Benjamin Banneker Elementary Milford, DE Michelle M. Baldwin - - PowerPoint PPT Presentation

benjamin banneker elementary
SMART_READER_LITE
LIVE PREVIEW

Benjamin Banneker Elementary Milford, DE Michelle M. Baldwin - - PowerPoint PPT Presentation

Benjamin Banneker Elementary Milford, DE Michelle M. Baldwin Mechanical Option Presentation Outline Existing Conditions Existing Mechanical System Analysis of Mechanical Redesign Dedicated Outdoor Air System Radiant Panels


slide-1
SLIDE 1

Benjamin Banneker Elementary

Milford, DE Michelle M. Baldwin Mechanical Option

slide-2
SLIDE 2

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Presentation Outline

Existing Conditions Existing Mechanical System Analysis of Mechanical Redesign Dedicated Outdoor Air System Radiant Panels Fire Protection Economic Analysis Lighting Conclusions

slide-3
SLIDE 3

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Project Team

Owner: Milford School District Mechanical: Furlow Associates Electrical: Carew Associates Structural: Baker Ingram Associates General Contractor: Conventional Builders

Building Cost: $8,195,200 Building Size: 64,600 ft2 Dates of Construction

Start: January 2002 Finish: October 2003

Existing Conditions

slide-4
SLIDE 4

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Architecture

Building Exterior

Decorative concrete block with a stacked bond Prefinished metal panels Metal awnings

slide-5
SLIDE 5

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

First Floor

slide-6
SLIDE 6

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Second Floor

slide-7
SLIDE 7

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Electrical

750 KVA transformer 208/120 V, 3 phase, 4 wire 70 A emergency generator

Classroom Lighting

Direct/indirect fluorescent suspended fixtures

slide-8
SLIDE 8

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Structural

Structural steel joists and girders Non-composite floor system 14’ floor to floor height 10’ ceiling height

Construction Management

New school built on the same site as existing

school

slide-9
SLIDE 9

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Existing Mechanical System

Dedicated Outdoor Air System

Two Energy Recovery Units (ERU)

Six Roof-top units Air-cooled chiller Fire-Tube Boilers Two-Pipe System

Unit Ventilators Fan Coil Units Fin-Tube Radiation

slide-10
SLIDE 10

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Mechanical System Flow Diagram

slide-11
SLIDE 11

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Existing Mechanical System

Supply Air Temp: 75˚F Terminal unit supply air temp:

Cooling – 55˚F Heating – 150˚F

Space dew point temp: 57˚F Space relative humidity: 53% Latent and Sensible load on the terminal

units

slide-12
SLIDE 12

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Mechanical Redesign Goals

Remove the existing terminal units Add radiant panels Decouple the Sensible and Latent Loads

Decrease the supply air temperature

Resize the cooling coil

Reduce the dew point temperature

Determine radiant panel supply water temperature

slide-13
SLIDE 13

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Mechanical Redesign

Noise in Classrooms

Decrease in ability to learn as background

noise increases

HVAC systems are the major source of

background noise

Classroom rating – NC 30dB Unit Ventilators – NC 45dB Typical classroom with unit ventilators –

NC 50 - 55dB

slide-14
SLIDE 14

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Dedicated Outdoor Air System

1. Outdoor air inlet 2. Enthalpy Wheel 3. Cooling and Heating Coils

100% Outdoor Air 15 cfm/person Energy Recovered from the return air stream

without mixing

slide-15
SLIDE 15

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Dedicated Outdoor Air System

  • Cooling
  • Outdoor air inlet:

93˚F

  • Enthalpy Wheel
  • utlet: 81˚F
  • Heating
  • Outdoor air inlet:

14˚F

  • Enthalpy Wheel
  • utlet: 54˚F
slide-16
SLIDE 16

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Mechanical Redesign

ERU supply temperature reduced from

75˚F to 50˚F

Resized Cooling Coil

Relative humidity reduced from 53% to

49%

Dew point temperature reduced from

57˚F to 54˚F

Reheat Coils

slide-17
SLIDE 17

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Radiant Panels

Invensys RCU-166

panels

Piping Connection Panel Shape

slide-18
SLIDE 18

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Radiant Panels

Room Air Temperature °F 75 Temperature Water Inlet °F 56 Temperature Water Outlet °F 59 Total Ceiling Area in ft2 800 Total RCU Area in ft2 per Module 10.40 Room Ceiling Height ft 8.50 Total Cooling Capacity BTUH/ft2 Active Area 53.41 Water Flow RCU per Module in gal/min 0.37 Total Number of Panels 844

slide-19
SLIDE 19

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Controls

Thermostat control

Heating Coils Radiant Panels

Condensation Risk

Operable windows Outdoor humidity

slide-20
SLIDE 20

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Fire Protection

Integration of sprinkler piping and

radiant panel piping

Normal Flow control

Chilled water supplied to radiant panels

Fire Flow control

Water supplied directly to sprinkler heads

slide-21
SLIDE 21

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Flow Diagram

slide-22
SLIDE 22

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Economic Analysis

First Cost Analysis

$6,634 $39,000 $2,760 $111,300 Total Condensate Piping Fan-Coil Units Fin-Tube Radiators Unit Ventilators

Equipment Removed

$900 $26,498 $21,000 $11,210 $114,109 Total Pumps Valves Reheat Coils Piping Radiant Panels

Equipment Added

slide-23
SLIDE 23

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Energy Analysis

Initial System Total Cost: $69,414

22.9% Air System Fans 22.6% Cooling 2.2% Heating 1.9% Pumps 29.5% Lights 21.0% Electric Equipment 22.9% Air System Fans 22.6% Cooling 2.2% Heating 1.9% Pumps 29.5% Lights 21.0% Electric Equipment

slide-24
SLIDE 24

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Energy Analysis

Redesigned System Total Cost: $ 65,292

15.6% Air System Fans 23.2% Cooling 4.0% Heating 3.6% Pumps 31.4% Lights 22.3% Electric Equipment 15.6% Air System Fans 23.2% Cooling 4.0% Heating 3.6% Pumps 31.4% Lights 22.3% Electric Equipment

slide-25
SLIDE 25

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Economic Analysis Summary

First Cost Analysis Summary

$14,024 Additional Cost $1,196,699 Total $173,717 Plus $159,693 Minus $1,182,675 Mechanical Cost

Energy Analysis Summary

The redesigned system is $4,122 less

expensive annually

Payback period is 3.4 years

slide-26
SLIDE 26

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Lighting

30 fc on task surface 1.5 W/ft2 3 types of light fixtures considered

Direct/Indirect fluorescent suspended fixture Direct recessed fluorescent fixture Direct fluorescent suspended fixture

slide-27
SLIDE 27

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Indirect/Direct Suspended Fluorescent Fixtures

48.6 fc 1.07 W/ft2

slide-28
SLIDE 28

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Direct Recessed Fluorescent Fixture

45.6 fc 0.89 W/ft2

slide-29
SLIDE 29

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Direct Suspended Fluorescent Fixture

40.1 fc 1.31 W/ft2

slide-30
SLIDE 30

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Lighting Recommendation

Direct fluorescent suspended fixtures 40.1 fc > 30 fc No shadows 1.31 W/ft2 < 1.5 W/ft2

slide-31
SLIDE 31

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Conclusions

Advantages

Lower Annual Energy Cost Short Payback Period Increased System Control Flexibility Increased Floor Area Decreased Background Noise

Increased Comfort Increased Learning Ability

Disadvantages

More Complicated Controls Higher First Cost

slide-32
SLIDE 32

Benjamin Banneker Elementary AE Senior Thesis Spring 2003 Michelle Baldwin Mechanical Option

Thanks

Furlow Associates

  • Dr. Mumma

AE Department Friends & Family

slide-33
SLIDE 33

?? Questions ??

AE Senior Thesis Spring 2003