BGRIM: Investor Presentation for Q22019 August 2019 Agenda 4 - - PowerPoint PPT Presentation

bgrim investor presentation for q2 2019
SMART_READER_LITE
LIVE PREVIEW

BGRIM: Investor Presentation for Q22019 August 2019 Agenda 4 - - PowerPoint PPT Presentation

BGRIM: Investor Presentation for Q22019 August 2019 Agenda 4 HIGHLIGHTS BGRIM UPDATE Q22019 OPERATING RESULTS Q 22019 BGRIM INVESTOR PRESENTATION Q32018 UPDATE Q32018 OPERATING RESULT BGRIM OVERVIEW 1 BGRIM: Q22019


slide-1
SLIDE 1

BGRIM: Investor Presentation for Q2’2019

August 2019

slide-2
SLIDE 2

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

1

Agenda

4

BGRIM UPDATE Q2’2019 OPERATING RESULTS HIGHLIGHTS

slide-3
SLIDE 3

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

2

BGRIM: Q2’2019 highlights

◼ Revenue Growth

  • Synchronized additional 10 MW

from Industrial users (IUs) in Rayong

  • Awarded The Green Financing
  • f the Year from The Asset

Triple A Asia Infrastructure Awards 2019

◼ Awards ◼ Profit Margin Enhancement

▪ Completed THB 2.2

billion debt refinancing of Solar projects to save interest of 2.0% p.a. or THB 119 million throughout the project life

▪ Significant efficiency improvement at

ABP3, thanks to LTSA with Siemens

◼ MW Growth

  • 3 COD projects during June 1-13,

adding installed capacity of 692 MW and contributing revenue of THB 191 million in Q2’19

slide-4
SLIDE 4

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

3

Achieved COD 3 projects on schedule and within budget

Nam Che 1 DT1&2 Phu Yen TTP

June 1 DT1 - June 3 DT2 - June 13 June 10

COD 2019

Capacity: Installed - 420 MW dc Contract - 350 MW ac Tariff: 9.35 Cent USD per kWh EVN PPA: 420 MW / 20 Years BGRIM Holding: 55.0% Capacity: Installed - 257 MW dc Contract - 214 MW ac Tariff: 9.35 Cent USD per kWh EVN PPA: 257 MW / 20 Years BGRIM Holding: 80.0% Capacity: Installed - 15 MW Tariff: 6.50 Cent USD per kWh EDL PPA: 15 MW / 25 Years BGRIM Holding: 72.0%

June 10

slide-5
SLIDE 5

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

4

Updated Vietnam Solar Projects Operation

2019 COD June July DT1&2 (420 MW) DT1 (180 MW) - June 3, 2019 DT2 (240 MW) - June 13, 2019 114,767,474 153,463,450 Phu Yen TTP (257 MW) June 10, 2019 68,659,479 87,768,327

Sales to EVN (THB) DT1&2 (Tay Ninh) Phu Yen TTP (Phu Yen)

Tuy Hoa Substation Quang Ngai city, Nha Trang city (The tourist destination of Vietnam) Tay Ninh Substation Ho Chi Minh city (The biggest demand of electricity in Vietnam) Binh Long Substation Binh Long Province Tay Ninh Province

(220 kV EVN transmission line) (220 kV EVN transmission line) (220 kV EVN transmission line)

slide-6
SLIDE 6

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

5

BGRIM: 2H’2019 outlook

◼ MW Growth ◼ Revenue Growth

Fully recognize revenue from all new projects with total capacity

  • f 816 MW added in 1H’19

Synchronize up to 11 MW from new IU customers in Rayong

  • Received the ESG 100

certificate for two consecutive years for excellent performance in sustainable development

◼ Awards ◼ Profit Margin Enhancement

Apply LTSA with Siemens to upgrade

  • ne

gas turbine

  • f

ABP5, to improve heat rate, shorten maintenance periods and add more MW

Scheduled COD of Interchem with 5 MW capacity at the end

  • f December
slide-7
SLIDE 7

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

6

Agenda

4

BGRIM UPDATE Q2’2019 OPERATING RESULTS HIGHLIGHTS

slide-8
SLIDE 8

BGRIM INVESTOR PRESENTATION Q2’2019 7

Well-Diversified Portfolio with Expert in Green-Field Developer

29.9% 28.7% 10.6% 10.1% 8.7% 5.8%6.2%

84.3% 13.6% 0.5% 1.6%

Total 975 MW

In Operation 842 MW*

Solar Group 822 MW Hydro Group 133 MW (98 MW Under Development) Wind Group 16 MW (Under Development) Bien Hoa 13 MW Diesel Gas Fired

Total 2,257 MW

In Operation 2,022 MW*

Amata City (Chonburi) 675 MW (Including ABP1&2 Replacement 140 MW each) Amata City (Rayong) 647 MW Bangkadi 229 MW Laem Chabang 196 MW

(Including BPLC1 Replacement 140 MW)

WHA Chonburi 1 130 MW BGPR1&2 240 MW (Under Development)

Type of Energy Installed MW Equity MW Total Capacity % In

  • peration

Total Capacity % In

  • peration

Gas fired 2,257 MW 69.5% 2,022 MW 1,587 MW 70.2% 1,202 MW Hydro 133 MW 4.1% 35 MW 95 MW 4.2% 25 MW Solar 822 MW 25.3% 822 MW 557 MW 24.7% 557 MW Wind 16 MW 0.5% 15 MW 0.7% IWTE 5 MW 0.1% 2 MW 0.1% Diesel 13 MW 0.4% 13 MW 4 MW 0.2% 4 MW Total 3,245 MW 100% 2,892 MW* 2,260 MW 100% 1,788 MW*

TRANSMISSION & DISTRIBUTION 0.4%

Waste to Energy (IWTE) 5 MW (Under Development)

RENEWABLE GROUP 30.1%

Poi Pet PPSEZ 14 MW**

SOLAR ROOFTOP

WHA (Map Ta Put) 140 MW (Including SPP1 Replacement) Solar rooftop for industrial users and commercial buildings with up to 100 MW

  • pportunity**

*Up to 280 MW

*As of July 2019

SPP – INDUSTRIAL ESTATE 69.5%

**Transmission & distribution and solar rooftop are not included in total installed capacity

slide-9
SLIDE 9

BGRIM INVESTOR PRESENTATION Q2’2019 8

Long-Life PPA and Benefit from Well-Establishment of PPA

2019 SALES AND SERVICE INCOME BY CUSTOMER WEIGHTED AVERAGE REMAINING PPA LIFE

EGAT

66%

IU-TH

24%

IU-VN

3%

Steam-TH

2%

EVN

1%

Others

3.4%

THB 21,123 mm

6M’2019 Sales and Service Income LONG-TERM PPA STRUCTURE

  • EGAT : 21 to 25 years tenor with take-or-pay structure
  • PEA : 25 years tenor (VSPP of solar, wind, waste to energy)
  • Industrial Users : up to 15-year tenor with track record of

extensions Secured Gas Supply with PTT covering respective PPA tenors Gas price pass-through at contracted heat rate under EGAT PPA

24.6 22.4 19.9 18.6 8.9

EDL PEA / MEA EVN EGAT Industrial users

  • electricity

(Thailand)

Track Record of Extensions

Years Years Years Years Years Note: Weighted Average Remaining PPA life is calculated as the average remaining contractual term remaining from 30 June 2019 to expiry weighted by the aggregate contracted capacity under the relevant agreement 15.0 Years

slide-10
SLIDE 10

BGRIM INVESTOR PRESENTATION Q2’2019

9

FOOTHOLD IN TOP INDUSTRIAL ESTATES WITH MULTIPLE OF GENERATING UNITS IN EACH LOCATION SELECTED TOP IU FOR ELECTRICITY AND STEAM

THAILAND CAMBODIA LAOS VIETNAM ▪ 1 power plant ▪ 130 MW ▪ 3 generating units ▪ 2 power plants ▪ 229 MW ▪ 6 generating units ▪ 2 power plants ▪ 240 MW ▪ 6 generating units ▪ 1 power plant ▪ 13 MW ▪ 5 power plants ▪ 647 MW ▪ 15 generating units ▪ 5 power plants ▪ 732 MW ▪ 17 generating units ▪ 2 power plants ▪ 159 MW ▪ 5 generating units

WHA Chonburi 1 Bangkadi BGPR1&2 Amata City Rayong

Amata City Bien Hoa Gas-fired cogeneration power plants Transmission and Distribution

Delivery of Reliability in Form of Electricity and Steam

▪ 2 power plants ▪ 124 MW ▪ 4 generating units

WHA Eastern (Map Ta Phut) Amata City Chonburi Laem Chabung Poi Pet PP SEZ

slide-11
SLIDE 11

10

Expanding Renewable Power Rapidly in the Region

THAILAND CAMBODIA LAOS VIETNAM

▪ 8 power plants ▪ 60 MW ▪ 1 power plant ▪ 8 MW

▪ 1 power plant ▪ 8 MW

BGYSP Solar WVO-Coop Nam Khao

▪ 5 power plants ▪ 67.5 MW

Hydro power plants BGPSK TPS Com. Solar power plants DT

▪ 1 power plant ▪ 420 MW

Phu Yen TTP

▪ 1 power plant ▪ 257 MW

Nam Che 1

▪ 1 power plant ▪ 15 MW

▪ 7 power plants ▪ 31 MW

Solarwa

▪ 5 power plants ▪ 39 MW ▪ 1 power plant ▪ 5 MW

Interchem XXHP

▪ 1 power plant ▪ 20 MW

Tadsakoi

▪ 1 power plant ▪ 30 MW ▪ 2 power plants ▪ 16 MW

Bo Thong

slide-12
SLIDE 12

BGRIM INVESTOR PRESENTATION Q2’2019 11

Robust Growth Pipeline with Promising on Execution

ACHIEVED COD IN TIME AND WITHIN BUDGET

Gas Solar IWTE Hydro Wind

2020

Plants

Solar WVO-Coop

(7 plants - 31 MW)

40

Plants

2,076 MW

Installed Capacity

1,217 MW

Equity Capacity

ABPR3, ABPR4 & ABPR 5

(3 plants - 399 MW)

52

3,193 MW

Installed Capacity

Tadsakoi

(30 MW)

2022 Plants

ABP1 Replacement

(140 MW)*

BPLC1 Replacement

(140 MW)*

ABP2 Replacement

(140 MW)*

Nam Khao 3

(15 MW)

3,152 MW

Installed Capacity

2,105 MW

Equity Capacity

Plants

BGPR1, BGPR2

(2 plants -240 MW)

2021

50

Plants 2021

SPP1 Extension

(2 plants -124 MW)

46

2019

Plants

1,850 MW

Equity Capacity DTE (1 plants - 420 MW) Interchem (5 MW) (166 MW)

2,896 MW

Installed Capacity Phu Yen TTP (1 plants - 257 MW) ABP1 Extension Nam Che (15 MW) SPP1 (2 plants - 124 MW)

53

2,222 MW

Equity Capacity

2023 Plants

3,200 MW

Installed Capacity

Nam Khao 5

(8 MW)

2,912 MW

Installed Capacity

1,865 MW

Equity Capacity

Bo Thong 1 & 2

(2 plants - 16 MW)

48

Plants

2,227 MW

Equity Capacity

3,215 MW

Installed Capacity

Nam Khao 4

(15 MW)

SPP1 Replacement

(2 plants -140 MW)**

3,245 MW

Installed Capacity

Nam Khao 2

(15 MW)

2,238 MW

Equity Capacity

Nam Khao 1

(15 MW)

2,260 MW

Equity Capacity

2024

54

Plants

56

2025 Plants 2018

*Up to 150 MW, **Up to 280 MW

***Based on our projections and may subject to change depending on project suitability

slide-13
SLIDE 13

BGRIM INVESTOR PRESENTATION Q2’2019 12

Diligently Invest in Suitable Opportunities via Strong Networks

May

Mutual Cooperation Meeting with KEPCO Strengthening the cooperation and implementation of energy storage system and smart grid technology 100 MW solar rooftop opportunities

1.8 MW COD achievement and 12 MW under construction which target COD in 2019.

June

Determine target KPI

THAILAND LAOS MALAYSIA

Gas Solar Hybrid Hydro Transmission and Distribution System (T&D) Wind

VIETNAM CAMBODIA KOREA PHILIPPINES

MOU signing with LG Chem Cooperation with LG Chem, world leader in fields of energy storage system (ESS), automotive batteries and mobile batteries, for the development in energy storage system.

slide-14
SLIDE 14

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

13

Energy Policy in Disruption Era with 4D 1E Digitalization Decarbonization Decentralization De-Regulation Electrification

MOU with LG Chem Smart Microgrid Private PPA with IUs Wind Projects Solar Projects Entering to develop sandbox IPS

slide-15
SLIDE 15

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

14

Agenda

4

BGRIM UPDATE Q2’2019 OPERATING RESULTS Q2’2019 HIGHLIGHTS

slide-16
SLIDE 16

BGRIM INVESTOR PRESENTATION Q2’2019

2,369 2,413 2,808 4,587 5,221 26.9% 23.5% 25.8% 27.0% 24.7%

23.0% 24.0% 25.0% 26.0% 27.0% 28.0%

1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

Q2'18 Q1'19 Q2'19 6M'18 6M'19 97% 97% 96% 96% 97%

1% 2% 2% 2% 2% 2% 1% 2% 2% 1%

8,805 10,257 10,866 16,961 21,123 Q2'18 Q1'19 Q2'19 6M'18 6M'19

15

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

Top Line and EBITDA Grew Strongly

Revenue grew strongly:

  • The y-on-y growths of total revenues were 23.4% for Q2’2019 and

24.5% for 6M’2019 and primarily due to

  • The COD of 12 projects with total capacity of 989 MW during

Q2’2018-Q2’2019, consisting of ABPR 4-5, 7 solar projects in Thailand, one hydropower plant in Laos and 2 solar projects in Vietnam.

  • Two acquisitions: 51% additional holding of BGYSP in July

2018 and SPP1 acquisition with 124 MW in March 2019, and

  • rising tariff of electricity and steam.

EBITDA increased continually:

  • The y-on-y EBITDA growths were 18.5% for Q2’2019 and 13.8% for

6M’2019 mainly from portfolio expansion through COD and acquisitions as mentioned.

EBITDA margin improved q-on-q in Q2’19:

  • EBITDA margin increased q-on-q to 25.8% in Q2’2019 from 1) a 2.4%

q-on-q declining gas cost while Ft-charge was stable, 2) no scheduled maintenance and 3) contributions from Solar projects in Vietnam which give relatively higher EBITDA margin.

  • .. although it softened y-o-y to 24.7% in 6M’2019 and 25.8% in Q2’2019

from an 13.8% increase in gas cost while there was a lag time in Ft charge adjustment.

Electricity Others Steam

(Unit: THB mn) (Unit: THB mn)

EBITDA Margin

EBITDA AND EBITDA MARGIN TOTAL REVENUES

+2,061 / 23.4% YoY +609 / 5.9% QoQ +4,162/ 24.5% YoY +634 / +13.8% YoY EBITDA +395 / 16.4% QoQ +439 / 18.5% YoY

slide-17
SLIDE 17

BGRIM INVESTOR PRESENTATION Q2’2019 16

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

796 792 175 229 349 338 189 199 6M/18 6M/19 6M/18 6M/19 6M/18 6M/19 6M/18 6M/19

2.88 3.24 3.27 3.30

6M/18 6M/19 6M/18 6M/19 EGAT Industrial Users (TH)

(Unit:THB/KWh)

3,644 1,506 4,326 1,558 6M/18 6M/19 6M/18 6M/19 EGAT Industrial Users (TH)

(Unit: GWh) (Unit: GWh)

KEY DRIVERS: ELECTRICITY AND NATURAL GAS VOLUME AND PRICE 6 MONTHS YoY

ELECTRICITY SALES VOLUME YoY ELECTRICITY SELLING PRICE YoY SALES VOLUME FOR EACH INDUSTRIAL USER (TH) FOR 6 MONTHS YoY

(Unit:THB/mmBTU)

Electricity Sales Volume Increased YoY for Both EGAT and IU (6M/2018 vs 6M/2019)

244.28

6M/18 6M/19

EFFECTIVE GAS COST

277.98

EGAT

  • EGAT sales volume increased 18.7% YoY primarily due to the inclusion of

ABPR4 and ABPR5 which commenced commercial operation in June and October 2018 respectively, and additional contributions from SPP1 acquisition in March 2019.

  • Electricity price sales to EGAT increased 10.2% YoY because the energy

payment is generally adjusted to reflect changes in natural gas price which rose during these periods.

IU Thailand

  • IU Thailand sales volume increased 3.5% YoY primarily due to
  • The inclusion of new industrial users in Amata City Rayong Industrial

Estate especially from new operation plants in 2018.

  • The inclusion of SPP1’s industrial users in WHA Eastern (Map Ta Phut).
  • An increase in demand load from existing customers in WHA Chonburi

Industrial Estate and Bangkadi Industrial Park.

  • Electricity price sales to industry users in Thailand increased 0.9% YoY

which is in line with the changes in Ft charge announced by the ERC.

Top Line and EBITDA Grew Strongly

Amata City Amata City Laem Chabang Others (Bangkadi, Chonburi Rayong WHA Chonburi, Map Ta Phut)

slide-18
SLIDE 18

BGRIM INVESTOR PRESENTATION Q2’2019

EGAT

  • EGAT sales volume increased 3.6% QoQ primarily due to fully contributions

from SPP1 acquisition in March 2019.

  • Electricity price sales to EGAT increased by 0.3% because the energy

payment is generally adjusted to reflect changes in natural gas price which rose in Q1’2019.

IU Thailand

  • IU Thailand sales volume increased 1.0% QoQ primarily due to
  • The inclusion of new industrial users in Amata City Rayong Industrial

Estate especially from new operation plants in 2018.

  • An increase in demand load from existing customers in Bangkadi

Industrial Park.

  • Electricity price sales to industry users Thailand remain unchanged which

is in line with the changes in Ft charge announced by the ERC. 2,127 775 2,199 783 Q1/19 Q2/19 Q1/19 Q2/19 EGAT Industrial Users (TH)

(Unit: GWh) (Unit: GWh)

17

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

Top Line and EBITDA Grew Strongly

3.25 3.24 3.30 3.30

Q1/19 Q2/19 Q1/19 Q2/19 EGAT Industrial Users (TH)

(Unit:THB/KWh)

ELECTRICITY SELLING PRICE QoQ

(Unit:THB/mmBTU)

0.0%

SALES VOLUME FOR EACH INDUSTRIAL USER (TH) QoQ ELECTRICITY SALES VOLUME QoQ

KEY DRIVERS: ELECTRICITY AND NATURAL GAS VOLUME AND PRICE QoQ

Electricity Sales Volume Increased QoQ for Both EGAT and IU (Q1/2019 vs Q2/2019)

Q1/19 Q2/19

EFFECTIVE GAS COST

281.42 274.66

395 397 106 123 172 166 101 98 Q1/19 Q2/19 Q1/19 Q2/19 Q1/19 Q2/19 Q1/19 Q2/19 Amata City Amata City Laem Chabang Others (Bangkadi, Chonburi Rayong WHA Chonburi, Map Ta Phut)

slide-19
SLIDE 19

BGRIM INVESTOR PRESENTATION Q2’2019

Ft (Fuel Adjustment Charge) is a component of electricity tariff announced by Energy Regulatory Commission (ERC) every 4 months to reflect overall

cost of fuel that EGAT uses to generate electricity which includes a portion that EGAT purchases from private sector and import from neighboring countries ➢ In general, natural gas is contributed for 70% of total fuel used to produce electricity in Thailand. Thus, change in gas price has high correlation with change in Ft over the past 10 years. ➢ In addition, the gap between these two indexes is widen since 2011 – the year that renewable business was start commencement in Thailand BGRIM’s Electricity price sold to IU is normally benchmark with Ft which would, in the long run, be moved in the same direction with change in gas price

18

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

High Correlation between Gas Price and Ft – Benefit to IU Sales

Change in Ft vs Gas Price in 2005-2019

Introduction of renewable energy

Adjusted FT Index Gas Price Index 0% 50% 100% 150% 200% 250% 300% Jan-05 Jul-05 Jan-06 Jul-06 Jan-07 Jul-07 Jan-08 Jul-08 Jan-09 Jul-09 Jan-10 Jul-10 Jan-11 Jul-11 Jan-12 Jul-12 Jan-13 Jul-13 Jan-14 Jul-14 Jan-15 Jul-15 Jan-16 Jul-16 Jan-17 Jul-17 Jan-18 Jul-18 Jan-19 Jul-19 Adjusted FT Index Gas price Index

slide-20
SLIDE 20

BGRIM INVESTOR PRESENTATION Q2’2019

8,389 7,599 7,551 8,437 7,588 7,550

1st Round SPP 2nd Round SPP 3rd Round SPP

2018 6M'2019

19

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

High Standard Technology Leads to High Efficiency & Availability

95.2 96.4 98.6 96.4 95.9 99.6

70 75 80 85 90 95 100

1st Round SPP 2nd Round SPP 3rd Round SPP

2018 6M'2019

Our SPP power plants realized lower heat rates Most of our gas-fired cogeneration power plants have availability factors of above 90% since COD

HIGH AVAILABILTY (AVAILABILTY FACTOR)

Note: (a) Electricity equivalent generations of steam dispatched are calculated according to efficiency calculation of EGAT PPA (SPP generation 1) 1st Round SPP consist of ABP1, ABP2, BPLC1 BPLC2 and SPP1 2nd Round SPP consist of ABP3, ABP4, ABPR1, ABPR2 BIP1 and BIP2 3rd Round SPP consist of ABP5, ABPR3, ABPR4 ABPR5 and BPWHA

(%)

HIGH EFFICIENCY (HEAT RATE)

Contracted Heat Rate 8,600 BTU/kWh Contracted Heat Rate 8,000 BTU/kWh Contracted Heat Rate 7,950 BTU/kWh

(BTU/kWh)

slide-21
SLIDE 21

BGRIM INVESTOR PRESENTATION Q2’2019

1,075 1,040

700

6M'18 6M'19

563 443 557

100 200 300 400 500 600 700

Q2'18 Q1'19 Q2'19

20

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

NP for Q2’2019 increased 228.8%

938 1,158 581 716

1,519 1,874

500 1000 1500 2000 2500

6M'18 6M'19 9.0% 8.9%

215 532 626 101 303 412

316 835 1,038

200 400 600 800 1000 1200

Q2'18 Q1'19 Q2'19

PROJECT UPDATE

3.6% 8.1% 9.6% NP Margin NP to owner NP to Non-Controlling Interest (NCI)

NP / NP to owner grew 228.5% y-o-y to Baht 1,038 million in Q2’2019 / 23.4% to Baht 1,874 million in 6M’2019

  • The improvements were from
  • new COD of 2 solar projects in Vietnam and Nam Che1,
  • new client synchronizing in Rayong,
  • full contribution from SPP1,
  • Improving heat rate at ABP3 (thanks to LTSA with Siemens) and
  • 2.4% decline in gas cost while Ft charge was stable.

+722 / 228.5% YoY

NET PROFIT (NP)

(Unit: THB mn) (Unit: THB mn)

+203 / 24.3% QoQ

(Unit: THB mn)

1,038 886 557 245 92 329

Unrealized Fx Gain Non-recurring expense NNP NNP to NCI NNP to Owner Q2’19 Net Profit

RECONCILE NORMALIZED NET PROFIT (NNP) OF Q2’2019

+355 / 23.4% YoY

Portfolio expansion and cost saving could more than offset gas price increasing y-on-y

  • If one-time items were excluded (which were 1. THB 125 million

realized FX gain from BIP refinance in Q2’2018 and 2. THB 40 million temporary impact from EGAT’s transmission line modification which would be compensated in 2H’2019), NNP could grow 6% y-on-y in Q2’2019 which was because of portfolio expansion and cost saving. This was more than

  • ffset

by the THB 105 million earnings contribution project COD, MD&A and cost saving.

(1) (2)

668 597 1,200

(1) (2)

1,040

(1) Realized Fx Gain from BIP refinance (2) EGAT transmission line modification 125

40

125

40

slide-22
SLIDE 22

BGRIM INVESTOR PRESENTATION Q2’2019 21

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

Strong Financial Position Thanks to the Well-Managed Capital Structure

72% 75% 28% 25% 31 Dec 18 30 Jun 19 15% 14% 9% 8% 76% 78% 31 Dec 18 30 Jun 19

100,636 113,801

Cash, cash Equivalents and ST investments Other Current Assets

(Unit: THB mn)

Assets

Total Liabilities Total Equity

113,801 100,636

Liabilities and Equity

Non- Current Assets

Financial Position as at 30 Jun 2019 Total assets

  • Total assets increased by 13.1%, primarily due to the

continual expansion

  • f

project portfolio both local and

  • verseas.

Total liabilities

  • Total liabilities increased by 16.9%, primarily due to an

increase in short-term borrowing for project acquisition, construction payable for project under construction and additional loan drawdown for the projects under development and construction.

Total Equities

  • Total equities increased by 3.0%, primarily due to the

increase in retained earnings during the period.

STATEMENT OF FINANCIAL POSITION AS OF 30 JUN 2019

slide-23
SLIDE 23

BGRIM INVESTOR PRESENTATION Q2’2019 22

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

BGRIM optimizes Capital Structure through Well Managed Debt Profile

THB 60,053 mn

(as of 30 June 2019) Project Level (In Operation) Loan (THB)

  • Only 29% loan represents loan at the corporate level. The remaining 71%

contributes to debts at power plant level with limited recourse to sponsor

  • Interest obligations of almost all power plant level debts are swapped to

fixed rate

  • Only 15% of total loan as at 30 June 2019 is denominated in USD which is

matched with a proportion of EGAT tariff indexation to USD at project level, so called “Natural Hedge” strategy

THB 15,507 mn THB 9,018 mn Project Level Debenture THB 3,037 mn Corporate Level Loan THB 14,614 mn Corporate Level Debenture

24%

THB 17,877 mn Project Level (In Operation) Loan (USD)

5% 30% 26% 15% DEBT PROFILE

4.9% 4.7% 4.6% 4.5%

0.04 0.04 0.04 0.05 0.05 0.05 0.05 0.05 0.05

2016 2017 2018 Q2/2019

  • Financing costs decreased to 4.5% in Q2/2019 due to:
  • Project bond refinance of BIP1 and BIP2 THB 6.7 billion in May 2018
  • Corporate bond issuance of THB 9.7 billion in October 2018 and

green bond of THB 5.0 billion in December 2018

  • Solar projects refinance of BGSENA THB 2.2 billion in May 2019

with tenors of 14 years and interest saving rate around 2.0% p.a.

  • r THB 119 mn throughout the project life

FINANCING COSTS

slide-24
SLIDE 24

BGRIM INVESTOR PRESENTATION Q2’2019

Gearing Ratios

  • Consolidated

net interest-bearing debt to equity ratio increased to 1.6x, and for the Company only decreased to 0.9x as a result of additional investments in new projects to support the company’s earnings growths in both short term and long term.

23

PROJECT UPDATE BGRIM FINANCIAL PERFORMANCE

Capital Structure and Dividend Policy

  • Manage debt and equity funding to optimize capital structure
  • Seek to obtain financing at project level
  • Limited-recourse project loan with back-end equity
  • Target 3.0x debt to equity project financing at outset,

delivering over project life

  • Consolidated debt included loans at power plant because

BGRIM holds majority in most of the projects

Note: Net Interest-bearing debt is Interest-bearing debt less cash, cash equivalents and short-term investments.

60%

40% NNP to Owner 1H'2019

NET INTEREST-BEARING DEBT TO EQUITY RATIO

  • Minimum 40% of normalized net profit of consolidated financial

statements

Interim dividend of 0.15 THB per share was approved by BOD on 13 August 2019 with the scheduled payment on 10 September 2019

40% of NNP in 1H’19 will be paid as dividend with the total amount of THB 391 mn

1,842

(Unit: THB mm)

DIVIDEND PAYMENT

DIVIDEND POLICY CAPITAL STRUCTURE

0.7x 0.9x 1.5x 1.6x

(1.50) (1.40) (1.30) (1.20) (1.10) (1.00) (0.90) (0.80) (0.70) (0.60) (0.50) (0.40) (0.30) (0.20) (0.10)
  • 0.10
0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30 2.40 2.50

Dec-18 Jun-19

Company only Consolidated

slide-25
SLIDE 25

BGRIM INVESTOR PRESENTATION

Q2’2018 OPERATING RESULT Q3’2018 UPDATE BGRIM OVERVIEW

Q1’2019

Q3’2018 UPDATE Q3’2018 OPERATING RESULTS BGRIM OVERVIEW Q3’2018 OPERATING RESULTS BGRIM OVERVIEW

24

Appendix

24

slide-26
SLIDE 26

BGRIM INVESTOR PRESENTATION Q2’2019 25

140th Year Anniversary of B.Grimm

  • Longest established infrastructure, industrial, and healthcare group in Thailand since 1878
  • Concessionaire and contractor of the largest infrastructure system in Thailand and South East Asia of the 1890s:

Rangsit irrigation canals

  • Introducing leading engineering technologies into Thailand since the 1880s until today with Krupp, Siemens, Carl Zeiss,

Merck, Voith and United Technologies

Values: Positivity, Pioneering Spirit, Professionalism, and Partnership

"Doing Business with Compassion for the Development

  • f Civilization in Harmony with Nature"

Opened Siam Dispensary

1890 1931 1996 2010

Built Rangsit canal together with Snidvongse family Installed the first telephone line between Germany and Thailand Supplied turnkey systems and services with Siemens for BTS sky train Awarded first Small Power Producer (SPP) contract for Amata B.Grimm Power 1 Consortium leader for Airport Rail Link

1878

B.Grimm Power reached 2,892 MW installed capacity

1994 June 2019

slide-27
SLIDE 27

BGRIM INVESTOR PRESENTATION

Q2’2018 OPERATING RESULT Q3’2018 UPDATE BGRIM OVERVIEW

Q1’2019

Q3’2018 UPDATE Q3’2018 OPERATING RESULTS BGRIM OVERVIEW Q3’2018 OPERATING RESULTS BGRIM OVERVIEW

26 26

BGRIM Corporate Structure – Long Commitment from Management

B.Grimm Power’s Team

  • Mr. Harald Link

Chairman (23 years with B.Grimm Power) Major Shareholder

  • Ms. Preeyanart Soontornwata

President (23 years with B.Grimm Power) Chairperson of The Association of Private Power Producers, Thailand

  • Mr. Surasak Towanich

Senior Executive Vice President Sales, Marketing and Electricity Transmission and Distribution (23 years with B.Grimm Power) Previously held positions with EGAT and ABB

  • Mr. Nopadej Karnasuta

Senior Executive Vice President CFO (6 years with B.Grimm Power) Previously held positions with KBANK and EGCO

  • Mr. Peradach Patanachan

Senior Executive Vice President Legal Counsellor / Business &

Project Development I (Renewable & Hybrid Projects)

(12 years with B.Grimm Power) Previously held positions with Clifford Chance and KPMG

  • Mr. Chote Chusuwan

Senior Executive Vice President Chief Operation Officer (23 years with B.Grimm Power) Previously held positions with EGAT and Cogeneration PCL

  • Mr. Arunphun Pootong

Executive Vice President Business & Project Developments (Conventional) and Commercial & Procurement

Previously held positions with EGAT and JERA Power

slide-28
SLIDE 28

BGRIM INVESTOR PRESENTATION Q2’2019 27

Awards and Recognition

SET50

SET100

SETCLMV

FTSE SET Mid Cap

EIA Monitoring Awards 2016 Certificate of the Carbon Footprint for Organization (CFO) Best Energy Solutions Provider ASIA Project of the Year 2015: Best Distributed Generation Project The Most Innovative Bond Deal The First Non- financial Corporate Green Bond from Thailand Certificate

  • f membership
  • f GEIDCO*

Green Financing

  • f The Year

*Global Energy Interconnection Development and Cooperation Organization

slide-29
SLIDE 29

BGRIM INVESTOR PRESENTATION Q2’2019 28

“Excellent”

“ESG 100”

(by Thaipat Institute)

“Thai CAC”

(by Thai Institute of Directors Association (IOD))

“Thailand Sustainability Investment (THSI) List”

(by Stock Exchange of Thailand)

“AGM Level”

(by Thai Investors Association)

“CGR Score”

(by Thai Institute of Directors Association (IOD))

“Sustainability Report Awards”

(by Stock Exchange of Thailand)

Awards and Recognition

slide-30
SLIDE 30

BGRIM INVESTOR PRESENTATION Q2’2019 29

Q3’2018 UPDATE Q3’2018 UPDATE

*For PPAs expired in 2019 - 2021

Key consideration

EGAT PPA period (years) EGAT contract capacity (MW) EGAT Tariff IU Tariff Contracted heat rate (mmBTU/KWh) BGRIM’s power plants applied with this scheme

Replacement

25 Up to 30 Capacity Payment + Energy Payment Benchmark with PEA 7,409 ABP1, ABP2, BPLC1, SPP1 (2 plants)

Extension*

1-3 Up to 60 Energy Payment Benchmark with PEA 8,282 ABP1, SPP1 (2 plants)

Existing

21-25 Up to 90 Capacity Payment + Energy Payment Benchmark with PEA 8,600 ABP1, ABP2, BPLC1, SPP1 (2 plants)

SPP Extension and Replacement Scheme

ABP1 2019 2020 2021 2022 2023 2024 ABP2 BPLC1 SPP1 #1 SPP1 #2

166 MW, (15.3% holding) 166 MW, (51.2% holding) 140-150 MW, (51.2% holding), 25 years 140-150 MW, (51.2% holding), 25 years 140-150 MW, (100.0% holding), 25 years 171 MW, (15.3% holding) 103 MW, (100.0% holding) 62 MW, (100.0% holding) 62 MW, (100.0% holding) 62 MW, (100.0%) 62 MW, (100.0%) 70-140 MW, (100.0% holding), 25 years 70-140 MW, (100.0% holding), 25 years

slide-31
SLIDE 31

Q2’2019 BGRIM INVESTOR PRESENTATION

Q3’2018 OPERATING RESULT BGRIM OVERVIEW Q3’2018 UPDATE

30

BGRIM OVERVIEW Q3’2018 UPDATE

MOU signing with LG Chem (May 14, 2019)

Cooperation with LG Chem, world leader in fields of energy storage system (ESS), automotive batteries and mobile batteries, for the development in energy storage system.

MOU signing with Siemens and TPSC (Mar 23, 2019)

Service Collaborations to improve 9 power plants performance for increasing the availability and efficiency as well as introducing digitalization to their operation and maintenance.

MOU Signing with Strong Partners

slide-32
SLIDE 32

BGRIM INVESTOR PRESENTATION 31

Core subsidiaries and associates only

Corporate Structure

60.0%

slide-33
SLIDE 33

BGRIM INVESTOR PRESENTATION 32

BGRIM’s Shareholders

34.0% 24.4% 9.0% 1.1% 0.4% 31.1% B.Grimm Power (Singapore) PTE. LTD.

  • Mr. Harald Link

B.Grimm Joint Venture Holding

  • Ms. Caroline Link

Public Shareholders

Top Public Shareholders (as of 28 Jun 19) %

  • 1. ASIAN DEVELOPMENT BANK

4.7%

  • 2. BBL Long-Term Equity Fund

1.7%

  • 3. Thai Life Insurance Co., Ltd

1.1%

  • 4. Muang Thai Life Assurance Co., Ltd

1.0%

  • 5. SOUTH EAST ASIA UK (Type C) NOMINEES

LIMITED 0.8%

  • 6. Others

21.8% Total 31.1%

PUBLIC SHAREHOLDERS 2,606.9 MM SHARES

Directors and Management

slide-34
SLIDE 34

BGRIM INVESTOR PRESENTATION 33

Operational Power Plants: Conventional

Note: (a) Based on B.Grimm Power’s direct and/or indirect interest in the project company owning the power plant (b) Amata B.Grimm Power owned 30.0% of ABPIF’s units and consequently, our economic ownership of Amata B.Grimm Power 1 Limited and Amata B.Grimm Power 2 Limited was 15.3% (c) NEPC is currently in the process of establishing policies relating to the extension of SPP PPAs that will expire between 2019 – 2025 (include ABP1, ABP2 and BPLC1) for 10 years with up to the existing contracted capacity. (d) Acquired from Sime Darby Energy on 30 June 2014 (e) We instead purchase power directly from a subsidiary of EVN which we then on-sell to industrial users in Amata City Bien Hoa Estate

Company Abbreviation Fuel Type COD Economic Ownership %(a) Installed Equity Offtaker / PPA Expiry Contracted Capacity (MW) Electricity Contracted Capacity (MW) Steam Contracted Capacity (MW) (MW) Program (t/h) Amata Nakorn Industrial Estate, Thailand Amata B.Grimm Power 1 ABP1 Gas-Fired Cogen Sep-98 15.3%(b) 166.4 25.5 EGAT (SPP) Sep-19(c) 90 106.2 6 Amata B.Grimm Power 2 ABP2 Gas-Fired Cogen Sep-01 15.3%(b) 171.2 26.2 EGAT (SPP) Sep-22(c) 90 82.2 16 Amata B.Grimm Power 3 ABP3 Gas-Fired Cogen Oct-12 60.70% 132.5 80.4 EGAT (SPP) Oct-37 90 46.1 13 Amata B.Grimm Power 4 ABP4 Gas-Fired Cogen Nov-15 55.50% 131.1 72.8 EGAT (SPP) Nov-40 90 32.5 – Amata B.Grimm Power 5 ABP5 Gas-Fired Cogen Jun-16 55.50% 131.1 72.8 EGAT (SPP) Jun-41 90 33.4 13 Subtotal 732.3 277.7 450 300.4 48 Amata City Industrial Estate, Thailand Amata B.Grimm Power (Rayong) 1 ABPR1 Gas-Fired Cogen Nov-13 61.70% 123.3 76.1 EGAT (SPP) Nov-38 90 17 14 Amata B.Grimm Power (Rayong) 2 ABPR2 Gas-Fired Cogen Jun-13 61.70% 124.4 76.8 EGAT (SPP) Jun-38 90 24 14 Amata B.Grimm Power (Rayong) 3 ABPR3 Gas-Fired Cogen Feb-18 55.50% 133 73.8 EGAT (SPP) Feb-43 90 18

  • Amata B.Grimm Power (Rayong) 4

ABPR4 Gas-Fired Cogen Jun-18 55.50% 133 73.8 EGAT (SPP) Jun-43 90 16

  • Amata B.Grimm Power (Rayong) 5

ABPR5 Gas-Fired Cogen Oct-18 55.50% 133 73.8 EGAT (SPP) Oct-43 90 14

  • Subtotal

646.7 374.3 450 89 28 Laem Chabang Industrial Estate, Thailand B.Grimm Power (Laem Chabang) 1 BPLC1 Gas-Fired Cogen Jul-01(d) 100.00% 103 103 EGAT (SPP) Jul-22(c) 60 50.1 46.2 B.Grimm Power (Laem Chabang) 2 BPLC2 Gas-Fired Cogen Feb-09(d) 100.00% 56.1 56.1 – – – 60.8 18.5 Subtotal 159.1 159.1 60 110.9 64.7 Bangkadi Industrial Park, Thailand B.Grimm BIP Power 1 BIP1 Gas-Fired Cogen Apr-15 74.00% 114.6 84.8 EGAT (SPP) Apr-40 90 14 – B.Grimm BIP Power 2 BIP2 Gas-Fired Cogen Jan-16 74.00% 114.6 84.8 EGAT (SPP) Jan-41 90 18.5 – Subtotal 229.2 169.6 180 32.5 – WHA Chonburi1 Industrial Estate, Thailand B.Grimm Power (WHA) 1 BPWHA1 Gas-Fired Cogen Nov-16 75.00% 130.2 97.5 EGAT (SPP) Nov-41 90 31 – WHA Eastern (Map Ta Phut) Industrial Estate, Thailand SPP1 SPP1 Gas-Fired Cogen Feb & Dec-98 100.00% 124.00 124.00 EGAT (SPP) Feb & Dec--21 110 110 48 Gas-Fired Cogen Total 2,021.50 1,202.20 1,250.00 642.80 188.70 Amata City (Bien Hoa) Industrial Estate, Vietnam Amata Power (Bien Hoa)(e) APB Diesel Generator Apr-99 30.70% 13 4 – – – 310.5 – Conventional Total 2,034.50 1,206.20 1,250.00 953.30 188.70

slide-35
SLIDE 35

BGRIM INVESTOR PRESENTATION 34

Operational Power Plants: Solar

Company / Project Abbreviation Location COD Economic Ownership %(a) Capacity Main PPA(s) Installed (MW) Equity (MW) Offtaker / Program PPA Expiry B.Grimm Yanhee Solar Power BGYSP 100.0% 59.7 59.7 Sai Luang 2 Pathumthani province, Thailand Dec-15 8.0 8.0 PEA (FiT) Dec-40 8.0 8.0 Sai Luang 3 Sai Luang 9 7.2 7.2 Sai Luang 10 7.5 7.5 Sai Yai Nha 8.0 8.0 Sai Manow 8.0 8.0 Sai Putsa 8.0 8.0 Sai Sena 2 Ayutthaya province, Thailand 5.0 5.0 Solarwa Solarwa 47.5% 38.5 18.3 Sai Lui Rim Num Nakhon Pathom province, Thailand Dec-15 8.0 3.8 PEA (FiT) Dec-40 Sai Chalouw 1 8.0 3.8 Sai Sab 8.0 3.8 BGTTRE2 Saraburi province, Thailand 8.0 3.8 BGTTRE3 6.5 3.1 TPS Commercial TPS Saraburi province, Thailand Dec-15 47.5% 8.0 3.8 PEA (FiT) Dec-40 B.Grimm Solar Power (Sakaeo) 1 BGPSK Sakaeo province, Thailand Apr-16 100.0% 8.0 8.0 PEA (FiT) Apr-41 Solar WVO-Cooperatives Solar WVO-Coop Dec-18 100.0% 30.8 30.8 BSPCD Sakaeo province, Thailand 2.3 2.3 PEA (FiT) Dec-43 BGPCCS Phetchabun province, Thailand 3.6 3.6 BSPCB Surat Thani province, Thailand 5.0 5.0 BGSP1WN Bangkok province, Thailand 5.0 5.0 MEA BGPLKB Bangkok province, Thailand 5.0 5.0 BGPBBO Samut Prakan province, Thailand 5.0 5.0 BGPSAI Nonthaburi province, Thailand 5.0 5.0 Dau Tieng (Xuan Cau) DT Tay Ninh province, Vietnam Jun-19 55.0% 420.0 231.0 EVN Jun-39 Phu Yen TTP (Phu Yen) Phu Yen TTP Phu Yen province, Vietnam Jun-19 80.0% 257.0 205.6 EVN Jun-39 Total 822.0 557.2

Note: As of 30 June 2019 (a) Based on B.Grimm Power’s direct and/or indirect interest in the project company owning the power plant.

slide-36
SLIDE 36

BGRIM INVESTOR PRESENTATION 35

Source: 56-1, EGAT, PEA (a) Some contract terms are year-on-year basis (b) According to concession agreements

SPP Gas-fired Cogeneration Solar PV Solar (Vietnam) Wind Hydro EGAT Industrial Users PEA (FiT) EVN PEA (Adder) EDL Electricity Steam Term (years)

21 – 25 years 5 – 15 years(a) 5 – 15 years(a) 25 years 20 years 5 years 25 years

Extension option

✓ ✓

– – 5 years auto extension Up to 10 years

Contracted capacity

90 MW

(except for BPLC1 which is 60MW)

Depends on each contract 5 – 8 MW 677 MW dc 564 MW ac 8 MW 6.7 – 15 MW(b)

Secured fuel supply

✓ ✓ ✓

N/A N/A N/A N/A

Natural gas cost pass-through

(at contracted heat rate)

Partially through Ft Depends on contract N/A N/A N/A N/A

FX pass-through

Partially through Ft – – – – –

Inflation indexation

– –

– – – –

Tariff

See next page 5.66 THB/kWh 9.35 Cents/kWh PEA wholesale + 10-year adder at 3.50 THB/kWh 0.065 US$/kWh

Applicable power plants

ABP1-5, ABPR1-5, BPLC1, BIP1-2, BPWHA1, BGPR1-2, SPP1 BGYSP (8 projects), Solarwa (5 projects), TPS, BGPSK DT1&2, Phu Yen TTP Bo Thong (2 projects) XXHP (2 projects), Nam Che, Nam Khao 1-5 (5 projects)

Contractual Overview: Commercial Features

slide-37
SLIDE 37

BGRIM INVESTOR PRESENTATION 36

Electricity Tariff = Capacity Payment + Energy Payment + Fuel Saving Payment + VAT

Capacity Payment Rate (THB/kW/month) = 𝐷𝑄0 × 𝑦 ×

𝐺𝑌𝑢 𝐺𝑌0 +(1− 𝑦)

Energy Payment Rate (THB/kWh) = 𝐹𝑄0 +

𝑄𝑢−𝑄0 106

× contracted Heat rate Fuel Saving Payment Rate (THB/KWh) = 𝐺𝑇0 ×

𝑄𝐹𝑇𝑢 10%

𝐺𝑌𝑢 = THB/ US$ Exchange Rate 𝑄𝑢 = Price for natural gas PTT sells to SPPs in a month (THB/mmBTU) 𝑄𝐹𝑇𝑢 = primary energy saving (“PES”) statistic measuring the efficiency rate of

  • ur gas-fired cogeneration power plant in consuming natural gas in the

generation of electricity and thermal energy

Source: Company filing and data, EGAT

SPP Regulation 1992, 1998 & 2005 2007 2010 Applicable power plants ABP1-2, SPP1 BPLC1 ABP3, ABPR1-2, BIP1 ABP4-5, ABPR3-5, BIP2, BOWIN, BGPR1-2 Base Capacity Payment Rate (𝐷𝑄

0) (THB/kW)

302.00 383.66 420.00 Base Exchange Rate (𝐺𝑌0) (THB/US$) 27 37 34 US$THB FX indexation (𝑦) 0.8 0.5 0.5 Base Energy Payment Rate (𝐹𝑄

0) (THB/kWh)

0.85 1.70 1.85 Base Price for Natural Gas PTT sells to SPPs (𝑄

0)

(THB/mmBTU) 77.0812 209.4531 232.6116 Contracted Heat Rate (BTU/kWh) 8,600 8,000 7,950 Fuel Saving Payment

✓ Base Fuel Saving Payment (𝐺𝑇0) (THB/kWh)

  • 0.36

0.36

Contractual Overview: EGAT PPA under SPP Program

TARIFF STRUCTURE

slide-38
SLIDE 38

BGRIM INVESTOR PRESENTATION 37

Projects Installed Capacity (MW) Steam Capacity (ton/hr) Type of maintenance Duration (days) 2018 Q1 Q2 Q3 Q4

Amata City (Chonburi)

ABP1 166.4 30.0 Major Overhaul 24 ABP2 171.2 30.0 Major Overhaul 22 Major Overhaul 12 ABP3 132.5 30.0 Major Overhaul 20 ABP4 131.1 30.0 Major Inspection 15

Laem Chabang

BPLC1 103.0 50.0 Major Overhaul 14 Major Overhaul 15 BPLC2 56.1 20.0 Major Inspection 7

Bangkadi

BIP1 114.6 20.0 Major Inspection 12 BIP2 114.6 20.0 Major Inspection 11

Major Maintenance Schedule in 2018 & 2019

Projects Installed Capacity (MW) Steam Capacity (ton/hr) Type of maintenance Duration (days) 2019 Q1 Q2 Q3 Q4

Amata City (Chonburi)

ABP1 166.4 30.0 Major Overhaul 22 ABP2 171.2 30.0 Major Overhaul 25 ABP3 132.5 30.0 Major Overhaul 20 ABP4 131.1 30.0 Major Inspection 12 ABP5 131.1 30.0 Major Inspection 24

WHA Chonburi 1

BPWHA 130.0 30.0 Major Inspection 12

slide-39
SLIDE 39

BGRIM INVESTOR PRESENTATION

Abbreviation & Our Projects

ABBREVIATION

ADB Asian Development Bank COD Commercial Operation Date EBITDA Earnings before Interest, Taxes, Depreciation and Amortization EDL Electricite Du Laos EGAT Electricity Generating Authority of Thailand ERC Energy Regulatory Commission EPC Engineering, Procurement and Construction EVN Electricity of Vietnam FiT Feed-in Tariff FX Foreign exchange IPO Initial public offering IU Industrial user IWTE Industrial Waste to Energy JV Joint venture KWh / GWh Kilo / Gigawatt-hour MEA Metropolitan Electricity Authority mmBtu Million Btu (unit of gas consumption) NNP Normalized net profit O&M Operations and maintenance P.A. Per annum PEA Provincial Electricity Authority (Thailand) PPA Power purchase agreement PTT PTT public Company Limited ROA Return on assets ROE Return on equity SG&A Selling, general & administrative expense YE Year End YoY Year-on-Year

OUR PROJECTS

ABPIF Amata B.Grimm Power Plant Infrastructure Fund ABP1 Amata B.Grimm Power 1 ABP2 Amata B.Grimm Power 2 ABP3 Amata B.Grimm Power 3 ABP4 Amata B.Grimm Power 4 ABP5 Amata B.Grimm Power 5 ABPR1 Amata B.Grimm Power (Rayong) 1 ABPR2 Amata B.Grimm Power (Rayong) 2 ABPR3 Amata B.Grimm Power (Rayong) 3 ABPR4 Amata B.Grimm Power (Rayong) 4 ABPR5 Amata B.Grimm Power (Rayong) 5 BGPSK B.Grimm Solar Power (Sakaeo) 1 BGSENA B.Grimm Sena Solar Power Limited BGYSP B.Grimm Yanhee Solar Power BIP1 B.Grimm BIP Power 1 BIP2 B.Grimm BIP Power 2 BPLC1 B.Grimm Power (Laem Chabang) 1 BPLC2 B.Grimm Power (Laem Chabang) 2 BPWHA1 B.Grimm Power (WHA) 1 Nam Che Nam Che 1 Hydro Power Project XXHP Xenamnoy 2 and Xekatam 1 Hydro Power Project Interchem Progress Interchem Solar WVO Solar WVO-Cooperatives Projects DT Dau Tieng Tay Ninh Energy Solar Plant Project (Xuan Cau) Phu Yen TTP Phu Yen TTP Solar Plant Project (Phu Yen)

38

slide-40
SLIDE 40

BGRIM INVESTOR PRESENTATION

Abbreviation & Our Projects

OUR PROJECTS

BSPCD The Chon Daen agricultural cooperatives project BGPCCS The WVO project, namely the Veteran Support Office of Chonburi BSPCB The Ban Na Doem agricultural cooperatives project BGSP1WN The WVO project, namely Office of Agriculture, Industry and Services Affairs BGPLKB The WVO project, namely the Veterans General Hospital BGPBBO The WVO project, namely the WVO Office of Terminal Production Workshop BGPSAI The WVO project, namely the WVO Office of Security Services

39

slide-41
SLIDE 41

BGRIM INVESTOR PRESENTATION

INVESTOR RELATIONS IR Contact

Disclaimer None of the Company makes any representation or warranty, express or implied, as to the accuracy or completeness of the information contained in this document or otherwise made available nor as to the reasonableness of any assumption contained herein or therein, and any liability therein (including in respect of any direct, indirect or consequential loss or damage) is expressly disclaimed. Nothing contained herein or therein is, or shall be relied upon as, a promise or representation, whether as to the past or the future and no reliance, in whole or in part, should be placed on the fairness, accuracy, completeness or correctness of the information contained herein. Further, nothing in this document should be construed as constituting legal, business, tax or financial advice. This document is a summary only and does not purport to contain all of the information that may be required to evaluate any potential transaction and any recipient hereof should conduct its own independent analysis of the Company, including the consulting of independent legal, business, tax and financial advisers. The information in these materials is provided as at the date of this document and is subject to change without notice. .

Email: IR@BGrimmPower.com Tel: +66 (0) 2710 3528 Solaya Na Songkhla

Email: Solaya.N@BGrimmPower.com

Gunnlapat Wichutarat

Email: Gunnlapat.W@BGrimmPower.com

Thunruethai Makaraphan

Email: Thunruethai.M@BGrimmPower.com

Contact Us:

  • Dr. Gerhard Link Building,

5 Krungthepkreetha Road, Huamark, Bangkapi, Bangkok 10240, Thailand Tel: +66 (0) 2710 3400 Fax: +66 (0) 2379 4245

40