BALANCING CONTRACTUAL AND RELATIONAL APPROACHES FOR PPP SUCCESS - - PowerPoint PPT Presentation

balancing contractual and relational approaches for ppp
SMART_READER_LITE
LIVE PREVIEW

BALANCING CONTRACTUAL AND RELATIONAL APPROACHES FOR PPP SUCCESS - - PowerPoint PPT Presentation

BALANCING CONTRACTUAL AND RELATIONAL APPROACHES FOR PPP SUCCESS & SUSTAINABILITY Mohan Kumaraswamy Aaron Anvuur Motiar Rahman The University of Hong Kong PPP CONFERENCE HK 2005 1 Presentation Outline PPP Characteristics &


slide-1
SLIDE 1

PPP CONFERENCE HK 2005 1

BALANCING CONTRACTUAL AND RELATIONAL APPROACHES FOR PPP SUCCESS & SUSTAINABILITY Mohan Kumaraswamy Aaron Anvuur Motiar Rahman The University of Hong Kong

slide-2
SLIDE 2

PPP CONFERENCE HK 2005 2

Presentation Outline

PPP Characteristics &

Priorities

Control Mechanisms RC & PPPs RC & Sustainable

Infrastructure

Research Agenda Concluding Remarks

slide-3
SLIDE 3

PPP CONFERENCE HK 2005 3

PPP Projects

Characteristics

Mostly natural monopolies High stakeholder interests High Uncertainty

market, technology, economy, project contextual conditions

Long-term

and so accentuating the uncertainties

Large

requiring huge resource deployment

Complex

multiple interlocking dependencies of various aspects

Prohibitive transaction costs

lengthy and costly bidding process

slide-4
SLIDE 4

PPP CONFERENCE HK 2005 4

PPP Projects

Priorities

Maximise value capture to society

– the reason for the first ‘P’ in PPP

Obtain best quality at lowest possible cost

– another name is value for money

Demonstrate probity and accountability Ensure sustainability of service and the

environment

slide-5
SLIDE 5

PPP CONFERENCE HK 2005 5

Control Mechanisms

Approaches to ensure control and cooperation

Market Hierarchy Classical Contracting Trust Price, Authority & Trust

slide-6
SLIDE 6

PPP CONFERENCE HK 2005 6

Control Mechanisms

Market Transactions are governed by price and

sealed by contracts

Considered suitable when there

– are alternative supply sources – are low uncertainties – is low transaction frequency

slide-7
SLIDE 7

PPP CONFERENCE HK 2005 7

Control Mechanisms

Hierarchy Authority structures control transactions

and the allocation of resources

Authority dominates when

– there are limited supply sources – there are high uncertainties – requirements are difficult to define – frequent recontracting occurs

slide-8
SLIDE 8

PPP CONFERENCE HK 2005 8

Control Mechanisms

Classical contracting

PPPs share features of both mechanisms, e.g.

– many supply alternatives/outlets – high uncertainties

Price and authority are woven together to control

PPP project transactions

– competitive tendering establishes the right price – authority mechanisms are written into contracts – e.g. contractual adjustment mechanisms, guarantees

slide-9
SLIDE 9

PPP CONFERENCE HK 2005 9

Control Mechanisms

Classical contracting

Manipulative incentive systems designed to discourage

  • pportunism and promote cooperation

e.g. liquidated and ascertained damages

Quality control systems & inspection arrangements

e.g. regulatory reviews

But these incentive/ sanctioning systems are themselves the

source of many disputes

focus teams on achieving incentives or avoiding punishments

High transaction costs

bidding costs, inspections and monitoring, renegotiations

Leading to adversarial relationships, a damaging industry

reputation, missed opportunities

slide-10
SLIDE 10

PPP CONFERENCE HK 2005 10

Control Mechanisms

Classical contracting

Incentives/ sanctions have limitations in

ensuring control and encouraging cooperation

But the public sector relies on these controls

– to demonstrate probity and accountability – to demonstrate value for money??

A need for cooperation & transaction cost

efficiency

– the role of trust

slide-11
SLIDE 11

PPP CONFERENCE HK 2005 11

Control Mechanisms

Trust Trust creates norms of obligation (i.e.

control)

– limiting behaviours, self-regulation

Trust leads to discretionary cooperation But trust begets trust, distrust begets

distrust

slide-12
SLIDE 12

PPP CONFERENCE HK 2005 12

Control Mechanisms

Trust

Trust is shaped by justice judgements

– fairness of decision making processes & procedures

experienced

– fairness of outcomes received – e.g. distribution of risks and rewards and contractual

adjustment procedures

Trust is dynamic

– always increasing or decreasing

Trust determines the value of guarantees and

comfort letters

slide-13
SLIDE 13

PPP CONFERENCE HK 2005 13

Control Mechanisms

Price, Authority and Trust

Relational Contracting (RC)

– uses formal (price & authority) and informal (trust)

mechanisms

Trust does not replace price and authority

– it complements them

When trust is high, there is less need of formal

mechanisms

– e.g. contracts can be more flexible; incomplete

RC principles underpin partnering and alliancing RC engenders proactive project delivery

– by fostering cooperation among team members with a

longer-term mindset (Figure 1)

slide-14
SLIDE 14

PPP CONFERENCE HK 2005 14

RC & PPPs

Role of RC in PPPs

Balancing Classical contracting Approaches (CAs) & Relational contracting Approaches (RAs) in PPPs

slide-15
SLIDE 15

PPP CONFERENCE HK 2005 15

RC & PPPs

RC in PPPs RC should not make PPP projects cosy

– contracts should be clear – must transfer significant performance risks

to the private sector

– perform better than the PSC – maximise the value capture to society

But there are many challenges

slide-16
SLIDE 16

PPP CONFERENCE HK 2005 16

RC & PPPs

RC in PPPs

Level of profits

– needs to be substantial to be passed on as lower

costs to end users

– but this may undermine public confidence in the

regulatory system

Renegotiations

– are common in PPPs – but can create the potential for opportunistic

behaviour by investors

slide-17
SLIDE 17

PPP CONFERENCE HK 2005 17

RC & PPPs

RC in PPPs

A comprehensive regulatory framework is

needed to demonstrate probity & accountability

– and value for money?

The need to maximise level of service to

society

All these require the exercise of discretion on

information-deficient matters

– and these decisions cannot be contracted out

There is therefore the need for BALANCE

slide-18
SLIDE 18

PPP CONFERENCE HK 2005 18

RC & PPPs

Balancing CAs & RAs in PPPs

Balance is required in decisions on

– e.g. risks transferred & governmental guarantees

provided

This balance should be dynamic

– e.g. to accommodate changing environmental

contingencies

Achieving this balance requires joint efforts

– trust & RC approaches Reviews of PPPs support this proposal

– successful PPPs point to the existence of these principles – PPP failures also point to the absence of these principles

slide-19
SLIDE 19

PPP CONFERENCE HK 2005 19

RC & Sustainable Infrastructure

Sustainability defined Sustainability Indicators An RC Driven Approach

slide-20
SLIDE 20

PPP CONFERENCE HK 2005 20

RC & Sustainable Infrastructure

Sustainability Defined

Sustainable Development

– the Brundtland Report 1987 – ‘development that meets the needs of the present

without compromising the ability of future generations to meet their own needs’

Sustainable infrastructure

– goes beyond green construction

slide-21
SLIDE 21

PPP CONFERENCE HK 2005 21

RC & Sustainable Infrastructure

Sustainability Indicators

Public Health & Safety

– including occupational health, safe working systems

Solid Waste Management

– recycling, safe disposal systems

Design

– innovation, flexibility, design-out waste,

Contractor & suppliers involvement

– durability & constructability

Resource utilisation, e.g.

– re-usability of moulds & formwork, prefabrication

slide-22
SLIDE 22

PPP CONFERENCE HK 2005 22

RC & Sustainable Infrastructure

An RC Driven Approach?

Inclusion of sustainability related clauses at contract

administration levels

Stakeholders sign up to a common sustainability

agenda

Trust building in RC relationships results in team

working

– underpins collaborative decision-making across project

interfaces

– results in innovation, efficiency, sustainable infrastructure

slide-23
SLIDE 23

PPP CONFERENCE HK 2005 23

Research Agenda

Assessment

Frameworks

Parallel Research

Thrusts

Support for Proposal

slide-24
SLIDE 24

PPP CONFERENCE HK 2005 24

Research Agenda

Assessment Frameworks

for Relational and Sustainability performance

– qualitative and quantitative assessments

These tools need to be

– client-, project- and country-specific

ICT-enabled frameworks and decision-

support tools

– to address the knowledge sharing & computational

dimensions

slide-25
SLIDE 25

PPP CONFERENCE HK 2005 25

Research Agenda

Parallel Research Thrusts

into RC & JRM

– e.g. an international survey on selecting potential

project partners for RC evaluated the importance

  • f 22 factors comprising 9 technical and 13

relational factors with interesting findings

into the Sustainability Assessment of projects

– e.g. a Hong Kong based postal questionnaire

survey identified key Sustainability Indicators again with interesting findings

These and other findings will contribute to the

proposed framework

slide-26
SLIDE 26

PPP CONFERENCE HK 2005 26

Research Agenda

Support for Proposal

Global Reporting Initiative (GRI)

– sustainability performance reported alongside

financial performance

Innovative selection methodologies

– involving mainly non-price, relational and

sustainability criteria

Assessment of performance on technical

criteria is now common, e.g.

– PASS in Hong Kong – CONQUAS in Singapore

slide-27
SLIDE 27

PPP CONFERENCE HK 2005 27

Research Agenda

Support for Proposal

Assessment of past performance focuses

attention

– on developing needed capacities – ensures selection of optimal PPP teams

An integrated framework

– incorporating relational, technical and

sustainability assessment is required

– is synergistic, consistent and reliable

Research is ongoing at CICID

slide-28
SLIDE 28

PPP CONFERENCE HK 2005 28

Concluding Remarks

PPPs can be valuable Success in them requires a good

balance of classical and relational contracting approaches

Achieving this balance is a major

challenge, but nonetheless, surmountable

This balance is dynamic

slide-29
SLIDE 29

PPP CONFERENCE HK 2005 29