CBD COMMUNITY REFERENCE GROUP MEETING 10 Friday 08 June 2018 JOHN - - PowerPoint PPT Presentation

cbd community reference group
SMART_READER_LITE
LIVE PREVIEW

CBD COMMUNITY REFERENCE GROUP MEETING 10 Friday 08 June 2018 JOHN - - PowerPoint PPT Presentation

CBD COMMUNITY REFERENCE GROUP MEETING 10 Friday 08 June 2018 JOHN HOLLAND EARLY WORKS PROGRAM UPDATE METRO TUNNEL EARLY WORKS TOWN HALL STATION UPDATE TOWN HALL STATION TIMELINE EARLY WORKS KFC DEMOLITION & NICHOLAS BUILDING WORKS


slide-1
SLIDE 1

MEETING 10 Friday 08 June 2018

CBD COMMUNITY REFERENCE GROUP

slide-2
SLIDE 2

JOHN HOLLAND EARLY WORKS PROGRAM UPDATE

slide-3
SLIDE 3

METRO TUNNEL EARLY WORKS TOWN HALL STATION UPDATE

slide-4
SLIDE 4

TOWN HALL STATION TIMELINE – EARLY WORKS

slide-5
SLIDE 5

KFC Demolition

  • Develop separation methodology between KFC

and Nicholas Buildings - end June

  • Building demolition – mid-August

Nicholas Building works

  • Fit out works of Souvenir shop for handover – mid-

June

  • Internal amenities relocation (sewer works,

emergency stairwell) – late June

  • Basement wall construction – mid-June

KFC DEMOLITION & NICHOLAS BUILDING WORKS

slide-6
SLIDE 6

PORT PHILLIP ARCADE DEMOLITION

slide-7
SLIDE 7
  • Revision of methodology for demolition
  • f PPA Flinders St frontage – current
  • Remaining structure to be demolished –

mid-July

PORT PHILLIP ARCADE DEMOLITION

slide-8
SLIDE 8

METRO TUNNEL EARLY WORKS STATE LIBRARY STATION UPDATE

slide-9
SLIDE 9

STATE LIBRARY STATION TIMELINE – EARLY WORKS

slide-10
SLIDE 10
  • 24 hour works are now underway at both

shaft sites within the acoustic sheds

  • Deliveries of props, beams and materials

24 hours a day being prioritised to occur in early evenings from remote locations

  • Doors to be closed for all night works

FRANKLIN STREET & A’BECKETT STREET SHAFT UPDATE

slide-11
SLIDE 11

FRANKLIN STREET & A’BECKETT STREET SHAFT UPDATE

slide-12
SLIDE 12
  • Franklin Street utility relocation works,

between Swanston Street and Stewart Street, are now complete

  • Ongoing reinstatement works taking place
  • Weekend closures of Franklin Street

required for inspection

  • f recently completed drainage works until

the end of June

FRANKLIN STREET WEST SERVICE RELOCATION UPDATE

slide-13
SLIDE 13

CROSS YARRA PARTNERSHIP UPDATE

slide-14
SLIDE 14
  • We have completed drilling the current series of

boreholes

  • Works to connect the first series of boreholes on the

northeast side of Victoria Street are nearing completion with reinstatement works underway.

  • Upcoming works to service prove two water mains

will be done at night on the west and east side of Victoria Street given the assets location in the road

  • Service proving will be used to inform the design to

connect the south and north side series of wells ahead of night works to install pit and pipe network in the southbound lane on Victoria St between Swanston and Therry streets

GROUNDWATER MONITORING UPDATE

slide-15
SLIDE 15
  • 1. Property Condition Surveys Update
  • 2. Metro Tunnel Station Designs Update
  • 3. State Library Station Precinct Update
  • 4. Town Hall Station Precinct Update
  • 5. Underground Construction Methodology
  • 6. Acoustic Enclosure Methodology

AGENDA

slide-16
SLIDE 16

PROPERTY CONDITION SURVEY UPDATE

slide-17
SLIDE 17
  • Property condition surveys will be carried out prior to the first major construction

activity in a particular area

  • A post construction inspection will also be carried out
  • An intermediate inspection may occur if identified as appropriate during initial

assessment or/if a damage claim is made.

PROPERTY CONDITION SURVEYS

slide-18
SLIDE 18

QUESTIONS?

slide-19
SLIDE 19

METRO TUNNEL STATION DESIGN UPDATES

slide-20
SLIDE 20

NORTH MELBOURNE – LAURENS STREET ENTRANCE

slide-21
SLIDE 21

NORTH MELBOURNE - CONCOURSE

slide-22
SLIDE 22

NORTH MELBOURNE - PLATFORM

slide-23
SLIDE 23

PARKVILLE - CONCOURSE

slide-24
SLIDE 24

PARKVILLE - GRATTAN STREET ENTRANCE

slide-25
SLIDE 25

PARKVILLE - PLATFORM

slide-26
SLIDE 26

STATE LIBRARY – LA TROBE STREET ENTRANCE

slide-27
SLIDE 27

STATE LIBRARY - PLATFORM

slide-28
SLIDE 28

TOWN HALL – CITY SQUARE ENTRANCE

slide-29
SLIDE 29

TOWN HALL – COCKER ALLEY ENTRANCE

slide-30
SLIDE 30

TOWN HALL - CONCOURSE

slide-31
SLIDE 31

TOWN HALL – FEDERATION SQUARE ENTRANCE

slide-32
SLIDE 32

TOWN HALL - PLATFORM

slide-33
SLIDE 33

ANZAC STATION – ALBERT ROAD RESERVE

slide-34
SLIDE 34

ANZAC STATION – ALBERT PARK RESERVE

slide-35
SLIDE 35

ANZAC STATION - CONCOURSE

slide-36
SLIDE 36

ANZAC STATION - ENTRANCE

slide-37
SLIDE 37

ANZAC STATION - PLATFORM

slide-38
SLIDE 38

QUESTIONS?

slide-39
SLIDE 39

STATE LIBRARY STATION UPDATE

slide-40
SLIDE 40

INDICATIVE CONSTRUCTION DATES

slide-41
SLIDE 41
  • Little La Trobe Street works
  • Service investigations (Tuesday 12 June)
  • Service relocations (late July start)
  • Demolition of 12-16 (Stax; Building 38) and 18-20 (Doki Doki) Little La

Trobe Street in 2 stages (mid-July start)

  • La Trobe Street site: next 3-6 months
  • Slab demolition (3-4 weeks)
  • Archaeological dig (4 weeks)
  • Piling (late July – January)
  • Cribbing installation

STATE LIBRARY UPDATE

slide-42
SLIDE 42

LA TROBE STREET PILING

slide-43
SLIDE 43

STAGE 1-2: LA TROBE STREET PILING

slide-44
SLIDE 44

STAGE 3: LA TROBE STREET PILING

slide-45
SLIDE 45

STAGE 4: LA TROBE STREET PILING

slide-46
SLIDE 46

STAGE 5: LA TROBE STREET PILING

slide-47
SLIDE 47

STAGE 6: LA TROBE STREET PILING

slide-48
SLIDE 48

STAGE 7: LA TROBE STREET PILING

slide-49
SLIDE 49

LITTLE LA TROBE STREET DEMOLITION – LOCATIONS

slide-50
SLIDE 50

STAGE 1: 18-20 LITTLE LA TROBE STREET

slide-51
SLIDE 51

STAGE 2: 12-16 LITTLE LA TROBE STREET

slide-52
SLIDE 52

QUESTIONS?

slide-53
SLIDE 53

TOWN HALL STATION UPDATE

slide-54
SLIDE 54

INDICATIVE CONSTRUCTION DATES

slide-55
SLIDE 55

City Square site set up activities for June and July

  • Saw cutting of perimeter and removal of slab
  • Delivery of equipment including excavator
  • Soil testing
  • Reconfiguration of ramp
  • Demolition of structure behind ramp
  • Hoarding retrofit
  • Heavy equipment delivery (e.g. piling rig, crawler crane)
  • Piling

Flinders Quarter site

  • Archaeology investigations

TOWN HALL UPDATE

slide-56
SLIDE 56

RAMP WORKS

slide-57
SLIDE 57

RAMP WORKS: RECONFIGURATION

slide-58
SLIDE 58

QUESTIONS?

slide-59
SLIDE 59

UNDERGROUND CONSTRUCTION METHODOLOGY

slide-60
SLIDE 60

TOWN HALL – UNDERGROUND

slide-61
SLIDE 61

TOWN HALL - CONCOURSE

slide-62
SLIDE 62

STATE LIBRARY – UNDERGROUND

Connection to Melbourne Central Station

slide-63
SLIDE 63

STATE LIBRARY - PLATFORM

slide-64
SLIDE 64

ROAD HEADER OPERATIONS

slide-65
SLIDE 65

PRIMARY GROUND SUPPORT

slide-66
SLIDE 66

WATERPROOF LINING

slide-67
SLIDE 67

CONCRETE LINING WORKS

slide-68
SLIDE 68

QUESTIONS?

slide-69
SLIDE 69

ACOUSTIC ENCLOSURE METHODOLOGY

slide-70
SLIDE 70

Design considers

  • Building fabric
  • Doors and seals
  • Roller doors
  • Airflow paths
  • Truck movements
  • Noise control of plant and equipment

ACOUSTIC SHED DESIGN

slide-71
SLIDE 71

NOISE CONTROL ELEMENTS

Splitter-silencers Acoustic louvres

Absorption between splitters/louvres to reduce sound while allowing airflow Constructions selected to reduce transmission of sound through building elements

Wall construction Door and seals

slide-72
SLIDE 72

NOISE CONTROL ELEMENTS CONT.

Reduces noise of individual items of

  • plant. Requires detailed design.

Controls noise breakout, minimises duration of

  • pen doorway.
slide-73
SLIDE 73

VIBRATION CONTROL ELEMENTS

Spring isolation

Reduces vibration energy transmitted into the structure Reduces structure-borne energy transferring through building elements

Wall construction

slide-74
SLIDE 74

Software considers:

  • 3D geometry
  • Area of source
  • Reflections off buildings
  • Spectral content of sound
  • Air absorption
  • Ground effect
  • Angle of view

MODELLING

slide-75
SLIDE 75

QUESTIONS?

slide-76
SLIDE 76

PEDESTRIAN MODELLING RESULTS

RAIL PROJECTS VICTORIA PRESENTATION

slide-77
SLIDE 77

PROCESS TO DETERMINE STATION ENTRANCES – VITM

Victorian Integrated Transport Model (VITM)

Resident population Number of jobs Educational enrolments Input land use assumptions At city-block level of detail Number of trips to and from each geographic zone by car, walking, and public transport. Determines use of station entries/exits

slide-78
SLIDE 78

PROCESS TO DETERMINE STATION ENTRANCES – VITM – EXAMPLE

  • Graphic shows 2031 AM

Peak Town Hall Station walk access catchment distributions

  • Higher colour densities

represent more trips to/from that city-block zone

  • 58% of people accessing

the station will walk. The remaining 42% will interchange to/from trams.

slide-79
SLIDE 79

TOWN HALL 2031 AM PEAK STATION ENTRY AND EXIT FOOTFALL

10,300 6,700 1,800 1,500

  • 2031 AM two hour

peak Town Hall Station walk entries and exits

  • Flinders Street Station

passengers and interchanging passengers are not included in totals

  • Similar distribution
  • bserved for PM peak

Values rounded to nearest 100 passengers

slide-80
SLIDE 80

STATE LIBRARY 2031 AM PEAK STATION ENTRY AND EXIT FOOTFALL

6,700 7,900 1,900

  • 2031 AM two hour

peak State Library Station walk entries and exits

  • Melbourne Central

passengers and interchanging passengers are not included in totals

  • Similar distribution
  • bserved for PM peak

Values rounded to nearest 100 passengers

slide-81
SLIDE 81

STATE LIBRARY + MELBOURNE CENTRAL 2031 AM PEAK STATION ENTRY AND EXIT FOOTFALL

6,700 12,500 8,400

  • 2031 AM two hour

peak State Library Station walk entries and exits

  • For comparison with

the previous slide, Melbourne Central passengers are included in totals. Interchanges are not.

  • Similar distribution
  • bserved for PM peak

Values rounded to nearest 100 passengers 6,400

slide-82
SLIDE 82

ASSESSMENT OF PEDESTRIAN CIRCULATION AT STREET LEVEL

Background flows (b) Station flows (s) Tram flows (t)

Walking trips not associated with the Metro Tunnel Station, nor the adjacent tram stops Walking trips to and from the station and their distribution around the precinct Walking trips to and from tram stops near the station

People walking through precinct

slide-83
SLIDE 83

ASSESSMENT OF BACKGROUND FLOWS AT STREET LEVEL

  • Pedestrian survey in AM and PM peak

periods undertaken since 2015,

  • ngoing
  • Survey analysed to determine current

day background (non station and non tram) flows

  • Growth applied to the background

flows to obtain 2031 background matrix

  • Growth based on VITM model
  • Growth between current data and

2031 is 2.16% p.a.

slide-84
SLIDE 84

ASSESSMENT OF STATION EXIT FLOWS AT STREET LEVEL: EXAMPLE

  • Zones for pedestrians exiting

from the City Square exit and dispersing to/from the Collins Street precinct are sub-divided

  • Forecasts for residents, jobs,

and educational enrolments for each sub-zone assessed to provide distribution of station walk access trips

slide-85
SLIDE 85

ASSESSMENT OF TRAM ACCESS FLOWS AT STREET LEVEL: EXAMPLE

  • VITM provides tram trips between
  • rigin and destination (zone) and

station

slide-86
SLIDE 86

ONGOING WORK TO ASSESS PEDESTRIAN PRECINCT FLOWS

  • Pedestrian modelling undertaken through Reference Design and

EES to assess base (no project) and project case pedestrian flows, assess capacity and pedestrian comfort, and inform design

  • CYP currently building new models, with CYP station design and

updated data, to assess CYP stations

slide-87
SLIDE 87

QUESTIONS?

slide-88
SLIDE 88

GENERAL FEEDBACK AND ITEMS FOR FUTURE DISCUSSION

slide-89
SLIDE 89