Capital & Operating Costs Generic Case Study- SOx and - - PowerPoint PPT Presentation

capital operating costs
SMART_READER_LITE
LIVE PREVIEW

Capital & Operating Costs Generic Case Study- SOx and - - PowerPoint PPT Presentation

Capital & Operating Costs Generic Case Study- SOx and Sensitivity to Gold Price 400US$/oz 120 110 100 Relative NPV (US$M) 90 80 500 70 60 450 50 40 400 0 10 20 30 40 50 60 70 80 90 100 Sulphide Oxidation (%)


slide-1
SLIDE 1

Capital & Operating Costs

31

  • Generic Case Study- SOx and Sensitivity to Gold Price

50 100 150 200 250 300 350 400 450 500 10 20 30 40 50 60 70 80 90 100 Relative NPV (US$M) Sulphide Oxidation (%) 400US$/oz 600US$/oz 800US$/oz 1,000US$/oz

40 50 60 70 80 90 100 110 120 10 20 30 40 50 60 70 80 90 100 Relative NPV (US$M) Sulphide Oxidation (%)

400US$/oz

100 120 140 160 180 200 220 240 10 20 30 40 50 60 70 80 90 100 Re la tive NPV (US$M) Sulphide Oxidation (%)

600US$/oz

150 200 250 300 350 400 10 20 30 40 50 60 70 80 90 100 Relativ e N PV (US$M) Sulphide Oxidation (%)

800US$/oz

slide-2
SLIDE 2

32

Project Updates

slide-3
SLIDE 3

Project Updates

33

  • Las Lagunas Project
  • Developed by EnviroGold Limited
  • Location: Dominican Republic
  • JORC Resource 5.14Mt tailings @ 3.76 g/t Au

& 38.62 g/t Ag

  • Flotation + Albion Process + CIL flowsheet
  • Lycopodium Minerals QLD P/L (Brisbane)

completed detailed engineering

  • Design basis: 800ktpa tailings and 80k oz/y

Ag+Au

  • Project Life- 6.5 years
  • Construction by local contractor (IRISA) >40%

complete

  • Albion Process leach tanks (SS) to be shipped

from Taiwan in early May 2010

  • Commissioning delayed until early 2011 due to

financing issues

slide-4
SLIDE 4

Project Updates

34

  • Certej Project
  • Developed by European Goldfields Limited
  • Location: Romania
  • Resource ~46.9Mt ore @ ~1.6 g/t Au & ~11.5

g/t Ag

  • Flotation + Albion Process + CIL flowsheet
  • Aker Solutions (UK) completed basic

engineering

  • Design basis: 3Mtpa ore and 160k oz/y Au +

800k oz/y Ag

  • Project Life- 16 years
  • All permits now in place along with financing
  • Commissioning expected to start late 2011 /

early 2012

slide-5
SLIDE 5

Project Updates

35

  • Other Projects/Applications
  • Joanna Project- Mines Aurizons
  • Arsenopyrite refractory gold application (110k oz/y Au)
  • Pilot work commencing (hrltesting)
  • Numerous testwork programs supporting process studies
  • Enargite Cu/Ag/Ag (projects in South America, SE Asia…)
  • Pyrite gold (projects in QLD, Armenia, Mexico, Kazakhstan…)
  • Arsenopyrite gold (projects in WA, New Zealand…)
  • Internally with Xstrata PLC projects in advanced state of testing and engineering

through to commercial application

  • Copper/Cobalt applications – dust leaching plant
  • Nickel application
  • Zinc applications – smelter expansions
slide-6
SLIDE 6

36

Project Development Program

slide-7
SLIDE 7

Project Development Program

37

  • Steps involved

1. Define and collect preliminary key projects and metallurgical data about the likely feed and range of feed material to be treated via the Albion Process 2. Undertake a high level economic assessment of the process (indicative order of magnitude costing exercise) 3. Phase 1 testing- Initiate an orientation testwork program to broadly demonstrate the technical feasibility of the process

and generate key process design parameters to enable a preliminary process feasibility study to be completed

4. Commence a preliminary process study to establish the capital and operating costs for the process specific for project and target feed material 5. Phase 2 testing- Optimize process conditions and undertake testwork on variability samples 6. Phase 3 testing- Continuous pilot trial work 7. Commence bankable feasibility study (BFS) design and costing work leading into basic and detailed engineering and finally plant construction and commissioning

slide-8
SLIDE 8

Project Development Program

38

  • Steps involved- cost and duration

Step No. Dscription Cost Duration Sample Responsible 1 Data collection

  • 2-4 weeks

Client/Core 2 Highlevel OOM Capex/Opex

  • 2-4 weeks

Core 3 Phase 1- testing ~A$30-40K 6-8 weeks 10-20 kg hrltesting 4 Process Study ~A$20K 4-6 weeks XT/Core 5 Phase 2- testing ~A$50-100K 8-12 weeks 20-50 kg hrltesting 6 Phase 3- testing ~A$500-750K 3-6 months >250 kg hrltesting/vendors 7 Feasibility study etc… ? ? Engineering Houses* * Suggested EPCM contractors with Albion Process experience: Lycopodium (Las Lagunas) and Aker Solutions (Certej)

slide-9
SLIDE 9

Project Development Program

39

  • Testwork- hrltesting (www.hrltesting.com)
slide-10
SLIDE 10

THANK YOU

40

Duncan Turner PhD Core Resources Pty Ltd General Manager Albion Process dturner@coreresources.com.au +61 7 3637 8105 Mike Hourn Xstrata Technology Manager Hydrometallurgy mhourn@xstratatech.com.au +61 7 3833 8539

  • Any questions?