Carroll County Public Schools FY 2018 Capital Budget and FY 2019 - PowerPoint PPT Presentation

Carroll County Public Schools FY 2018 Capital Budget and FY 2019 FY 2023 Capital Improvement Program Request Board of Education Work Session August 24, 2016 1 CCPS Capital Budget Process Educational Facilities Master Plan June


  1. Carroll County Public Schools FY 2018 Capital Budget and FY 2019 – FY 2023 Capital Improvement Program Request Board of Education Work Session August 24, 2016 1

  2. CCPS Capital Budget Process  Educational Facilities Master Plan June  Presentation/Board Work Session August  Public Hearing September  Approval by Board of Education October  Submission to County and State October  County adoption of Budget May  State approval of final CIP May 2

  3. Focus of CIP Request  Career & Technology Center Project  Replacement of 12 Single Ply Roofs that are past their useful lives  Replacement of 7 Heating, Air Condition, and Ventilating (HVAC) Systems that are past their useful lives 3

  4. Career & Technology Center Project  Current Scope based on 2006 Study.  New Scope Study currently underway (Kickoff Meeting was held on August 10 th )  Anticipated Completion by January  New Study will look to address waiting list for CTE programs  New study will examine if WHS can house some CTE programs 4

  5. Roofing Projects  Plan replaces 12 single ply roofs that are past their useful lives  Implementation of this plan will replace all single play roofing systems 5

  6. HVAC Systems  Plan replaces seven HVAC systems that are past their useful lives  Average age of HVAC systems = 34 years 6

  7. Security Project  Project includes funding for the replacement of aging surveillance and security equipment  Also includes funding for the expansion of the existing system (new camera and access control locations)  Project also includes funding for upgrades to existing bus surveillance system 7

  8. Technology Project  Project includes funding for the replacement of aging technology infrastructure (servers, switches, routers and firewalls)  Also includes funding for the expansion of technology infrastructure to meet new demands (communication system upgrades, telephone system upgrades, intelligent classroom upgrades, etc.) 8

  9. Kindergarten Additions  Planning for first projects was deferred until FY19  Plan includes last four Kindergarten Additions required as part of the move to Full Day Kindergarten  Kindergarten classes are currently being held in classrooms not designed to meet the instructional needs of Kindergartners  Three of the Four remaining schools also have Prekindergarten programs which are utilizing space originally built to house Kindergarten  PRIDE program addition is included in Friendship Valley ES project 9

  10. High School Science Rooms  Plan includes the renovation of 13 science classrooms at our oldest high schools that have not been renovated to meet today’s instructional program 10

  11. Other Systemic Renovations  Plan includes the replacement of aging electrical equipment at Westminster High and Sykesville Middle  Plan includes the replacement of existing windows at South Carroll High, East Middle and Westminster High 11

  12. FY18 County Request ($000) omitted 1. Carrolltowne ES Roof $779 2. Runnymede ES Roof $945 3. Robert Moton ES Roof $970 4. Elmer Wolfe ES Roof $905 5. East MS HVAC $903 6. Sandymount ES HVAC $418 7. Westminster HS Electrical $100 8. Westminster HS Science Renovation $100 12

  13. FY18 County Request ($000) omitted 9. Security Improvements $2,100 10.Technology Improvements $1,350 11.Paving $ 550 12.Roof Repairs $ 170 13.Barrier Free Modifications $ 50 TOTAL $9,340 13

  14. FY19 – FY23 County Request County Share of FY19-FY23 Request = $111,913,000 Career & Technology Center project 8 Roof Replacement projects 7 HVAC Replacement projects 4 Kindergarten Addition projects 3 Science Room Renovation projects 2 Electrical Service projects 3 Window Replacement projects Annual Requests (Security, Technology, Paving, Roofing, Barrier Free Modifications, & Relocatables) 14

  15. County CIP & BOE Request $60,000 $50,000 $40,000 County CIP $30,000 (FY18-F22) $20,000 BOE Request $10,000 $- 18 19 20 21 22 23 ($000) Omitted 15

  16. FY18 State Request ($000) omitted 1. Carrolltowne ES Roof $ 833 2. Runnymede ES Roof $ 1,012 3. Robert Moton ES Roof $ 1,039 4. Elmer Wolfe ES Roof $ 968 State Total $ 3,852 16

  17. State Construction Funding $40,000,000 $35,000,000 $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $- 05' 06' 07' 08' 09' 10' 11' 12' 13' 14' 15' 16 17 18 19 20 21 22 23 Historic State Funding State Funding based on BOE Request State Funding based on County CIP 17

  18. Questions? 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.