SLIDE 1
CALTRANS I-8 CONCRETE OVERLAY
PILOT PROJECT
Mehdi Parvini California Department of Transportation
SLIDE 2
- Introduction
- Pilot Project
- Design Process
- Status Update
Outline
SLIDE 3
Concrete overlays are sustainable and cost effective strategies that extend pavement life and improve both functional and structural characteristics of the pavements.
Benefits of Concrete Overlays
SLIDE 4
Existing Process
SLIDE 5
Concrete Overlay Training
SLIDE 6
Pilot Project
SLIDE 7
Original Design
SLIDE 8
Design Request
SLIDE 9
Existing Pavement (As-Built)
SLIDE 10
Existing Pavement (Pavement Condition Survey)
SLIDE 11
Existing Pavement (Cores)
SLIDE 12
Existing Pavement (Field Visit on 4/17/2015)
SLIDE 13
Industry Partnership
SLIDE 14
Design Process (Traffic Data)
SLIDE 15
Pavement ME Design
SLIDE 16
Proposed Design Memo
SLIDE 17
Specifications & Plans
SLIDE 18 Using the winning bidders unit cost and the quantities for each project, there is approximately a
$270,000 per mile per lane savings when constructing the overlay versus
replacement.
Cost Saving Update
SLIDE 19
- Segment 4 (Overlay) – 56 lane-miles
- Segment 5 (Overlay) – 28 lane-miles
Construction began July 2017
Project Status
SLIDE 20
Construction
SLIDE 21
Construction (cont.)
SLIDE 22
Construction (cont.)
SLIDE 23
Construction (cont.)
SLIDE 24
Construction (cont.)
SLIDE 25 Future Plans
- Monitoring and Evaluation
- Policy Improvement (design, standards, guides)
- Construction Quality
– Training
SLIDE 26