Caltrain Advanced Signal System August / September 2011 Stakeholder Meetings Purpose Rail Corridor Need Enhanced Safety Growing Caltrain Operations Increase Capacity Increase Efficiency 3 Enhanced Safety 2008 Metrolink


slide-1
SLIDE 1

Caltrain Advanced Signal System

August / September 2011 Stakeholder Meetings

slide-2
SLIDE 2

Purpose

slide-3
SLIDE 3

Rail Corridor Need

  • Enhanced Safety
  • Growing Caltrain Operations

– Increase Capacity – Increase Efficiency

3

slide-4
SLIDE 4

Enhanced Safety

  • 2008 Metrolink Accident
  • Rail Safety Improvement Act 2008
  • FRA Unfunded Mandate
  • Install Positive Train Control (PTC)
  • End of 2015

4

slide-5
SLIDE 5

Growing Caltrain Operations

  • Growing transit market
  • Existing services

– Caltrain – ACE and Capital Corridor – Freight

  • New services planned

– HSR – Dumbarton

5

slide-6
SLIDE 6

Project Scope

slide-7
SLIDE 7

Advanced Signal System

  • CBOSS

– Communication based overlay signal system – Acronym (not a product)

  • System Purpose

– PTC Requirements – Caltrain Operating Needs

7

slide-8
SLIDE 8

PTC Requirements

  • Prevent collisions
  • Enforce speed limits
  • Protect work zones
  • Interoperability

8

slide-9
SLIDE 9

Caltrain Operating Needs

  • Improving Crossing Safety/

Performance

  • Efficient running of mixed traffic
  • Enforce Scheduled Station Stopping

9

slide-10
SLIDE 10

Technology Considerations

  • FRA interoperable requirement
  • Class I railroad standards

Caltrain Advanced Signal System I-ETMS (US Class I) Base Frequency Band PTC 220mhz required PTC 220mhz Customization Caltrain Needs Freight Needs

10

slide-11
SLIDE 11

Project Status

slide-12
SLIDE 12

Request for Proposal

  • Project Cost: Approximately $250M
  • Package

– Design – Materials and Equipment – Installation / Testing / Commissioning – FRA Safety Certifications – Training – Backup Center Control Faculty – Operations and Maintenance Support – Warranty

12

slide-13
SLIDE 13

Project Schedule

  • 2011 - 2013

– Award Contract – Design – Manufacturing

  • 2013 - 2014

– Installation – Testing

  • 2015

– Safety Certification – Revenue Service

13

slide-14
SLIDE 14

HSR Coordination

Critical Design (2012) Procurement Design (Date?) HSR & Caltrain FRA Grant Agreement Implementation (Post) 2015 HSR Interoperability Requirements Implementation (2013 - 2015) CALTRAIN Procurement

14

Final Design (2013)

slide-15
SLIDE 15

Discussion