MassDOT Highway Projects Briefing for the 495/MetroWest Partnership Transportation Committee Meeting Tuesday, September 26, 2017 Overview Projects in Planning/Design Construction Projects Resurfacing Projects Recently Completed


slide-1
SLIDE 1

MassDOT Highway Projects Briefing

for the

495/MetroWest Partnership Transportation Committee Meeting

Tuesday, September 26, 2017

slide-2
SLIDE 2
  • Projects in Planning/Design
  • Construction Projects
  • Resurfacing Projects
  • Recently Completed Projects

2 9/26/2017

Overview

slide-3
SLIDE 3

3 9/26/2017

I-495/Metrowest Projects

slide-4
SLIDE 4
  • The purpose of the project is to address

the geometric and operational deficiencies that result in safety issues and increased congestion at one of the busiest interchanges on the Massachusetts Turnpike.

  • The existing interchange will be

reconfigured to improve safety and to meet high volume interstate-to-interstate demands.

4 9/26/2017

I-90/495 Interchange Improvements

slide-5
SLIDE 5
  • The project is in the preliminary design stage and is

slated to be advertised in FY 2020 as a design-build

  • project. The current timeline has construction slated

from 2020-2023.

  • The project team is currently refining the conceptual

alternatives for evaluation and public comment as part of the environmental review stage of this project, in order to identify a preferred alternative.

  • After the environmental review phase is completed, the

preferred alternative will be advanced to the 25% design stage.

  • The project team has recently launched a project

website providing more details on the project and anticipates holding public information meetings in the near future.

  • https://www.massdot.state.ma.us/highway/HighlightedProjects/I-

495I-90InterchangeImprovements.aspx

5 9/26/2017

I-90/495 Interchange Improvements

slide-6
SLIDE 6

6 9/26/2017

I-90/495 Interchange Improvements

slide-7
SLIDE 7

Concept 22-3

9/26/2017

slide-8
SLIDE 8

Concept 14-4

slide-9
SLIDE 9

Concept 14-5

slide-10
SLIDE 10

Concept C2

slide-11
SLIDE 11
  • Ashland- Reconstruction on Route 126 (Pond Street), from the Framingham T.L. Holliston T.L.

($13 million) The project is at 25% design stage and listed on 2020 TIP.

  • Bellingham- Ramp Construction & Relocation, I-495 at Route 126, ( $13.5 million)

interchange improvement project is at the preliminary design stage. An Interchange Modification Report was submitted to FHWA for review.

  • Framingham, Natick- Cochituate Rail Trail, ($8 million) project is at the 25% design stage. It

is currently programmed in FY 2018 of the Boston TIP utilizing Statewide Congestion Mitigation Air Quality (CMAQ) funds.

  • Framingham- Pedestrian Hybrid Beacon at Route 9 and Maynard Road. ($1 million) The

project is at the 25% design stage and construction funding has yet to be identified.

  • Framingham- Reconstruction of Union Avenue, from Proctor Street to Main Street. ($10

million) The is programmed on the FY 2021 Boston TIP.

  • Holliston- Multi-Use Trail Construction on a section of the Upper Charles Rail (2 Miles of

Proposed 27 Miles - Phase I ($2.3 million) Construction funding has not been identified.

  • Hopkinton - Route 135 signal and intersection improvement. ($8 million) The project is a the

25% design phase and appears on the 2019 TIP.

  • Littleton- Ayer- Intersection Improvements on Route 2A at Willow Road and Bruce Street.

($2.4 million) Project is in the preliminary design phase and construction has not been identified

  • Littleton- Westford - Interstate Maintenance and Related Work on I-495 ($17 million)

Project is listed on the 2020 TIP.

11 9/26/2017

Project Development

slide-12
SLIDE 12
  • Hudson, Marlborough- Interchange Reconstruction at I-290 & 495, including Bridge
  • Replacements. ($123 million) The proposed interchange improvement project significant

changes to the ramping system and replacement of four bridges. Conceptual design

  • Marlborough -Reconstruction of Route 85 ($5.4 million) The project was programmed on the

TIP in FY 2017 and was advertised on 6/24/2017. The bid opening is set for 11/7/2017.

  • Marlborough- Resurfacing and Related Work on Route 20 $9.9 million the pre-25% design

stage and is programmed on the FY 2019 TIP with a Spring/Summer 2019 advertisement

  • Natick- Reconstruction of Route 27 (North Main Street), From North Avenue to the

Wayland Town Line. ($ 8 million)The project is currently at the 25% design stage is currently programmed in FY 2019 on the TIP.

  • Shrewsbury- Bridge Rehabilitation Boylston Street (Rte. 140) over I-290. ($18 million) is at the

25% design phase.

  • Southborough –Resurfacing and Related Work on Rte. 9, from the Framingham town line to

White Bagley Road. Total estimated project cost is $4.7 million and the project was recently advertised on 9/9/2017.

  • Southborough- Reconstruction of Main Street (Route 30), from Sears Road to Park Street 75%

design stage and is programmed on the FY 2018 TIP with a December 2017 advertisement date.

  • Stow- Gleasondale Bridge Replacement Project ($6.7 million) Project is listed on the 2020 TIP.
  • Sudbury-Intersection Improvements at Rte. 20 and Landham Rd. $1.7 million. The project is

progressing to the 75% design phase, and construction is currently unfunded.

12 9/26/2017

Project Development

slide-13
SLIDE 13
  • The D3 demolition contract was

awarded Skanska-McCourt with the bid price of $39.6 million.

  • Work included the removal of roadway,

abandoned toll collection structures and roadside infrastructure no longer needed following the implementation of the 1-90 All Electronic Tolling System at Interchange 9 (Sturbridge), 10 (Auburn), 10A (Millbury), 11 (Millbury), 11A (Hopkinton), 12 (Framingham) and 13 (Framingham/Natick). The roadway will be reconstructed to accommodate vehicles using the new roadway alignment.

  • The contract completion is November

30, 2017 and work is currently on schedule.

13 9/26/2017

I-90 Toll Demolition and Roadway Reconstruction

slide-14
SLIDE 14
  • Acton, Carlisle, Westford-Bruce Freeman Rail Trail Phase 2A

project ($9.9 million) April 2018 completion.

  • Acton, Maynard-Assabet River Rail Trail, ($6.7 million)

Spring/Summer 2018 completion.

  • Framingham- Bridge Betterment, F-07-045, I-90 over MDC
  • Reservoir. ($5.7 million) November 2018 completion.
  • Framingham- Bridge Replacement, F-07-015, Winter Street
  • ver MBTA, Amtrak & CSX Railroad ($6.6 million) Bridge is

scheduled to reopen in late 2017, with final project completion in 2018

  • Franklin, Wrentham, Plainville, Foxborough, Mansfield-

Interstate and Related Work on I-495 (NB & SB), ($6.7 million) Project completion. April 2018 completion.

  • Hudson- Bridge Replacement, H-25-003, State Route 85

(Washington Street) Over the Assabet River. ($4.5 million) Bridge is currently closed to traffic but scheduled to reopen in October 2017, with final project completion in 2018.

  • Marlborough-Northborough Interstate Maintenance and

Related Work on I-290 ($12.9 million) September 2018 completion.

  • Medway-Route 109 Reconstruction,($9.6 million) June 2019

completion

14 9/26/2017

Ongoing Construction Projects

Hudson, Washington Street Bridge

slide-15
SLIDE 15
  • Natick- Bridge Replacement, N-03-003, Marion Street over the MBTA Railroad
  • Northborough, Shrewsbury, Roadway and Ramp Reconstruction and Related Work at

the Intersection of Routes 9 and 20. ($2 million) Contract recently awarded, August 2018 completion.

  • Shrewsbury, Northborough, Westborough-Resurfacing and Related Work Rte. 9 ($12

million) March 2019 completion.

  • Shrewsbury- Boylston- Northborough- Interstate Maintenance & Related Work on I-

290 ($14 million) August 2019 completion.

  • Westborough- Intersection & Signal Improvements at Route 9 & Lyman Street. The ($7

million) July 2019 project completion.

  • Wayland-Route 27 at Route 30, ($1.9 million), Spring 2018 completion.
  • Westford- Route 110 & Tadmuck Road Intersection Improvements ($3.9

million) October 2018 completion.

15 9/26/2017

Ongoing Construction Projects

Westborough, Rte. 9 resurfacing

slide-16
SLIDE 16
  • Acton- Milling and paving on Route 2A (Great Road) from the

Littleton Town line to the Concord Town line.

  • Boxborough- Milling and paving Route 111 (Massachusetts Ave)

from the Harvard Town Line Easterly to a pavement joint near the driveway of 1233 Mass. Ave known as the Boxborough Green Plaza.

  • Littleton - Milling and paving on Route 110/2A from 495 ramp to the

Westford Town Line as well as Rte. 2A from the Littleton Town Center to the Acton Town line.

  • Hopedale- Milling and paving Route 140 from Mendon town line to

Milford town line.

  • Mendon- Milling and paving Route 140 from Bellingham town line to

the Hopedale town line.

  • Milford -Milling and paving Route 140 from Hopedale town line to

Route 16.

  • Wayland- Milling and paving Route 20 from Route 27 to the Weston

town line.

16 9/26/2017

2017 Resurfacing Projects

slide-17
SLIDE 17
  • Framingham- Framingham – Reconstruction of Route 126,

Concord Street ($6.6 million) Spring 2017

  • Franklin-Reconstruction on Rte. 140, Main St. and Emmons St.,

($5.2 million) July 2016 completion

  • Littleton-I-495 Bridges Replacement Project, ($30 million)

Summer 2016 completion

  • Natick/Wellesley-Route 9 & Oak Street Intersection

Reconstruction ($5.5 million) Summer 2016

  • Southborough / Westborough – Resurfacing of Route 9

between Breakneck Hill Road and Lyman ($7 million) Summer 2016

17 9/26/2017

Recently Completed Projects

slide-18
SLIDE 18

Barry J. Lorion District 3 Acting Highway Director

barry.lorion@state.ma.us

Adam Nabulsi District 3 Operations

adam.nabulsi@state.ma.us Massachusetts Department of Transportation District 3 403 Belmont Street Worcester, MA 01604 508-929-3830

18 9/26/2017