CBD COMMUNITY REFERENCE GROUP MEETING 15
26 OCTOBER 2018
CBD COMMUNITY REFERENCE GROUP MEETING 15 26 OCTOBER 2018 JOHN - - PowerPoint PPT Presentation
CBD COMMUNITY REFERENCE GROUP MEETING 15 26 OCTOBER 2018 JOHN HOLLAND EARLY WORKS UPDATE TOWN HALL STATION TIMELINE EARLY WORKS KFC & PORT PHILLIP ARCADE DEMOLITION & NICHOLAS BUILDING WORKS Port Phillip Arcade Demolition
26 OCTOBER 2018
TOWN HALL STATION TIMELINE – EARLY WORKS
Port Phillip Arcade Demolition
Former KFC building Demolition
KFC building will be ongoing until late November
Nicholas Building works
following completion of KFC demolition
STATE LIBRARY STATION TIMELINE – EARLY WORKS
all John Holland facilities and materials now removed
to CYP anticipated in late November
FRANKLIN STREET & A’BECKETT STREET SHAFT UPDATE
Completed works
Underway
westbound lanes on Victoria Street
Therry Streets
wells into system requiring occupation of kerbside carparks
– until December
1. Creative Program Update 2. Piling 3. State Library Station Update 4. Town Hall Station Update
METRO TUNNEL CREATIVE PROGRAM
Presented by Mary Parker October 2018
Walking Tours for Open House
community partnership with Koorie Heritage Trust
Design Matters’ at KHT
Practitioner site visit to archaeology dig
as part of Melbourne Music Week
the city
indicative
NAIDOC week
collaboration with RMIT
Melbourne for City Square
visit to prompt concepts
excavation of the shafts
Complete Complete Commencing late Oct 2018
Commencing mid- November 2018
Commencement 2019 Indicative
In Progress – 25%
Commencement Q1 2019
Commencement Q1 2019
Activity Involves Timing
Set up construction shaft site and laydown area
requiring Franklin Street southside footpath closure
Ongoing – November 2018 Piling platform and support works
Ongoing – late October 2018 Piling at shaft site
Late October 2018 – Q2 2019
Indicative
Activity Involves Timing
Site establishment / handover
equipment
Stewart Street for workers
work sites
22 October – December 2018 Material delivery
Early-mid November Excavation
Ongoing
Indicative
Street
establishment works, Stewart Street will re-open as a one-way street, running southbound direction.
Indicative
Activity Involves Timing
Demolition
Trobe and Literature Lane
Lane to allow for safe removal of material for Doki Doki demolition 29 October 2018 – February 2019
Archaeology
to excavate the area February – June 2019
Further relocation works
piling
Lane traffic changes Sewer relocations: January 2019 Gas proving: Mid-late November Gas relocation: Mid-2019
Indicative
Indicative
Activity Involves Timing
Archaeology
to excavate the area Ongoing – November 2018
Driveway installation
Yarra Trams to remove) Completed
Piling preparation
Trobe
compaction) Ongoing – mid November 2018
Piling
From mid November 2018
Indicative
Indicative
Activity Involves Timing
Material removal
required up to 7pm Ongoing Piling
Ongoing – February 2019 Collins Street civil works
gate that accommodates larger vehicles
Collins Street footpath End November TBC
Indicative
Oversized deliveries are required at this time due to relevant traffic permits
10pm – 6am
– Friday 9 November, 10pm – 6am
Flinders Lane will be closed between Swanston Street and Russell Street during these deliveries
What:
accommodates larger vehicles
footpath When:
for 3 weeks
5am), from early January for 1 week TBC Traffic/Pedestrian changes:
during working hours TBC
Activity Involves Timing
Archaeology
and hand tools to excavate the area Ongoing – December 2018 Demolition of archaeology footings*
excavators, and a tipper truck to remove previous building footings Ongoing – December 2018 Port Phillip Arcade basement demolition (JHEW)
excavators
Ongoing – November 2018 Piling preparation works
(nightworks) Ongoing – January 2019 Piling
Late January – August 2019
Indicative
What:
When: 8pm – 6am, Sunday to Thursday from 7th – 30th November 2018 Pedestrian changes:
between Young & Jackson and the Nicholas Building
Activity Involves Timing
Flinders Street civil works
lane
changes
Ongoing – mid November (nightworks)
Demolition
Shard and Federation Deck Ongoing until January 2019
Indicative
Stage 3: Ongoing – mid November Construction of a concrete barrier using an excavator, jackhammer and saw cut between the two westbound left-hand turning lanes When: 10pm – 5am
Stage 4: Early – late November
jackhammer and saw cut
the corner of Federation Square at the Flinders Street and Swanston Street intersection
When: 10pm – 5am
Kerb Works Tram pole relocations: two nights
Groundwater well installation Recharge Testing
What
wells
pedestrians changes during works
existing well locations
will need to be established
pedestrian changes during works When
For certain well locations, out
minimise disruption
Out of hours work is required in
Site handover: Tuesday 30 October 2018 Public parking will be removed until late 2023 This involves:
installation