Caltrain Advanced Signal System August / September 2011 Stakeholder - PowerPoint PPT Presentation

Caltrain Advanced Signal System August / September 2011 Stakeholder Meetings Purpose Rail Corridor Need Enhanced Safety Growing Caltrain Operations Increase Capacity Increase Efficiency 3 Enhanced Safety 2008 Metrolink


  1. Caltrain Advanced Signal System August / September 2011 Stakeholder Meetings

  2. Purpose

  3. Rail Corridor Need • Enhanced Safety • Growing Caltrain Operations – Increase Capacity – Increase Efficiency 3

  4. Enhanced Safety • 2008 Metrolink Accident • Rail Safety Improvement Act 2008 • FRA Unfunded Mandate • Install Positive Train Control (PTC) • End of 2015 4

  5. Growing Caltrain Operations • Growing transit market • Existing services – Caltrain – ACE and Capital Corridor – Freight • New services planned – HSR – Dumbarton 5

  6. Project Scope

  7. Advanced Signal System • CBOSS – Communication based overlay signal system – Acronym (not a product) • System Purpose – PTC Requirements – Caltrain Operating Needs 7

  8. PTC Requirements • Prevent collisions • Enforce speed limits • Protect work zones • Interoperability 8

  9. Caltrain Operating Needs • Improving Crossing Safety/ Performance • Efficient running of mixed traffic • Enforce Scheduled Station Stopping 9

  10. Technology Considerations • FRA interoperable requirement • Class I railroad standards Caltrain I-ETMS Advanced Signal (US Class I) System PTC PTC Base 220mhz 220mhz Frequency Band required Customization Caltrain Needs Freight Needs 10

  11. Project Status

  12. Request for Proposal • Project Cost: Approximately $250M • Package – Design – Materials and Equipment – Installation / Testing / Commissioning – FRA Safety Certifications – Training – Backup Center Control Faculty – Operations and Maintenance Support – Warranty 12

  13. Project Schedule • 2011 - 2013 – Award Contract – Design – Manufacturing • 2013 - 2014 – Installation – Testing • 2015 – Safety Certification – Revenue Service 13

  14. HSR Coordination CALTRAIN Procurement HSR HSR & Interoperability Critical Design Caltrain Requirements (2012) FRA Grant Agreement Final Design Procurement (2013) Design (Date?) Implementation (2013 - 2015) Implementation (Post) 2015 14

  15. Discussion Contact Information: Caltrain Modernization Program caltrainptc@samtrans.com www.caltrain.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.