CDR SCU14 in ANKA TDR DEPENDING ON APPROVED FUNDING! 1 CDR - - PowerPoint PPT Presentation

cdr
SMART_READER_LITE
LIVE PREVIEW

CDR SCU14 in ANKA TDR DEPENDING ON APPROVED FUNDING! 1 CDR - - PowerPoint PPT Presentation

Nb 3 Sn Nb-Ti Technology Technology CDR SCU14 in ANKA TDR DEPENDING ON APPROVED FUNDING! 1 CDR proposal Cost estimate Coldmass cost estimate (per magnet). This cost estimate does not include the auxiliary infrastructure needed for


slide-1
SLIDE 1

Nb3Sn Technology Nb-Ti Technology

CDR TDR

DEPENDING ON APPROVED FUNDING!

SCU14 in ANKA

1

slide-2
SLIDE 2

CDR proposal – Cost estimate

Nb3Sn, kCHF Nb-Ti, kCHF Comparison

  • Stable operations

high margin to critical current and high temperature margin.

  • More options for cryogenics
  • peration at 4.5 K.
  • Shorter magnets can produce

same field amplitude

  • Proven technology, ductile

material but current design requires operation at 95% on the load line

Tooling 11.6 9.1 Components 321.1 130.2 Design Office 2.1 2.1 Manpower Manufacturing 97.5 75.1 Total Cost 432.2 216.5

2

Coldmass cost estimate (per magnet). This cost estimate does not include the auxiliary infrastructure needed for superconducting magnets such as cryo-refrigeration plants, cryostats, power supplies, and current leads

slide-3
SLIDE 3

Nb-Ti Baseline Design

  • Wiggler with similar parameters as CLIC damping-ring wiggler can

be used for beamline at ANKA.

  • Conceptual design done within CERN-KIT collaboration, technical

design within CERN-KIT-BINP collaboration until end of 2011.

  • Installation until end of 2012 (latest).

Open Issues:

  • What is the contribution of CERN, KIT, and BINP?
  • Vacuum, cryogenics, magnet protection, measurement, current

leads, interconnection issues must be addressed and coordinated. (Establishment of a project structure?)

3

slide-4
SLIDE 4

Nb3Sn Advanced Design

  • In parallel with the Nb-Ti baseline design we will advance with the

Nb3Sn design, first tests have shown the feasibility of Nb3Sn.

  • Nb3Sn technology for wiggler is less demanding than for accelerator

magnets (inner triplets, LHeC, 11 T dipole projects) because of modular geometry, force distribution, and short unit lengths of wire. Open issues:

  • Nb3Sn short model testing (unavailability of Block 4 until Summer

1011).

  • For a first full prototype around 20 km strand are needed (approx.

200 kCHF). Strand procurement has a long lead time; when to start with the procurement process?

  • Nb3Sn prototype design is planned to be finished by the end of

2011, but production delay due to LHC consolidation in 2012.

4

slide-5
SLIDE 5

5

Spending Profile

Budget (kCHF) 2010 2011 2012 2013 Material 20 220 60 30 Design Office 18 45 55 25 Workshop 32 30 50 80 FSU 50 50 50 100 Misc (Travel) 24 25 25 25 TOTAL 144 370 240 260