Central VS Distributed Architecture
in utility PV plants
Central VS Distributed Architecture in utility PV plants Main - - PowerPoint PPT Presentation
Central VS Distributed Architecture in utility PV plants Main Figures FIMER INDUSTRIAL BUSINESS UNITS Zero CO emitted 2 2% 36.000 m2 Production area 128.000 m2 Total land area 3.800 m2 Offices and facilities 27% 3,560 MW *
in utility PV plants
71% 27% 2%
FIMER INDUSTRIAL BUSINESS UNITS
Solar Welding Air cond.
7% 93%
REVENUES FIMER INDUSTRIAL
Domestic Export
50000 100000 150000 Offices 3.800 sqm Production areas 36.000 sqm Total land area 128.000 sqm
HEADQUARTER
“Zero“ CO 2 emitted 36.000 m2 Production area 128.000 m2 Total land area 3.800 m2 Offices and facilities 3,560 MW * Solar division production capacity/year (String Inv. –Central Inv. - Storage Inv.) 150.000 Welding machines/year 420.000 PC Board dpt. production capacity/year 530 Conversion Units/year 15.800 Combiner Boxes production/year 6.200 Air conditioners/year * 4,120 MW by the end of the year
50 100 150 200 250 2007 2009 2011 2013 2015 2017
Fimer Industrial Fimer Group
10 20 30 40 50 60 70 80 2014 2015 2016 2017
Fimer Group Fimer Industrial
82,6 Mln € Turnover Fimer Group 63,5 Mln € Turnover Fimer Industrial 238 Fimer Group Employees 195 Fimer Employees
2017
0,5 1 1,5 2 2,5 3 2010 2012 2014 2016 2017
PORTFOLIO OPERATING O&M
(Fimer VS standard central solution)
DC&AC side – 1 MPPT (with internal sync – only way
to erase current leackage to earth)
EFFICIENCY DIAGRAM
MONOLITHIC INVERTER
Eff
P/Pn
100% 50%
EFFICIENCY DIAGRAM
4 MODULE INVERTER
Eff
P/Pn
100%
50% EFFICIENCY DIAGRAM
10 MODULE INVERTER
Eff
P/Pn
100% 50%
MPS system (Modular Power System) is a particular architecture for power modules of FIMER inverters which GUARANTEES HIGHER EFFICIENCY & Energy Production compared to conventional centralized
Thanks to this system our inverters’ power modules switch on gradually PRODUCING ENERGY AT ONLY < 700W generated by the PV plant. This means that a FIMER inverter SWITCHES ON EARLIER AND SWITCHES OFF LATER! The result is that FIMER inverters produce on average 11% MORE than conventional PV inverters. This highst efficiency means HIGHER GAIN already in the first working years of the machine and warranty period.
The most reliable, competitive and advanced technology available
CENTRAL INVERTER
STRING INVERTER
PV PLANT DC CABLE CONNECTION DC/AC CONVERSION AC PARALLEL CONNECTION
PV PLANT DC CABLE CONN. DC/AC CONVERSION AC PARALLEL CONNECTION
case of not uniform radiation (e.g. roof, local shadow, hot spot dirty).
have a better performance with a unique MPPT.
and Inverter.
losses are 150% higher than DC losses.
(MTBF)
produce energy.
conversion unit).
to inverter is the same (only a clamp of
In case of maximum indication and only in the first years of life of the PV moduls.
three level of AC parallel Circuit Breaker. (up to 3,200 A) *very expensive and difficult to be procured
considered with the inside inverter efficiency.
a big number of inverter paralleled on AC side.
MV-LV Transformer.
during factory test.
this panel connects all the inverter together on AC side. AC panel could be splitted in two different types; one (see picture) close to MV/LV transformer and other panels for first parallel level distributed on field. For central solution there is only a point to point connection between the inverter and MV/LV transformer.
this panel has switches and Circuit Breaker in series to power flow and this reduce the BOS efficiency.
Higher number of AC connection increases the probability of fault of PV plant.
They’re checked by a PLC conversion unit that directly controls them with digital and analog signals (very fast).
They can only be checked via modbus
the adjustment loop).
PREMISE: Connection rules and grid compliances impose much more restrictive constraints to the system every day. And evry day we are subject to updated of the PPCs. Very fast response times from external commands (disconnection, power limitation) or digital frequency control loop (voltage frequency regulation).
ITEM MODULAR CENTRAL SOLUTION DISTRIBUTD SOLUTIONS ITEM INVERTER 28,500 29,000 INVERTER CONVERSION UNIT OR SKIN (TRAFO + MW SG) 30,700 29,500 LV – MV – TRAFO + MV SG COMBINER BOX 4,500 12,000 LV AC PARALLEL BOX BOS 29,740 37,600 BOS COMMISSIONING 3,700 5,200 COMMISSIONIG TOTAL SOLUTION
67,400 + 29,740 75,700 + 37,600
TOTAL SOLUTION
€/MWp
wired and tested at the factory, reducing commissioning time due to Inverter / PPC communication.
but increased number of AC side connections.
Weight 70 kg (minimum 2 technician) Outdoor (any intervention is subject to weather conditions) Interaction of more than one vendor for commissioning, O&M & warranties Longer Commissioning Time Total setting on plant
1 module stack (heaviest component) 18 kg (1 technician) Indoor (any intervention is possible in all weather conditions) One vendor for all the issues Shorter commissioning Time Pre-setting on factory
LOSS OF PRODUCTION POWER PRODUCTION DURING ONE FAULT
Time
P
100% 90%
STRING SOLUTION
inverters only
locally, a reliable production line for advanced electronic
inverter manufacturer
the plant construction phase CENTRAL SOLUTION
electromechanical components
Conversion units or skid
power transformers
combiner boxes
switch gears
construction phase.
Thank you for your attention.