Belmont Public Schools
School Committee Update September 11, 2018
1
Belmont Public Schools School Committee Update September 11, 2018 - - PowerPoint PPT Presentation
Belmont Public Schools School Committee Update September 11, 2018 1 Discussion Points Belmont Public School Goals Highlights Leading into 2018/19 Belmont High School Building Committee (BHSBC) Update Alternative Plan if Needed
School Committee Update September 11, 2018
1
2
Goals 2018- 2019
students that result in a positive and productive school culture
and learn about Culturally Responsive Teaching
increase our staff and add space by implementing our short and long term capacity plan
3
in the last four years
the School Committee recommended class size guidelines – as
halls in half from last year
and supplies - first increase in many years
4
plans:
CMS for new Grade 5 Teacher Team
Building Committee, Board of Selectman, School Committee and MSBA for a 7-12 school building project
5
6
7
2016 Summer 2017 Summer 2018 Fall 2017 Fall 2018
Timeline of Belmont High School Building Committee (BHSBC)
8
9
Need: Facilities
10
Non-ADA compliance Outdated systems Plumbing Leaks Windows Leak Contains materials now deemed to
be hazardous
Lacks modern security measures
11
Need: Teaching and Learning
12
Need for hands-on learning space Fully functional science facilities
No running water Non-functioning safety equipment Inadequate science lab space Inadequate science classroom space
Rooms used for a purpose for
which they were not intended
Chorus in the old auto shop garage Health and Wellness in old lecture hall Physics class not in a lab space
Meeting the Need: Belmont 7-12 Project Site Design
13
Meeting the Need: Belmont 7-12 Project Design
14
15
$295 M
Total Project Costs
-$80 M
MSBA Funding
$215 M
Belmont Cost
-$2 M
Previous Committed Expenditure
$213 M
Belmont’s Future Costs Comparable Projected Total Project Costs
Arlington (1,755 students)
$308 M (Feasibility Phase)
Waltham (1,830 students)
$280-300 M (Feasibility Phase)
Belmont 7-12 (2215 students)
16
2018/19 School Year -
Design Detailed Plans
Summer 2019 –
Break ground on BHS site on Phase One (9-12 portion of
building)
Summer 2021 –
Students in grades 9-12 move into new school; Enter into Phase Two of project (Grades 7/8)
Summer 2023 –
Students in grades 7 & 8 move in from Chenery
November 6th election
aspects of this Pre K – 12 reconfiguration work and participation on Steering Committees
may have…
17
Belmont’s Alternative: Capacity Challenge Planning
18
What If the vote does not pass? What is going to happen? What is the potential cost to the Town? The School Committee and the School Department will enter into: Belmont Capacity Challenge Planning
19
Belmont Capacity Challenge Planning
Phase 1: Modular Space
Middle School and Belmont High School
This will require:
FY21
All phases of the project from design to construction and funding will need to be approved and voted on by Town Committees ,Town Meeting and likely community - wide vote. 20
Belmont Capacity Challenge Planning
Phase 2: Plan, Design, and Construct Chenery Renovation and Addition
This will require:
All phases of the project from design to construction and funding will need to be approved and voted on by Town Committees, Town Meeting and likely community-wide vote.
21
Belmont Capacity Challenge Planning
Phase 3: Plan, Design, and Construct Belmont High School Major Renovation and Addition
This will require:
hazardous materials
All phases of the project from design to construction and funding will need to be approved and voted on by Town Committees, Town Meeting and likely community-wide vote.
22
Belmont Capacity Challenge Projected Costs
Timeline Phase Type of Space
Location
Cost Notes 2019/20 2020/21 # 1 Additional Modular Space CMS Up to 12 units $9 M Estimates based on current purchase at Burbank BHS Up to 16 units $12 M Elem. Up to 4 units $3 M Modular units will remain at Burbank and new location permanently 2021- 2025 # 2 Addition and Renovation CMS * Starting in 2022 $20 M
Plan, Design, Bid, Fund, Construct Cost Estimates from SMMA Grade Configuration Study, January 9, 2018
2024- 2028 # 3 Addition and Renovation BHS * Starting in 2024 $203M
Plan, Design, Bid, Fund, Construct Cost Estimates from BHSBC – Daedalus Projects Inc. – August 2018
10 Years for funding and construction $247 M Total Expended No State Funding Support
23
Summary Belmont Capacity Challenge Planning
The district would have: Up to 40 modular classrooms in use for a period of time. Permanent modular classrooms at the elementary level All or parts of the K-12 district in partial or full construction for
the next 10 years
Every phase will require: Design planning OPM support Constructions costs All of these projects will need: Separate Town Meeting approval and funding A yes vote at each junction is not guaranteed There is no state funding to support this work Projected costs totaling: $247 million will be placed on the Belmont
taxpayer
24
BHSBC 7-12 Project Alternative Planning Cost to Belmont Taxpayers $ 215 M $247 Best timeline for completion 5 years 10 years Quality of educational space for all students K-12 Yes To be determined Number of projects involved in solution 1 Up to 3 projects To be determined Funding secured and supported by State $80,000,000 $0 Funding secured and supported by Town Meeting 1 Vote TBD Several Votes TBD 25
26