MillerCoors Golden Brewery
Path to a Culture of Sustainability
.
Energy Water Waste to Landfill
Julie Smith, PE, MS Plant Optimization Engineer Utilities/Technical Services
Brewery Path to a Culture of Sustainability . Energy Water Waste - - PowerPoint PPT Presentation
MillerCoors Golden Brewery Path to a Culture of Sustainability . Energy Water Waste to Landfill Julie Smith, PE, MS Plant Optimization Engineer Utilities/Technical Services Culture Elements for Success Leadership Green Teams
.
Julie Smith, PE, MS Plant Optimization Engineer Utilities/Technical Services
Water Projects Steam Projects Electrical Projects
Effort
Impact
Consumption, Cost, Carbon
Loss & Waste Analysis Process Packaging TS Logistics Focused Improvements Packaging Line “Zero Energy” Pilot Keg Line Air A Water Overflow Packaging Dry Lube Conditioning Cold Sanitization
Cost Improvements Fuel Cost and Mix Fixed Cost Elimination Energy Audit Initiatives & Projects Metering Strategy Electrical and Steam Meters Metering Plan
Cooling Tower VFD’s Heat Exchanger Condensate Return Plant Air System Projects Frick #5 Evaporative Condenser Lighting Projects
Golden Brewery Sustainability Wins - 2011
Project Savings mmBTU/ 1000 BBL Ammonia Compressor Opt 14.8 Cameron TA3000 Compressor 3.41 Shut Down Fan Coil Units WH 2.95 Fix Leaks in Steam and Cond Pipe 1.51 Building Automation Upgrades BOC 0.9 Cellar 8 HEx Replacement 0.81 Keg Air and Energy Savings 0.6 Cold Sanitization 0.53 Close Steam Supply Valve in Summer 0.47 Beer Loss Reduction 0.46
Corporate Scorecard
Monthly Indicator* Mthly Actual Mthly Stretch Target Mthly Budget Target Actual YTD 2012 YTD Stretch Goal YTD Budget
STPY % Change
People/ Process Tech MillerCoors
136 137 147 146 141 151 151
Milwaukee
120 131 133 132 138 140 145
Fort Worth
108 91 92 112 106 108 111 1.5%
Eden
124 159 171 139 151 162 164
Albany
128 134 147 130 132 144 140
Irwindale
125 120 129 122 119 128 129
Trenton
141 132 151 152 137 157 154
Golden
196 196 208 228 204 218 225 1.2%
Shenandoah
101 90 95 102 98 104 103
Monthly Indicator* Mthly Actual Mthly Stretch Target Mthly Budget Target Actual YTD 2012 YTD Stretch Goal YTD Budget
STPY % Change
People/ Process Tech MillerCoors
3.76 3.85 3.94 3.84 3.80 3.89 4.03
Milwaukee
4.37 3.94 4.01 4.15 3.92 3.99 4.66
Fort Worth
3.50 3.52 3.60 3.47 3.41 3.48 3.56
Eden
3.22 3.54 3.61 3.33 3.76 3.84 3.91
Albany
3.54 3.86 3.95 3.72 3.61 3.69 3.80
Irwindale
3.60 3.53 3.60 3.71 3.61 3.68 3.71
Trenton
3.32 3.27 3.42 3.60 3.40 3.55 3.66
Golden
4.15 4.61 4.76 4.53 4.50 4.65 4.67
NP
Shenandoah
4.22 4.06 4.12 3.94 3.83 3.89 4.04
High Usage Typical Usage Reduced Usage
August 2012 - DRAFT
Total Energy (MJ/hl)
FEWER
60- 80% Stretch Reduction
>80%
Water (hl/hl)
FEWER
Monthly Indicator Monthly/YTD/Budget KPI FEWER - People/ Process & Technology
*Monthly Indicator relative to 2009-2011 usage rates. Linear regression model factors include brewed, packed, weather, rainfall, electrical generation.
Above Upper Target
Nothing Planned - NP < 60%
Between Stretch &Upper Target
SIT Goals 2011 2012 2013 2014 2015 Water 4.07 3.83 3.60 3.38 3.18 Energy 154 143 136 128 120
“Committed to Active Responsibility for the Environment”
Earth Day Network
Share your pledge: http://act.earthday.org/
…bike to work eat local products get an energy audit switch to LED light bulbs eliminate pesticide use plant a garden/tree organize a neighborhood recycling event engage your parents or children recycle old electronics turn off lights, do laundry in cold water use rechargeable batteries take the stairs call your legislators use reusable shopping bags compost ….
What’s your DOT? Enter yours on the CARE SharePoint site. Look for the “Do One Thing” under Lists: