capital operating costs
play

Capital & Operating Costs Generic Case Study- SOx and - PowerPoint PPT Presentation

Capital & Operating Costs Generic Case Study- SOx and Sensitivity to Gold Price 400US$/oz 120 110 100 Relative NPV (US$M) 90 80 500 70 60 450 50 40 400 0 10 20 30 40 50 60 70 80 90 100 Sulphide Oxidation (%)


  1. Capital & Operating Costs • Generic Case Study- SOx and Sensitivity to Gold Price 400US$/oz 120 110 100 Relative NPV (US$M) 90 80 500 70 60 450 50 40 400 0 10 20 30 40 50 60 70 80 90 100 Sulphide Oxidation (%) Relative NPV (US$M) 350 600US$/oz 300 240 400US$/oz 220 250 600US$/oz tive NPV (US$M) 200 200 180 800US$/oz 160 Re la 150 140 1,000US$/oz 120 100 100 0 10 20 30 40 50 60 70 80 90 100 50 Sulphide Oxidation (%) 0 800US$/oz 0 10 20 30 40 50 60 70 80 90 100 400 350 Sulphide Oxidation (%) PV (US$M) 300 e N Relativ 250 200 150 0 10 20 30 40 50 60 70 80 90 100 Sulphide Oxidation (%) 31

  2. Project Updates 32

  3. Project Updates • Las Lagunas Project  Developed by EnviroGold Limited  Location: Dominican Republic  JORC Resource 5.14Mt tailings @ 3.76 g/t Au & 38.62 g/t Ag  Flotation + Albion Process + CIL flowsheet  Lycopodium Minerals QLD P/L (Brisbane) completed detailed engineering  Design basis: 800ktpa tailings and 80k oz/y Ag+Au  Project Life- 6.5 years  Construction by local contractor (IRISA) >40% complete  Albion Process leach tanks (SS) to be shipped from Taiwan in early May 2010  Commissioning delayed until early 2011 due to financing issues 33

  4. Project Updates • Certej Project  Developed by European Goldfields Limited  Location: Romania  Resource ~46.9Mt ore @ ~1.6 g/t Au & ~11.5 g/t Ag  Flotation + Albion Process + CIL flowsheet  Aker Solutions (UK) completed basic engineering  Design basis: 3Mtpa ore and 160k oz/y Au + 800k oz/y Ag  Project Life- 16 years  All permits now in place along with financing  Commissioning expected to start late 2011 / early 2012 34

  5. Project Updates • Other Projects/Applications Joanna Project- Mines Aurizons  Arsenopyrite refractory gold application (110k oz/y Au) o Pilot work commencing ( hrl testing) o Numerous testwork programs supporting process studies  Enargite Cu/Ag/Ag (projects in South America, SE Asia…) o Pyrite gold (projects in QLD, Armenia, Mexico, Kazakhstan…) o Arsenopyrite gold (projects in WA, New Zealand…) o Internally with Xstrata PLC projects in advanced state of testing and engineering  through to commercial application Copper/Cobalt applications – dust leaching plant o Nickel application o Zinc applications – smelter expansions o 35

  6. Project Development Program 36

  7. Project Development Program • Steps involved 1. Define and collect preliminary key projects and metallurgical data about the likely feed and range of feed material to be treated via the Albion Process 2. Undertake a high level economic assessment of the process (indicative order of magnitude costing exercise) 3. Phase 1 testing- Initiate an orientation testwork program to broadly demonstrate the technical feasibility of the process and generate key process design parameters to enable a preliminary process feasibility study to be completed 4. Commence a preliminary process study to establish the capital and operating costs for the process specific for project and target feed material 5. Phase 2 testing- Optimize process conditions and undertake testwork on variability samples 6. Phase 3 testing- Continuous pilot trial work 7. Commence bankable feasibility study (BFS) design and costing work leading into basic and detailed engineering and finally plant construction and commissioning 37

  8. Project Development Program • Steps involved- cost and duration Step No. Dscription Cost Duration Sample Responsible 1 Data collection 2-4 weeks Client/Core - 2 Highlevel OOM Capex/Opex - 2-4 weeks Core 3 Phase 1- testing ~A$30-40K 6-8 weeks 10-20 kg hrl testing 4 Process Study ~A$20K 4-6 weeks XT/Core 5 Phase 2- testing ~A$50-100K 8-12 weeks 20-50 kg hrl testing 6 Phase 3- testing ~A$500-750K 3-6 months >250 kg hrl testing/vendors 7 Feasibility study etc… ? ? Engineering Houses* * Suggested EPCM contractors with Albion Process experience: Lycopodium (Las Lagunas) and Aker Solutions (Certej) 38

  9. Project Development Program • Testwork- hrl testing (www.hrltesting.com) 39

  10. THANK YOU • Any questions? Duncan Turner PhD Mike Hourn Core Resources Pty Ltd Xstrata Technology General Manager Albion Process Manager Hydrometallurgy dturner@coreresources.com.au mhourn@xstratatech.com.au +61 7 3637 8105 +61 7 3833 8539 40

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend