Nb3Sn Technology Nb-Ti Technology
CDR TDR
DEPENDING ON APPROVED FUNDING!
SCU14 in ANKA
1
CDR SCU14 in ANKA TDR DEPENDING ON APPROVED FUNDING! 1 CDR - - PowerPoint PPT Presentation
Nb 3 Sn Nb-Ti Technology Technology CDR SCU14 in ANKA TDR DEPENDING ON APPROVED FUNDING! 1 CDR proposal Cost estimate Coldmass cost estimate (per magnet). This cost estimate does not include the auxiliary infrastructure needed for
Nb3Sn Technology Nb-Ti Technology
DEPENDING ON APPROVED FUNDING!
SCU14 in ANKA
1
Nb3Sn, kCHF Nb-Ti, kCHF Comparison
high margin to critical current and high temperature margin.
same field amplitude
material but current design requires operation at 95% on the load line
Tooling 11.6 9.1 Components 321.1 130.2 Design Office 2.1 2.1 Manpower Manufacturing 97.5 75.1 Total Cost 432.2 216.5
2
Coldmass cost estimate (per magnet). This cost estimate does not include the auxiliary infrastructure needed for superconducting magnets such as cryo-refrigeration plants, cryostats, power supplies, and current leads
be used for beamline at ANKA.
design within CERN-KIT-BINP collaboration until end of 2011.
Open Issues:
leads, interconnection issues must be addressed and coordinated. (Establishment of a project structure?)
3
Nb3Sn design, first tests have shown the feasibility of Nb3Sn.
magnets (inner triplets, LHeC, 11 T dipole projects) because of modular geometry, force distribution, and short unit lengths of wire. Open issues:
1011).
200 kCHF). Strand procurement has a long lead time; when to start with the procurement process?
2011, but production delay due to LHC consolidation in 2012.
4
5
Budget (kCHF) 2010 2011 2012 2013 Material 20 220 60 30 Design Office 18 45 55 25 Workshop 32 30 50 80 FSU 50 50 50 100 Misc (Travel) 24 25 25 25 TOTAL 144 370 240 260