ccug 2013 meeting control system upgrades and retrofits
play

CCUG 2013 Meeting Control System Upgrades and Retrofits Arthur L. - PowerPoint PPT Presentation

CCUG 2013 Meeting Control System Upgrades and Retrofits Arthur L. Mayclin, PE Calpine Corporation Manager, I&C Engineering Agenda Control system overview Scope Procedure Legacy Status Technical Specification


  1. CCUG 2013 Meeting Control System Upgrades and Retrofits Arthur L. Mayclin, PE Calpine Corporation Manager, I&C Engineering

  2. Agenda • Control system overview • Scope • Procedure • Legacy Status • Technical Specification • Key Points 1

  3. Control System Overview DCS Control Level Indication Algorithm (Process Variable) Tank Level Setpoint Process Source Demand Control Valve Tank Supply (Controlled Variable) Pump Discharge Valve Process Discharge • The basic control system is an intermediary between process variables and controlled variables. The most simple case is level control for a tank. The control system reads the indicated level (process variable), compares it against the desired level (setpoint), and opens a valve (controlled variable) to adjust. 2

  4. Control System Overview DCS Automation Processor Station DCS I/O Rack DO Module AO Module DI Module AI Module Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface Module Spare Processor HMI Tank level setpoint generated in HMI and stored in processor Level Indication (Process Variable) Process Source Demand Control Valve Tank Supply (Controlled Variable) Pump Discharge Valve Process Discharge • These variables interface to the control system via input/output (I/O) modules, which connect to processors, where the control logic resides. Human machine interface (HMI) computers provide the interface between operators or programmers, and the control system. 3

  5. Control System Overview Upgrade Retrofit DCS Automation Processor Station DCS I/O Rack I/O Rack Interface I/O Rack Interface I/O Rack Interface DO Module AO Module DI Module AI Module Interface Module Processor Spare HMI • In general, an upgrade is performed by the same vendor and replaces only the outdated parts of the control system: Be it HMIs (software), processors, network equipment or all. A retrofit is the replacement of the entire system, which includes I/O modules. 4

  6. Scope • Upgrades: - Will encompass HMI computers and software. - May include processors and network equipment (including serial links). - 3 to 6 month schedule (engineer and build), and 1 to 2 weeks to install. HMI EWS Root Switch Root Switch Automation Processor Automation Processor I/O Rack Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface Processor Processor 5

  7. Scope • Retrofits: - Will encompass all components to the field terminations. - May include determ and reterm of field connections. - 6 to 9 month schedule (engineer and build), and 2 to 4 weeks to install. DCS I/O Rack HMI EWS DO Module AO Module DI Module AI Module Interface Module Spare Root Switch Root Switch Automation Processor Automation Processor I/O Rack Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface I/O Rack Interface Processor Processor Valve Transmitter 6

  8. Procedure – Risk Analysis High 3 1 H i g Regions: h L e Probability of Occurrence v e l R 1. Critical Importance i s k M e d i u 2. High Importance m L e v e l 3. Moderate Importance R i s k L 4. Low Importance o w L e v e l R i s k 4 2 Low Impact of Risk Low High • Probability of Occurrence: Occurrence being equipment failure and/or process interruption. Heavily influenced by historical data. Operating hours per year is also a factor. • Impact of Risk: Safety or monetary impact. 7

  9. Procedure Process Flow Chart for Control System Retrofits or Upgrades Analysis Yes Control System Yes Control System Hold to Next Meets Operational Supportable Budget Cycle Note 1 Note 2 Needs No No Validation No Cost Justified for Current Budget Cycle Yes Budgeting Yes Like Systems in Group Like Systems Fleet Budgeted for Single Bid Note 3 No Scheduling Upgrade Retrofit RFP or Sole Upgrade or Retrofit RFP Source Note 4 Note 5 Note 1: Supportable includes the availability of spare parts as well as Note 4: For some upgrades, a sole source is justified since a technical support services. competitive bid is impossible. Notes Note 2: Operational needs includes the ability to operate properly, add Note 5: The RFP procedure would consist of a technical logic, or system expansion for plant upgrades. specification, including training, installation, and project completion dates. For Spring outage installations, costs Note 3: Like systems are those that are capable of being upgraded or may be incurred over two budget cycles. retrofitted by the same vendor. 8

  10. Legacy Status • Always Verify with the OEM • Emerson WDPF (ten year support commitment): - Level-8: January 2012 - Q-Line I/O: January 2018 • Emerson Ovation (five year support commitment): - Release 3.2: May 2014 - Release 3.3: July 2015 - Release 3.5: October 2017 • Siemens TXP: - All releases no longer supported. - Network gear no longer supported. - ET200M I/O supported (no end date published) 9

  11. Legacy Status • Millennium Control System - Fanuc 90-70 (new parts not being manufactured). - Field I/O no longer supported. - Mark VI (some cards not available new) - Software! • Toshiba D-EHC - HMI computers no longer supported (as well as the NCCX and Processors for C900 system). • Mark V: - Hardware no longer supported - HMI additions required. • Mark VI: - Formal support to 2018 with exceptions: - Processor and communication cards - Network equipment - Software 10

  12. Legacy Status • Siemens T-3000: - All versions supported but significant development ongoing - ET200 I/O still standard - Application Server virtualized but all previous versions supported - Scalance network switches (recommend X-300 managed) • Woodward - 501, 505, Netcon are all legacy but can still be supported if spare parts are available (knowledge is still available). • Allen Bradley - PLC5 legacy but spares can be found - SLC supported - ControlLogix, CompactLogix, and MicroLogix are now standard • GE Fanuc - Fanuc 90-70: No new parts - Fanuc 90-30: Supported 11

  13. Technical Specification • Topics: - Scope - Overview - Furnished by Seller and Buyer - Codes, Standards or Regulations (if pertinent) - Equipment Specifications (what it is) - Number of HMIs, number of monitors, mounting, etc. - Links - Network - Technical Requirements (how it works) - Trending, alarming, logging, diagnostics, failure modes, accuracy, redundancy, etc. - Execution - Project management - Schedule - FAT 12

  14. Technical Specification • Topics: - Execution (continued) - Installation and commissioning (coordinate with schedule) - Ancillaries - Training - Options (what you may add if the price is right) • Critical Issues (ensure they are covered sufficiently): - Commissioning, since available time is always a factor. - Equipment protection (all trips and protective settings) - Equipment operation (primary control devices) - Indications (if time permits) - Project Management. Ensure the seller provides overall on-site management during installation and commissioning (especially for turn-key retrofit covering both BOP and turbines). 13

  15. Key Points • A vendor’s quote is targeted at reducing their risk! • A technical specification enforces what you require, not what the vendor is willing to sell you. Include it in the contract or reference it in the PO. • Full documentation is essential to prevent assumptions. - Accurate I/O count by type and location. - Logic diagrams. - Electrical schematics and wiring diagrams. - Serial link delineation (integration with other systems). • A turn-key project prevents the vendor from blaming others for delays. - Installation and testing will occur during an outage when people are busy with other projects. - Equipment may be required to remove and install control cabinets. - Laydown and storage area may be required for electronic equipment (sheltered from the elements). 14

  16. Key Points • Verify key dates (schedule): - Kick-off and transfer of all pertinent documentation. - Design review (prior to hardware or software freeze). - Hardware and Software FAT. - Equipment shipped to site. Once equipment arrives at site, liability for damages shifts to the buyer. - If schedule slips, have Seller store the equipment (added cost is worth it). - Mobilization at site and scheduled completion. - Breakdown and schedule all activities at site to ensure they mesh with other work ongoing at that time. - Murphy rules! Provide contingency where possible. • The FAT is free training but limit interference with the vendor once on site. • Hold back as much money for final payment as possible. 15

  17. Key Points • Cost adders: - Contractor support for evaluation and review - Technical specification - Bid evaluation - Hardware Design - Logic - FAT support - Commissioning support - Cabling additions - Fiber optic - Electrical - Links - HVAC - Furniture 16

  18. Key Points • Upgrade only if absolutely necessary: - Existing system: - Burn in complete, with all bugs worked out - Support personnel trained - Known history of issues to fall back on - Operator familiarity - Spare parts (unless the lack of them is a reason to upgrade) - Board level repair can extend spare part lifetimes considerably. - New system: - Punch list! - Warrantee period! - New manuals and training - Patch path just beginning 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend