Project: Capital Improvement New classroom ventilation units that have air-conditioning capacity in addition to heat Project Upgrading existing electrical systems in all aging school buildings Proposed Bond Cost: $50 million.


slide-1
SLIDE 1

Project:

  • New classroom ventilation units that have

air-conditioning capacity in addition to heat

  • Upgrading existing electrical systems in all aging

school buildings Proposed Bond Cost:

  • $50 million. The school district will be eligible for

reimbursement from New York State on 45% of total construction costs. Projected tax impact estimate:

  • $11.95/month

This is a one-time increase on home assessed at average value as determined by County Assessor.

Capital Improvement Project

slide-2
SLIDE 2

Oceanside School District Proposed Bond

slide-3
SLIDE 3

Capital Project Details

  • Replacement of existing classroom unit ventilators with new unit-ventilators with air conditioning capacity in

addition to heat

  • Installation of new roof top heating and air conditioning units including steel dunnage, electrical work, gas piping

work and associated roofing work

  • Upgrade existing buildings’ electrical service to accommodate new equipment
  • Installation of split heating and ventilating units in small offices
  • Installation of sheet rock chases to conceal new piping
  • Ceiling reconstruction work
  • Casework reconstruction associated with the HVAC reconstruction work
  • Asbestos abatement associated with the HVAC reconstruction work
  • Automatic temperature controls associated with the new HVAC reconstruction work
slide-4
SLIDE 4

The district expects to receive approximately 45% of total construction costs reimbursed from New York State.

Reimbursed Expenses to Minimize Tax Impact

slide-5
SLIDE 5

Why now?

  • The electrical systems in all of our aging

buildings need upgrading.

  • The district’s current ventilation/air

circulation system does not allow for consistent temperatures in school buildings for optimal teaching and learning.

  • The medical needs of students and staff

are increasing.

  • This project will impact ALL students and

community members within the Oceanside schools.

slide-6
SLIDE 6

Why a bond?

  • The majority of the proposed project will

be eligible for state aid, with 45% of total construction costs reimbursed from New York State; reimbursements will offset budget expenses to minimize burden on taxpayers.

  • The cost of borrowing is currently low.
slide-7
SLIDE 7

Phasing & Timeline of Project

December 2019: BOE adopts a bond resolution Spring 2020: Architect completes and files plans with SED Fall 2020: Receipt of approval Late Fall/Early Winter 2020: Bid packages are distributed to contractors Winter 2021: Contracts awarded Spring 2021: Project construction commences

slide-8
SLIDE 8

Oceanside School District

Your vote matters! Tuesday, Nov. 12, 2019 7 am to 9 pm School #6 Merle Ave. Gym