central vs distributed architecture
play

Central VS Distributed Architecture in utility PV plants Main - PowerPoint PPT Presentation

Central VS Distributed Architecture in utility PV plants Main Figures FIMER INDUSTRIAL BUSINESS UNITS Zero CO emitted 2 2% 36.000 m2 Production area 128.000 m2 Total land area 3.800 m2 Offices and facilities 27% 3,560 MW *


  1. Central VS Distributed Architecture in utility PV plants

  2. Main Figures FIMER INDUSTRIAL BUSINESS UNITS “Zero“ CO emitted 2 2% 36.000 m2 Production area 128.000 m2 Total land area 3.800 m2 Offices and facilities 27% 3,560 MW * Solar division production capacity/year (String Inv. – Central Inv. - Storage Inv.) Solar 150.000 Welding machines/year 71% Welding 420.000 PC Board dpt. production capacity/year Air cond. 530 Conversion Units/year 15.800 Combiner Boxes production/year 6.200 Air conditioners/year * 4,120 MW by the end of the year REVENUES FIMER INDUSTRIAL HEADQUARTER 7% Total land area 128.000 sqm Domestic Production areas 36.000 sqm Export Offices 3.800 sqm 93% 0 50000 100000 150000

  3. Main figures 3 2,5 2 PORTFOLIO 1,5 OPERATING 1 O&M 0,5 0 2010 2012 2014 2016 2017 250 80 200 70 60 Fimer 150 Fimer Group 50 Industrial 40 Fimer Fimer 100 30 Group Industrial 20 2017 50 10 82,6 Mln € Turnover 238 Fimer Group Fimer Group Employees 0 63,5 Mln € Turnover 0 2014 2015 2016 2017 195 Fimer Fimer Industrial 2007 2009 2011 2013 2015 2017 Employees

  4. Central Modular Inverter FIMER architecture VS Standard Central solutions

  5. Fimer VS Standard central arch.  10 Modular Master-Slave (Fimer VS standard central solution)  Power Stack parallel DC&AC side – 1 MPPT (with internal sync – only way to erase current leackage to earth )

  6. Plus EFFICIENCY DIAGRAM EFFICIENCY DIAGRAM MONOLITHIC INVERTER 4 MODULE INVERTER Eff Eff P/Pn P/Pn 100% 50% 100% 50% Eff EFFICIENCY DIAGRAM 10 MODULE INVERTER P/Pn 100% 50%

  7. Modular Power System The most reliable, competitive and advanced technology available MPS system (Modular Power System) is a particular architecture for power modules of FIMER inverters which GUARANTEES HIGHER EFFICIENCY & Energy Production compared to conventional centralized inverters. This Technology maximize all the advantages of the Central and Distributed configuration. Thanks to this system our inverters’ power modules switch on gradually PRODUCING ENERGY AT ONLY < 700W generated by the PV plant. This means that a FIMER inverter SWITCHES ON EARLIER AND SWITCHES OFF LATER! The result is that FIMER inverters produce on average 11% MORE than conventional PV inverters. This highst efficiency means HIGHER GAIN already in the first working years of the machine and warranty period.

  8. Modular Central solutions VS String Distributed architecture

  9. General PV plant configuration CENTRAL INVERTER DC/AC AC PARALLEL PV PLANT DC CABLE CONNECTION CONVERSION CONNECTION STRING INVERTER PV PLANT DC DC/AC AC PARALLEL CABLE CONVERSION CONNECTION CONN.

  10. PV Plant configuration VS • MPPT power from 10 kWp up to 100 kWp. • MPPT power from 160 kWp up to 1,6 MWp. • Big number of MPPT is a plus only in It’s enough to have uniform radiation to • case of not uniform radiation (e.g. roof, local shadow, hot spot dirty). have a better performance with a unique MPPT. - all PV power to a single stack. - low starting threshold.

  11. DC cable connection/ Combiner box VS • Direct connection between PV string • Energy transport on DC voltage. and Inverter. • Simple external combiner box. • Energy transport on AC side and AC losses are 150% higher than DC losses. • Flexibility of configuration.

  12. DC/AC Conversion VS • Limited nr. of inverters (4 or 6 per • Bigger number of inverters/components conversion unit). (MTBF) • In case of fault PV generator the power In case of inverter fault the PV subplant doesn’t • to inverter is the same (only a clamp of produce energy. one stack). In case of maximum indication and only in the first years of life of the PV moduls.

  13. AC parallel connection VS • External expensive Panel with two or • Direct connection from Inverter to three level of AC parallel Circuit Breaker. MV-LV Transformer. (up to 3,200 A) *very expensive and difficult to be procured All AC power connection are verified • during factory test. • Losses of these AC boxes are not considered with the inside inverter efficiency. • Difficult to create a switching syncronism for a big number of inverter paralleled on AC side.

  14. Distributed solution critical points in utility PV scale

  15. Minus of ‘ distributed ’ solutions AC Distribution Grid code compliance Costs Commissioning time False mithos and O&M Advantages

  16. AC Distribution  AC PARALLEL PANEL: this panel connects all the inverter together on AC side. AC panel could be splitted in two different types; one (see picture) close to MV/LV transformer and other panels for first parallel level distributed on field. For central solution there is only a point to point connection between the inverter and MV/LV transformer.  AC LOSSES: this panel has switches and Circuit Breaker in series to power flow and this reduce the BOS efficiency.  FAULT PROBABILITY (MTBF): Higher number of AC connection increases the probability of fault of PV plant.

  17. Grid Code Compliance PREMISE: Connection rules and grid compliances impose much more restrictive constraints to the system every day. And evry day we are subject to updated of the PPCs. Very fast response times from external commands (disconnection, power limitation) or digital frequency control loop (voltage frequency regulation).  Centralized Inverter: They’re checked by a PLC conversion unit that directly controls them with digital and analog signals (very fast).  String Inverter: They can only be checked via modbus or wifi (slow and unsafe bus because of the adjustment loop).

  18. Costs ITEM MODULAR CENTRAL DISTRIBUTD SOLUTIONS ITEM SOLUTION INVERTER 28,500 29,000 INVERTER LV – MV – TRAFO CONVERSION UNIT OR 30,700 29,500 SKIN + MV SG (TRAFO + MW SG) COMBINER BOX 4,500 12,000 LV AC PARALLEL BOX BOS 29,740 37,600 BOS COMMISSIONING 3,700 5,200 COMMISSIONIG TOTAL SOLUTION 67,400 + 29,740 75,700 + 37,600 TOTAL SOLUTION € /MWp

  19. Commissioning time  Centralized Inverter: PPC and Scada systems are wired and tested at the factory, reducing commissioning time due to Inverter / PPC communication.  String Inverter: Reduced number of DC connections but increased number of AC side connections.

  20. False mithos Standard Central String Inverter Inverter Weight 70 kg 1 module stack (heaviest component) 18 kg (minimum 2 technician) (1 technician) Outdoor Indoor (any intervention is subject to weather conditions) (any intervention is possible in all weather conditions) Interaction of more than one vendor One vendor for all the issues for commissioning, O&M & warranties Longer Commissioning Time Shorter commissioning Time Total setting on plant Pre-setting on factory

  21. O&M Advantages  Modular stacks are indipendently managed from Supervisor Control Unit.  When a fault happens in one stack, the other can work fine.  Power from PV field is managed from the other nr. 9 power stacks .  The only case of convertion power loss is when PV field gives more than 9/10 of nominal power. P 100% 90% POWER PRODUCTION DURING ONE FAULT LOSS OF PRODUCTION Time

  22. Local Content possibilities STRING SOLUTION CENTRAL SOLUTION - Production line of string - Local production of the main inverters only electromechanical - Difficulties on implementing, components locally, a reliable production - Assembly lines for line for advanced electronic Conversion units or skid - All the main components are - Local production of MV out of the SoW of the power transformers inverter manufacturer - Local production of - No local people involved in combiner boxes the plant construction phase - Local production of MV switch gears - Many people involved during construction phase.

  23. Thank you for your attention. Fimer, Inverter for Life

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend