BC Hydro Rock Bay Remediation Project Approach and Challenges - - PowerPoint PPT Presentation

bc hydro rock bay remediation project
SMART_READER_LITE
LIVE PREVIEW

BC Hydro Rock Bay Remediation Project Approach and Challenges - - PowerPoint PPT Presentation

BC Hydro Rock Bay Remediation Project Approach and Challenges Remediating a Former Deep Coal Tar Well under a Heritage Building David Kettlewell, SNC-Lavalin Inc. Lindsay Thompson, BC Hydro BC Hydro Working Area 1 (Stage 1)


slide-1
SLIDE 1

› BC Hydro Rock Bay Remediation Project

› Approach and Challenges Remediating a Former › Deep Coal Tar Well under a Heritage Building

David Kettlewell, SNC-Lavalin Inc. Lindsay Thompson, BC Hydro

slide-2
SLIDE 2

BC Hydro – Working Area 1 (Stage 1)

2

› Assessment (1990-2003) › Stage 1 Remediation (2004/05) › Post Remediation Assessment (2007-15) › Heritage Revitalization Agreement (2012) › WA1 Supplementary Remediation and Tar Well Removal (2013) › BC Certificate of Compliance (2016)

Remediation History

Roc

  • ck

k Bay ay (Power erhous house) e) Building uilding Ins nstrument umentation ion Building uilding

slide-3
SLIDE 3

Manufactured Gas Plant 101

3

› Subtitle

  • Normal text

› Third level › Fourth level › Fifth level

Retorts

Retorts Hydraulic Main Condenser Tar Well Scrubber Purifying Pan Gas Holder

slide-4
SLIDE 4

Manufactured Gas Plant 101

4

Retorts

Scr crub ubber bers Condens

  • ndenser

ers Ret etor

  • rt Hous

House e

1891 1891

Pur urif ifying ing Hous House e

Tar ar Well ell

slide-5
SLIDE 5

Historical Structures with Heritage Value

5

› Adminis

dministration ion Building uilding

› Roc

  • ck

k Bay ay (Power erhous house) e) Building uilding

slide-6
SLIDE 6

Historical Structures with Heritage Value

6

› Ins

nstrument umentation ion Building uilding

slide-7
SLIDE 7

Historical Structures with Heritage Value

7

› Ins

nstrument umentation ion Building uilding

slide-8
SLIDE 8

BC Hydro – Stage 1 Remediation

8

› Excavation and off-site disposal of over 110,000 tonnes of contaminated material from BC Hydro and Transport Canada Lands › Minimal contamination identified beneath the Admin Building and the Rock Bay Building › Significant volume of Waste and Hazardous Waste contamination remained beneath the Former Instrumentation Building (FIB) (estimated at ~2,000 tonnes) › Source of ongoing groundwater contamination for the property

slide-9
SLIDE 9

9

› Identified during the excavation around the perimeter of the Former Instrumentation Building › 1.9 m diameter / 14 m depth › Estimated to contain 26,000 litres of coal tar NAPL

BC Hydro – Stage 1 Remediation

Tar Well

slide-10
SLIDE 10

10

BC Hydro – Stage 1 Remediation

Tar ar Well ell

› Temporary CDF stabilizaton

slide-11
SLIDE 11

11

BC Hydro – Stage 1 Remediation

Ins nstrument umentation ion Building uilding

› Waste and Hazardous Waste isolated around the Former Instrumentation Building with CDF until a resolution on how to address the material could be reached

slide-12
SLIDE 12

Heritage Revitalization Agreement

12

› BC Hydro collaborated with the City of Victoria to establish a heritage revitalization agreement in 2012 › Engagement and consultation with Planning Department, Heritage Advisory Committee, City Council, and Community Groups › Ensured stabilization of two heritage buildings (Admin Building / Rock Bay Powerhouse Building) › Exchange for demolition of the Former Instrumentation Building › Allowed unfettered access to the Tar Well

slide-13
SLIDE 13

Tar Well Remediation

13

› High risk project › Technically challenging › Specialized solution needed › Candidate for Early Contractor Involvement Approach (ECI) › Three specialist remediation contractors engaged to assist with developing the overall remedial approach › Successful in mitigating risk (technical feasibility, constructability, schedule, costs) › Aid to ensure that the design will achieve the desired outcome!

Ear arly Cont

  • ntract

actor

  • r

Involv

  • lvement

ement

slide-14
SLIDE 14

Tar Well Remediation

14

› Temporary Sheetpile Box

  • Excavate to 8 m bgs for working platform
  • 5 m sheetpile box with bracing around the

Tar Well

  • Once the contents have been excavated,

backfill the Tar Well footprint with CDF and remove the steel sheets

Remedial emedial Opt Option ion Evalua aluation ion

slide-15
SLIDE 15

Tar Well Remediation

15

› Steel Caisson Shorting

  • ~3 m (10 ft) diameter steel pipe driven

into the ground around the Tar Well

  • Removal of contents with clamshell

attachment on a large lattice boom crane

  • Caisson removed and filled with CDF

› Secant Barrier Wall

  • 900 mm diameter overlapping secant

piles consisting of medium strength concrete columns

  • Removal of contents with clamshell

attachment on a large lattice boom crane

  • Secant piles are permanent, filled with

CDF upon completion

Remedial emedial Opt Option ion Evalua aluation ion

slide-16
SLIDE 16

Tar Well Remediation

16

› Tar Well constructed of brick and mortar – potential for tar leakage › Detailed drilling program to understand impacts around the well › 14 boreholes drilled to >14 m depth

Planning lanning

slide-17
SLIDE 17

Tar Well Remediation

17

› Detailed drilling program to understand impacts around the well › 14 boreholes drilled to >14 m depth › Ensure the diameter of the Secant Pile Shoring systems captures all contamination

Planning lanning

slide-18
SLIDE 18

Tar Well Remediation

18

› 22 Interlocking Secant Piles @ 3.75 m dia › Styrofoam forms used as guide › Secants keyed into bedrock

Secant ecant Ins nstalla allation ion

slide-19
SLIDE 19

Tar Well Remediation

19

› Soil, brick and tar removed using a various pieces of equipment › Material stabilization in-situ using

  • hogfuel. Needed to meet

specifications of treatment facility (Envirogreen Technologies) › Specialized equipment to remove residual material and clean the sidewalls of the secant piles › Shipments carefully planned / coordinated to minimize odour coming from the transport trucks

Tar ar Well ell Exca cavation ion

slide-20
SLIDE 20

Tar Well Remediation

20

Tar ar Well ell Exca cavation ion

slide-21
SLIDE 21

Tar Well Remediation

21

Tar ar Well ell Exca cavation ion

slide-22
SLIDE 22

Tar Well Remediation

22

Tar ar Well ell Exca cavation ion

VIDEO O

slide-23
SLIDE 23

QUESTIONS?