BEACH ELEMENTARY SCHOOL FEASIBILITY STUDY Presentation to Calvert - - PowerPoint PPT Presentation
BEACH ELEMENTARY SCHOOL FEASIBILITY STUDY Presentation to Calvert - - PowerPoint PPT Presentation
BEACH ELEMENTARY SCHOOL FEASIBILITY STUDY Presentation to Calvert County Board of Education February 7, 2019 FEASIBILITY STUDY Process Step 1: Information Gathering & Evaluation Compare Existing Building Program vs. Project Goals
FEASIBILITY STUDY
Process
Step 1: Information Gathering & Evaluation
- Compare Existing Building Program vs. Project Goals & Ed Spec
- Evaluate Existing Building Issues
- Code Analysis / Review
- Building Specific Diagrams
- Site Plan Analysis
Step 2: Concept Design
- Proposed Concept Bubble Diagrams Depicting General Planning
Concepts
- Committee Input is Applied to Diagrams
- Combinations of Preferred Features
- Incorporated of New Committee Input
- Development of Refined Approaches
Step 3: Development of Plan Options
- Concepts are refined into Formal Plan Approaches and Technically
Scrutinized
- Engineering Disciplines are Applied
- Code Compliance
- Cost Estimating
- Sustainability, Energy Conservation & Life Cycle Cost Analysis
- Construction Schedule, Duration, and Phasing Plan
Step 4: Technical Report Preparation
- Prepare Board of Education Presentation and Brochures
- Prepare IAC Feasibility Study Submission
FEASIBILITY STUDY
Stakeholder Advisory Group
- The study is the result of it’s collaborative process
- Thank you to the members of the Stakeholder Advisory
Group for dedicating your time, knowledge, and efforts into this process
- Dr. Michael Shisler, Principal, Beach Elementary School
- Casey Grenier, Teacher, Beach Elementary School
- Gwen Redden Henderson, Parent, Beach Elementary School
- Mary Sterling, Parent, Beach Elementary School
- Shuchita Warner LEED AP, Director of School Construction, CCPS
- Darrell Barricklow AIA, LEED AP, Supervisor of School
Construction, CCPS
- Gregg Gott, Supervisor of Operations, CCPS
- Ed Cassidy, Director of Transportation, CCPS
FEASIBILITY STUDY
Program Goals
- Existing Building
- Area: 54,893 GSF
- SRC: 514 students
- 9 Portables
- Proposed Building
- Ed Spec NSF: 50,115
- Ed Spec GSF: 67,860
- Ed Spec SRC: 600
Admin Instructional Media Center Special Ed Gym/ Cafe Music/ Arts Building Services
FEASIBILITY STUDY
Existing Conditions Evaluation
- Architectural
- Smolen Emr Ilkovitch Architects
- Civil
- Collinson Oliff & Associates
- Structural
- ADTEK Engineers
- Mechanical
- James Posey Associates
- Electrical
- James Posey Associates
- Plumbing
- James Posey Associates
- Data / IT
- James Posey Associates
- Life Safety
- Smolen Emr Ilkovitch Architects
- James Posey Associates
- Cost Estimating
- MK Consulting Engineers
FEASIBILITY STUDY
Approach Comparison
APPROACH 1
Phased While Occupied
Minimize Demolition Maximize Adaptive-Reuse Minimize Sitework Satisfactory Program & Adjacencies APPROACH 2
Phased While Occupied
Increase Demolition Increase New Construction Improve Sitework Good Program & Adjacencies APPROACH 3A*
Phased While Occupied
APPROACH 3B
Phased While Occupied
APPROACH 3C REVITALIZATION MODERNIZATION REPLACEMENT Complete Demolition All New Construction Site Redevelopment Ideal Program & Adjacencies
*Retains 2006 Addition
The purpose of a feasibility study is to determine the project approach, not to design the building
APPROACH 1: REVITALIZATION
Site & Floor Plan
APPROACH 1: REVITALIZATION
Phasing Plan
existing building addition demolition renovation new building PHASING KEY SY 1
1 2a
SY 2 SY 3
2b 3 site
PHASING SCHEDULE 39 Months phase 0 phase 2 site phase 3 phase 1 a b
APPROACH 1: REVITALIZATION
Advantages
- New addition and renovation allows
for 21st century learning environments
- Front entry faces Bayside Road
- Separated Bus & Student Drop-Off
- Achieves Site Program
- All Teaching Spaces receive Natural
Light and Views
- Defined Pod Structure for Each
Grade
APPROACH 1: REVITALIZATION
Disadvantages
- Keeps most of building’s existing
infrastructure
- Choke point from main entry to
instructional core of the building
- Does not meet all ed spec
adjacencies
- Cafetorium to Gym
- Instrumental Music to 4th & 5th
Grades
- Media, Art & Music have to traverse
through the open Cafeteria
- No Natural Light in Cafeteria
- Gym SF remains the same
- 1971 addition revitalization is costly
- Admin and Public Program is distant
from Instruction (long travel distance)
- Gym is remote from Play Fields
- Differing Floor Elevations
- Nose to Tail Bus Parking
- Longer Construction Duration due
to Phasing
APPROACH 2: MODERNIZATION
Site & Floor Plan
2nd floor
APPROACH 2: MODERNIZATION
Phasing Plan
existing building addition demolition renovation new building PHASING KEY phase 0 phase 2 phase 4 phase 1 phase 3 site a b SY 1
1 2
SY 2 SY 3
3 site
PHASING SCHEDULE 30 Months
4a 4b
APPROACH 2: MODERNIZATION
Advantages
2nd floor
- New addition and renovation allows
for 21st century learning environments
- A clear front entry faces Bayside
Road
- Separated Bus & Student Drop-Off
- Achieves Site Program with
exception of Outdoor Dining
- Media Center is Prominent on Front
- f Building
- All Teaching Spaces receive Natural
Light and Views
- 2nd Floor allows views toward the
Water
- Clear separation of Public vs.
Private
- Secure evening use
APPROACH 2: MODERNIZATION
Disadvantages
2nd floor
- Choke point from main entry to
instructional core of the building
- Does not meet ed spec adjacencies
for some programs
- General Music to Stage
- Art to Music Suite
- Instrumental Music to 4th & 5th Grade
- Gym is remote from Play Fields
- Outdoor Play Areas are remote from
Cafeteria
- Differing Floor Elevations
- Media Center is not Centralized
- Must cross Bus Loop from Parking
Lot
- Drop-off Loop creates a push
condition
- Longer Construction Duration due
to Phasing
APPROACH 3A: REPLACE. PWO
Site & Floor Plan
2nd floor
APPROACH 3A: REPLACE. PWO
Phasing Plan
phase 0 phase 2 phase 4 phase 1 phase 3 phase 5 site SY 1
1 2
SY 2 SY 3
3 site
PHASING SCHEDULE 30 Months
4 5
existing building addition demolition renovation new building PHASING KEY
APPROACH 3A: REPLACE. PWO
Advantages
2nd floor
- New addition and renovation allows
for 21st century learning environments
- Separated Bus & Student Drop-Off
- Achieves Site Program
- When students enter they split into
two directions eliminating pinch point
- Media Center is Centralized
- All Teaching Spaces receive Natural
Light and Views
- Achieves all Adjacencies
- Large Courtyard can serve
Controlled Outdoor Learning Environments
- Clear separation of Public vs.
Private
- Secure evening use
- Ideal Building Location
- Phased While Occupied Replacement
APPROACH 3A: REPLACE. PWO
Disadvantages
2nd floor
- Gym does not directly open to Play
Fields
- May have Differing Floor Elevations
- Single loaded Corridor is Inefficient
- Service is visible from Bayside Road
- Will require screening
- Longer Construction Duration due
to Phasing
APPROACH 3B: REPLACE. PWO
Site & Floor Plan
2nd floor
APPROACH 3B: REPLACE. PWO
Phasing Plan
existing building addition demolition renovation new building PHASING KEY phase 0 phase 2 phase 4 phase 1 phase 3 site SY 1
1 2
SY 2 SY 3
3 site
PHASING SCHEDULE 30 Months
4 site
APPROACH 3B: REPLACE. PWO
Advantages
2nd floor
- Achieves 21st century learning
environments
- Separated Bus & Student Drop-Off
- Achieves Site Program
- Media Center is Centralized &
Prominent on face of Building
- All Teaching Spaces receive Natural
Light and Views
- Achieves all Adjacencies
- Large Plaza focuses the design on
Outdoor Learning Environments
- The shape provides features of a
courtyard without being a courtyard
- All play areas are remote from street
- 2nd Floor allows views toward the
Water
- Clear separation of Public vs.
Private with secure evening use
- Gym and Cafeteria are tucked away
- Portables do not have to be moved
- Ideal Building Location
APPROACH 3B: REPLACE. PWO
Disadvantages
2nd floor
- Parking is Remote from Entry
- Service area is visible from parking
and possible secondary entrance
- Longer Construction Duration due
to Phasing
APPROACH 3C: REPLACEMENT
Site & Floor Plan
2nd floor 3rd floor
APPROACH 3C: REPLACEMENT
Views
APPROACH 3C: REPLACEMENT
Phasing Plan
existing building addition demolition renovation new building PHASING KEY SY 1
1 2
SY 2 SY 3 PHASING SCHEDULE 27 Months
site
phase 0 phase 2 phase 1 site
APPROACH 3C: REPLACEMENT
Advantages
2nd floor 3rd floor
- Lighthouse concept acknowledges
Nautical identity of Community
- Fronts both roads
- Achieves 21st century learning
environments
- Large, Controlled Collaboration
Spaces
- Separated Bus & Student Drop-Off
- Very long Drop-off Loop
- Preferred Bus Loop Stacking
- Achieves Site Program
- Media Center is Centralized
- All Teaching Spaces receive Natural
Light and Views
- Achieves all Adjacencies
- 2nd & 3rd Floors Views of Water
- Clear separation of Public vs.
Private with secure evening use
- Ideal Building Location
- Takes advantage of learning
- pportunities from the creek
- Shorter Construction Duration
APPROACH 3C: REPLACEMENT
Disadvantages
2nd floor 3rd floor
- Vertical Circulation
- Highest Gross Area
- Greatest collaboration opportunities
- Parking is remote from entry
SUMMARY
Area Comparison
APPROACH 1
Phased While Occupied
Existing Demo. Reno. New Total Efficiency 54,893 18,237 36,693 31,666 68,359 73% APPROACH 2
Phased While Occupied
Existing Demo. Reno. New Total Efficiency 54,893 39,466 15,320 52,321 67,641 74% APPROACH 3A
Phased While Occupied
Existing Demo. Reno. New Total Efficiency 54,893 51,985 2,912 64,570 67,482 73% APPROACH 3B
Phased While Occupied
Existing Demo. Reno. New Total Efficiency 54,893 54,893 67,135 67,135 75% APPROACH 3C Existing Demo. Reno. New Total Efficiency 54,893 54,893 69,692 69,692 72% REVITALIZATION MODERNIZATION REPLACEMENT
SUMMARY
Program Comparison
APPROACH 1
Phased While Occupied
Admin Guidance Itinerant Grades 1-5 Pre-K & K Special Ed Music Visual Arts Media Ctr PE Facilities Cafetorium NET GROSS 97% 101% 85% 100% 100% 96% 134% 93% 98% 78% 99% 111% 100% 101% APPROACH 2
Phased While Occupied
Admin Guidance Itinerant Grades 1-5 Pre-K & K Special Ed Music Visual Arts Media Ctr PE Facilities Cafetorium NET GROSS 100% 106% 104% 98% 96% 101% 98% 97% 101% 101% 97% 103% 99% 98% APPROACH 3A
Phased While Occupied
Admin Guidance Itinerant Grades 1-5 Pre-K & K Special Ed Music Visual Arts Media Ctr PE Facilities Cafetorium NET GROSS 100% 100% 105% 99% 99% 100% 91% 85% 100% 100% 96% 101% 99% 100% APPROACH 3B
Phased While Occupied
Admin Guidance Itinerant Grades 1-5 Pre-K & K Special Ed Music Visual Arts Media Ctr PE Facilities Cafetorium NET GROSS 102% 97% 89% 100% 98% 100% 98% 101% 100% 100% 95% 106% 100% 99% APPROACH 3C Admin Guidance Itinerant Grades 1-5 Pre-K & K Special Ed Music Visual Arts Media Ctr PE Facilities Cafetorium NET GROSS 108% 134% 101% 99% 100% 101% 99% 95% 98% 101% 105% 100% 100% 103% REVITALIZATION MODERNIZATION REPLACEMENT
SUMMARY
Cost Comparison
APPROACH 1
Phased While Occupied
Duration
39 months
Construction Cost
$22,850,970
Contingency (13%)
$2,970,626
Escalation (15.6%)
$4,034,624.35
- Constr. Budget
$29,856,220
Life Cycle
O&M Expense: $8,425,508 40 Year Cost: $38,281,729
APPROACH 2
Phased While Occupied
Duration
30 months
Construction Cost
$22,762,190
Contingency (12%)
$2,731,463
Escalation (13.8%)
$3,505,377
- Constr. Budget
$28,999,029
Life Cycle
O&M Expense: $8,337,011 40 Year Cost: $37,336,040
APPROACH 3A
Phased While Occupied
Duration
30 months
Construction Cost
$23,527,973
Contingency (10%)
$2,352,797
Escalation (13.8%)
$3,558,605
- Constr. Budget
$29,439,375
Life Cycle
O&M Expense: $7,908,665 40 Year Cost: $37,348,040
APPROACH 3B
Phased While Occupied
Duration
30 months
Construction Cost
$22,849,118
Contingency (10%)
$2,284,912
Escalation (13.8%)
$3,455,929
- Constr. Budget
$28,589,959
Life Cycle
O&M Expense: $7,867,997 40 Year Cost: $36,457,955
APPROACH 3C Duration
27 months
Construction Cost
$23,222,447
Contingency (10%)
$2,322,245
Escalation (12.8%)
$3,256,948
- Constr. Budget
$28,801,640
Life Cycle
O&M Expense: $8,089,939 40 Year Cost: $36,891,578
REVITALIZATION MODERNIZATION REPLACEMENT
SUMMARY
Overall Results
APPROACH 1
Phased While Occupied
Existing Demo. Reno. New Total Efficiency Duration
- Const. Budget
Life Cycle 54,893 18,237 36,693 31,666 68,359 73.2% 39 months $29,856,220 $38,281,729 APPROACH 2
Phased While Occupied
Existing Demo. Reno. New Total Efficiency Duration
- Const. Budget
Life Cycle 54,893 39,466 15,320 52,321 67,641 74.8% 30 months $29,999,029 $37,336,040 APPROACH 3A
Phased While Occupied
Existing Demo. Reno. New Total Efficiency Duration
- Const. Budget
Life Cycle 54,893 51,985 2,912 64,570 67,482 73.5% 30 months $29,439,375 $37,348,040 APPROACH 3B
Phased While Occupied
Existing Demo. Reno. New Total Efficiency Duration
- Const. Budget
Life Cycle 54,893 54,893 67,135 67,135 75% 30 months $28,589,959 $36,457,955 APPROACH 3C Existing Demo. Reno. New Total Efficiency Duration
- Const. Budget
Life Cycle 54,893 54,893 69,692 69,692 72% 27 months $28,801,639 $36,891,578 REVITALIZATION MODERNIZATION REPLACEMENT
RECOMMENDED APPROACH
By Stakeholder Advisory Group
Stakeholder Advisory Group Unanimously Recommends the Replacement Approach
- Offers ideal building and site
learning environments and adjacencies
- Eliminates failing existing
building conditions
- All options were relatively
equal in construction budget
- Reduces complexity and
duration of construction limiting interference to instruction
- Offers best life cycle cost
analysis