BLAIR COVERED BRIDGE CAMPTON, NH Removal of Pavement Preparation - - PowerPoint PPT Presentation

blair covered bridge
SMART_READER_LITE
LIVE PREVIEW

BLAIR COVERED BRIDGE CAMPTON, NH Removal of Pavement Preparation - - PowerPoint PPT Presentation

BLAIR COVERED BRIDGE CAMPTON, NH Removal of Pavement Preparation for Concrete Siding Removal Siding and Flooring Removed Original Floor Joists Staging Sandbags Cofferdam New Concrete Poured Shoring truss being inserted Truss inserted


slide-1
SLIDE 1

BLAIR COVERED BRIDGE CAMPTON, NH

slide-2
SLIDE 2

Removal of Pavement

slide-3
SLIDE 3

Preparation for Concrete

slide-4
SLIDE 4

Siding Removal

slide-5
SLIDE 5

Siding and Flooring Removed

slide-6
SLIDE 6
slide-7
SLIDE 7

Original Floor Joists

slide-8
SLIDE 8

Staging

slide-9
SLIDE 9

Sandbags –Cofferdam – New Concrete Poured

slide-10
SLIDE 10

Shoring truss being inserted

slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Truss inserted – Jacking stations set -- Blair Bridge is suspended – Trusses are out of compression and can be examined and repaired

slide-14
SLIDE 14

Jacking stations at needle beams

slide-15
SLIDE 15

Typical conditions of the original bridge

slide-16
SLIDE 16

New arch leaves

slide-17
SLIDE 17

Only beam left from the original bridge that was destroyed by arson. Located at the center pier.

slide-18
SLIDE 18

Sawtooth Joinery

slide-19
SLIDE 19

Original sawtooth joinery done by Arnold M Graton from the 1980’s restoration

slide-20
SLIDE 20

Diagonal and vertical replacements

slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24

Repairs complete – truss removal

slide-25
SLIDE 25
slide-26
SLIDE 26

Preparing for the 30 day shutdown

slide-27
SLIDE 27

Never Ending Winter

slide-28
SLIDE 28

Pier – Ice Breaker

slide-29
SLIDE 29

{

slide-30
SLIDE 30

Repair Detail

slide-31
SLIDE 31

{

slide-32
SLIDE 32

{

slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35

{

slide-36
SLIDE 36

{

New floor joists

slide-37
SLIDE 37

{

slide-38
SLIDE 38

{

New oak flooring

slide-39
SLIDE 39

{

slide-40
SLIDE 40

{

New standing seam roof

slide-41
SLIDE 41

{

Wedge Counter Brace-Defining characteristic of Long Truss

slide-42
SLIDE 42

{

Pegged joinery in process

slide-43
SLIDE 43

{

Rebuild of the south east wing wall using traditional dry stack masonry

slide-44
SLIDE 44

{

slide-45
SLIDE 45

New siding

slide-46
SLIDE 46