Board of Trustees Project Presentation

San Gorgonio Pass Campus – Phase I

January 21, 2010

slide-2
SLIDE 2

Current Project Participants

  • Mt. San Jacinto

Community College District City of Banning

Other participants in consideration include: County, cities, school districts and various business partners

slide-3
SLIDE 3

Project Development Team

 Ms. Becky Elam, VP, Business Services, MSJCCD  Mr. Duane Burk, Director Public Works, City of Banning  Dr. Mike Webster, Project Manager, MSJCCD  Mr. David Higginson, AIA,

Higginson+Cartozian Architects, Inc.

 Mr. Aaron Skeers, PE, Encompass Civil Engineers  Mr. Jim Corns, JCA Electrical Engineers  Mr. Shawn Burch, ASLA, STB Landscape Architects

slide-4
SLIDE 4

Project Site Description

 Located at the SE corner of Sunset Ave

and Westward Avenue

 Large Parcel acreage - 48.6 acres  Small Parcel acreage – 1.5 acres  Combined acreage – 50.1 acres  Phase I Campus to cover approximately

2.68 acres

slide-5
SLIDE 5

Aerial Map of Property

Large Parcel Small Parcel

slide-6
SLIDE 6

Site Design Approach

 Maintain good visual connection to campus from

adjacent streets for safety and security

 Site design takes into account future classroom

growth

 Parking for 118 Cars  Off site street improvements per City of Banning

requirements

 Fully landscaped with appropriate planting

material

 Site to be fully ADA accessible  Utilize existing utilities where possible

slide-7
SLIDE 7

Overall Site Concept Plan

slide-8
SLIDE 8

Conceptual Site Plan Phase I Campus

slide-9
SLIDE 9

Building Design Approach

 Utilize custom modular buildings  Total square footage – 6,720 sf  Designed to appear as permanent facilities  Flush to grade installation – no ramps  Exterior materials and surfaces to be low

maintenance

 Incorporate all IT/Data/Communication systems

per college standards

 Utilize energy efficient systems and sustainable

materials where practical

slide-10
SLIDE 10

Conceptual Floor Plan Administration Building

slide-11
SLIDE 11

Conceptual Floor Plan Typical Classroom

slide-12
SLIDE 12

Conceptual Floor Plan Toilet and Storage Building

slide-13
SLIDE 13

Estimated Time Line Administration Building

 Construction Documents – 2 Months  DSA Approval – 1 Months  Bidding and Award – 1 Month  Construction – 3 Months  Total – 7 Months  Completion - Fall 2010

slide-14
SLIDE 14

Estimated Time Line Classroom Portion

 Construction Documents – 3 Months  DSA Approval – 3 Months  Bidding and Award – 1 Month  Construction – 5 Months  Total – 12 Months  Completion – Spring 2011

slide-15
SLIDE 15

Preliminary Cost Estimate

Site Preparation, Development, Fees

 Site Preparation

$ 540,984

 Site Development Costs 590,115  GC and Contingency 237,530  Misc. Costs/Fees 382,500

Subtotal $1,751,129 City of Banning Contribution: - 750,000

slide-16
SLIDE 16

Preliminary Cost Estimate Structures, Furniture, Equipment

 Modular Bldgs/Furniture/Equipment

Option A Enhanced Modular $1,057,240 Option B Basic Modular 760,600 Option C Relocate Existing 529,480

slide-17
SLIDE 17

Preliminary Cost Estimate Phase I*

Option A Enhanced Modular $2,058,369 Option B Basic Modular 1,761,729 Option C Relocate Existing 1,530,609 *Net of City of Banning contribution of $750,000

slide-18
SLIDE 18

Questions?