bc hydro rock bay remediation project
play

BC Hydro Rock Bay Remediation Project Approach and Challenges - PowerPoint PPT Presentation

BC Hydro Rock Bay Remediation Project Approach and Challenges Remediating a Former Deep Coal Tar Well under a Heritage Building David Kettlewell, SNC-Lavalin Inc. Lindsay Thompson, BC Hydro BC Hydro Working Area 1 (Stage 1)


  1. › BC Hydro Rock Bay Remediation Project › Approach and Challenges Remediating a Former › Deep Coal Tar Well under a Heritage Building David Kettlewell, SNC-Lavalin Inc. Lindsay Thompson, BC Hydro

  2. BC Hydro – Working Area 1 (Stage 1) Remediation History › Assessment (1990-2003) › Stage 1 Remediation (2004/05) › Post Remediation Roc ock k Bay ay (Power erhous house) e) Assessment (2007-15) Building uilding › Heritage Revitalization Agreement (2012) Ins nstrument umentation ion Building uilding › WA1 Supplementary Remediation and Tar Well Removal (2013) › BC Certificate of Compliance (2016) 2

  3. Manufactured Gas Plant 101 Retorts › Subtitle • Normal text Hydraulic Main › Third level › Fourth level Scrubber Condenser › Fifth level Gas Holder Retorts Purifying Pan Tar Well 3

  4. Manufactured Gas Plant 101 Retorts 1891 1891 Pur urif ifying ing Hous House e Scr crub ubber bers Condens ondenser ers Ret etor ort Hous House e Tar ar Well ell 4

  5. Historical Structures with Heritage Value › Adminis dministration ion Building uilding › Roc ock k Bay ay (Power erhous house) e) Building uilding 5

  6. Historical Structures with Heritage Value › Ins nstrument umentation ion Building uilding 6

  7. Historical Structures with Heritage Value › Ins nstrument umentation ion Building uilding 7

  8. BC Hydro – Stage 1 Remediation › Excavation and off-site disposal of over 110,000 tonnes of contaminated material from BC Hydro and Transport Canada Lands › Minimal contamination identified beneath the Admin Building and the Rock Bay Building › Significant volume of Waste and Hazardous Waste contamination remained beneath the Former Instrumentation Building (FIB) (estimated at ~2,000 tonnes) › Source of ongoing groundwater contamination for the property 8

  9. BC Hydro – Stage 1 Remediation Tar Well › Identified during the excavation around the perimeter of the Former Instrumentation Building › 1.9 m diameter / 14 m depth › Estimated to contain 26,000 litres of coal tar NAPL 9

  10. BC Hydro – Stage 1 Remediation Tar ar Well ell › Temporary CDF stabilizaton 10

  11. BC Hydro – Stage 1 Remediation Ins nstrument umentation ion Building uilding › Waste and Hazardous Waste isolated around the Former Instrumentation Building with CDF until a resolution on how to address the material could be reached 11

  12. Heritage Revitalization Agreement › BC Hydro collaborated with the City of Victoria to establish a heritage revitalization agreement in 2012 › Engagement and consultation with Planning Department, Heritage Advisory Committee, City Council, and Community Groups › Ensured stabilization of two heritage buildings (Admin Building / Rock Bay Powerhouse Building) › Exchange for demolition of the Former Instrumentation Building › Allowed unfettered access to the Tar Well 12

  13. Tar Well Remediation Ear arly Cont ontract actor or Involv olvement ement › High risk project › Technically challenging › Specialized solution needed › Candidate for Early Contractor Involvement Approach (ECI) › Three specialist remediation contractors engaged to assist with developing the overall remedial approach › Successful in mitigating risk (technical feasibility, constructability, schedule, costs) › Aid to ensure that the design will achieve the desired outcome! 13

  14. Tar Well Remediation Remedial emedial Opt Option ion Evalua aluation ion › Temporary Sheetpile Box • Excavate to 8 m bgs for working platform • 5 m sheetpile box with bracing around the Tar Well • Once the contents have been excavated, backfill the Tar Well footprint with CDF and remove the steel sheets 14

  15. Tar Well Remediation Remedial emedial Opt Option ion Evalua aluation ion › Steel Caisson Shorting • ~3 m (10 ft) diameter steel pipe driven into the ground around the Tar Well • Removal of contents with clamshell attachment on a large lattice boom crane • Caisson removed and filled with CDF › Secant Barrier Wall • 900 mm diameter overlapping secant piles consisting of medium strength concrete columns • Removal of contents with clamshell attachment on a large lattice boom crane • Secant piles are permanent, filled with CDF upon completion 15

  16. Tar Well Remediation Planning lanning › Tar Well constructed of brick and mortar – potential for tar leakage › Detailed drilling program to understand impacts around the well › 14 boreholes drilled to >14 m depth 16

  17. Tar Well Remediation Planning lanning › Detailed drilling program to understand impacts around the well › 14 boreholes drilled to >14 m depth › Ensure the diameter of the Secant Pile Shoring systems captures all contamination 17

  18. Tar Well Remediation Secant ecant Ins nstalla allation ion › 22 Interlocking Secant Piles @ 3.75 m dia › Styrofoam forms used as guide › Secants keyed into bedrock 18

  19. Tar Well Remediation Tar ar Well ell Exca cavation ion › Soil, brick and tar removed using a various pieces of equipment › Material stabilization in-situ using hogfuel. Needed to meet specifications of treatment facility (Envirogreen Technologies) › Specialized equipment to remove residual material and clean the sidewalls of the secant piles › Shipments carefully planned / coordinated to minimize odour coming from the transport trucks 19

  20. Tar Well Remediation Tar ar Well ell Exca cavation ion 20

  21. Tar Well Remediation Tar ar Well ell Exca cavation ion 21

  22. Tar Well Remediation Tar ar Well ell Exca cavation ion VIDEO O 22

  23. QUESTIONS?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend