems investigated Takus slide. SM-I (sector 8) un-installation done. Disassembly started.
Point 2 Status
- Cosmic data taking
finished.
- SM-II (sector 0)
Un-installation done. Disassembly done. Problems investigated Taku’s slide.
- SM-I (sector 8)
un-installation done. Disassembly started. will finish on Wednesday.
- Sector 17
Gas leak investigation Nora’s slide.
- Mini-frame PP0 (pre-trigger)
disconnection done.
- Wiener campaign nearly end (last 12 went Wiener).
- Thanks for big efforts: Kengo, Sylwester, Kenshi,
Nora, Joerg, StefanS, Yvonne, Dousatsu, Masahiro, Taku, Thomas, Kathrin, Tom, Kai, Chilo, Jochen, Markus, Ana, Bernd, Peter, Tobias, Norbert.
Detector Status by End of Shutdown (Arturo) ALICE Status
3/5 PHOS 8/18 TRD 18/18 TOF 7/7 HMPID 1/6 EMCAL 1 2 3 4 5 6 7 9 8 11 12 13 14 15 17 1 2 3 4 10 16
Point 2 Plan
- SM-I (sec. 8) disassembly finish = Wed.
- Shipping SM-II (and part of SM-I) chambers to GSI = Wed.
- SM-III
In the rotator already. Move to CR on Thu. and start on Fri.
- Sec. 7 final preparation ~ Nov. 17.
Installation to sec. 7 = Nov. 24, 25. Service connections & commissioning = Nov. 26, till end of Dec.
- Shipping rest of the chambers & 2 (or 1?) hulls … when SM-VI arrives.
- SM-VI
Arrival … End of Nov. (expectation). Testing … whole Dec. Installation to Sec. 1 … end of Dec. or beg. Jan.
- Sec. 8 LV patch cords installation ~ Nov.
- SM-I and SM-II Sec. 8 + 0 installation ~ end of Feb.
- Gas system leak tightness tests necessary (scan all sectors in BSF) ~ Nov..
- Cooling solving for Sec. 10.
- Commissioning and cosmic runs with sectors 0, 1, 7, 8, 9, 17 (+10, 16?).
- End of shutdown … May 1st.
Nora’s slide
Leak‐Hun)ng in SM 17
Tests: 1. By‐passing all layers (all inlets into manifold) all )ght – leak s)ll there 2. Disconnec)ng exhaust result: leak must be in exhaust between manifold and gasplant didn’t find it so far b/c of underpressure 3. Replacing aluminium ring of exhaust‐connec)on at babyframe with O‐ring leak s)ll there 4. Sniffing tubes and connec)ons (also the welding) in CR5 couldn’t find any leak 5. Disconnec)ng exhausSube totally system )ght ‐> tube must be the problem 6. Replacing tube system )ght (FINALLY!!!!) found hole in the tube ‐> happened (probably) b/c of spark from TOF power Connec)ng SM back on
Taku’s slide
SM00 disassembly and check
List of problems in SM00
TRD weekly meeting on 13.10.08
Investigation of the problems
Cooling problem:
S2L5 S3L5
We found strong bent of cooling tubes
http://phenix.cns.s.u- tokyo.ac.jp/~gunji/tmp/cooling_pipes_sm00l5.pdf
Optical output problem:
S0L2A
fiber (20) broken
confirmed with other ORIs and other fibers
S3L2A
fiber not connected at patch panel behind No problem after connecting fiber at patch panel
S4L4AB
fiber problem
confirmed with other ORI and other fibers
S4L5B
seems OK at surface test
Investigation of the problems
DCS board dead:
S2L5
flashing firmware using JTAG failed with some errors Need to investigate more detail in KIP
New problem happened during disassembly
DCS board on S3L5 can never be on.
0.8V instead of ~5V at the input of DCS board PDB is reason (no power from PDB to DCS of S3L5)
confirmed that DCS board is fine by using another line of the power.